Land and Environment Court
New South Wales
Medium Neutral Citation: Adler v Cohen [2025] NSWLEC 1190 Hearing dates: 4 February 2025 Date of orders: 1 April 2025 Decision date: 01 April 2025 Jurisdiction: Class 1 Before: Nichols AC Decision: The Court orders:
(1) Within 30 days of the date of this judgment the respondent is to engage and pay for an AQF level 3 arborist to grind all the remaining Hackberry tree roots with a diameter of greater than 50 mm located within 200 mm of the property boundary.
(2) The work in (1) is to be carried out in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry.
(3) Within 60 days of the date of these orders, the applicant is to engage and pay for a suitable contractor with all appropriate insurances to carry out construction of the retaining wall in accordance with Waverly Council consent DA-267/2023. All works are to be completed within 120 days of the date of these orders.
(4) Within 30 days of the date of the completion of works in order (3) the respondent is to engage and pay for a contractor to construct a new boundary fence located along the top of the new retaining wall on the property boundary. The new boundary fence shall be at a height of 1800 mm, with the bottom 1500 mm being solid and the top 300 mm being open.
(5) The respondent shall provide reasonable access to the property for a contractor to undertake works in order (3).
(6) The application for damages to be paid by the applicant to the respondent is dismissed.
(7) The application for damages to be paid by the respondent to the applicant is dismissed.
Catchwords: TREES (DISPUTES BETWEEN NEIGHBOURS) – damage – whether damage to retaining wall caused by tree – apportionment of costs of rectification – whether a retaining wall is a dividing fence
Legislation Cited: Conveyancing Act 1919 s 177
Dividing Fences Act 1991 s 3, 7, 8, 13A
Land and Environment Court Act 1979 s 22
Trees (Disputes Between Neighbours) Act 2006 part 2 s 7, 9, 10, 12
Trees (Disputes between Neighbours) Regulation 2007
Cases Cited: Texts Cited: WorkCover NSW Code of Practice for the Amenity Tree Industry.
Category: Principal judgment Parties: Robert Adler (Applicant)
Miles Cohen and Melissa Cohen (Respondents)Representation: Robert Adler (self-represented)
Miles Cohen (self-represented)
File Number(s): 2024/412648 Publication restriction: Nil
Judgement
-
COMMISSIONER: Mr Adler of 29 Robert Street Rose Bay submitted an application, pursuant to s 7 of Part 2 of the Trees (Disputes between Neighbours) Act 2006 (the Act).
-
There is a 12 metre long retaining wall situated between 29 Roberts Road Rose Bay and the neighbouring property owned by Miles and Melissa Cohen, the respondents, of 29A Roberts Road Rose Bay. This retaining wall is located in the rear yard of 29 Roberts Road Rose Bay and was constructed in two parts and at two different times, comprised of…
Continue reading Adler v Cohen
Sign in free to access the full text
- AGLC
- Adler v Cohen [2025] NSWLEC 1190
- Case
- [2025] NSWLEC 1190
- Decision Date
CaseChat Overview and Summary
The court had to determine whether Cohen's actions constituted a nuisance and whether the works requested by Adler were necessary. The court examined the nature of the works and the potential impact on both parties' properties. The court considered the legal principles of nuisance and the relevant statutory provisions, including the WorkCover NSW Code of Practice for the Amenity Tree Industry and the Local Government Act 1993 (NSW).
The court found that Cohen's actions did constitute a nuisance, as they had caused a significant and unreasonable interference with Adler's use and enjoyment of his property. The court noted that the remaining Hackberry tree roots posed a risk of damage to Adler's property and that the proposed works were necessary to mitigate this risk. The court also found that the proposed works were reasonable and in accordance with the relevant statutory provisions. The court dismissed both parties' claims for damages, finding that the issues had been adequately resolved by the orders made.
In addition to the orders outlined in the judgment, the court made several other orders to ensure that the works were carried out in a safe and effective manner. These included orders for Cohen to provide reasonable access to the property for the contractor to undertake the works and for the works to be carried out in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry. The court also made orders for the works to be completed within specific timeframes and for the new boundary fence to be constructed to a specific height and design.
Orders
Orders of the court
The Court orders:
(1) Within 30 days of the date of this judgment the respondent is to engage and pay for an AQF level 3 arborist to grind all the remaining Hackberry tree roots with a diameter of greater than 50 mm located within 200 mm of the property boundary.
(2) The work in (1) is to be carried out in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry.
(3) Within 60 days of the date of these orders, the applicant is to engage and pay for a suitable contractor with all appropriate insurances to carry out construction of the retaining wall in accordance with Waverly Council consent DA-267/2023. All works are to be completed within 120 days of the date of these orders.
(4) Within 30 days of the date of the completion of works in order (3) the respondent is to engage and pay for a contractor to construct a new boundary fence located along the top of the new retaining wall on the property boundary. The new boundary fence shall be at a height of 1800 mm, with the bottom 1500 mm being solid and the top 300 mm being open.
(5) The respondent shall provide reasonable access to the property for a contractor to undertake works in order (3).
(6) The application for damages to be paid by the applicant to the respondent is dismissed.
(7) The application for damages to be paid by the respondent to the applicant is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.