Acts Amendment (Mining and Petroleum) Act 1999 (WA)

Case
No judgment structure available for this case.

Western Australia

Acts Amendment (Mining and Petroleum)

Act 1999

No. 17 of 1999

An Act to amend the —

 Mining Act 1978;



Petroleum Act 1967; and



Petroleum (Submerged Lands) Act 1982,

and for related purposes.

[Assented to 15 June 1999]

The Parliament of Western Australia enacts as follows:

Acts Amendment (Mining and Petroleum) Act 1999

Part 1

Preliminary

s. 1

Part 1 Preliminary

1.             Short title

This Act may be cited as the Acts Amendment (Mining and

Petroleum) Act 1999.

2.             Commencement

The provisions of this Act come into operation on such day as is, or days as are respectively, fixed by proclamation.

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Mining Act 1978

Part 2

s. 3

Part 2 — Amendments to Mining Act 1978

3.             The Act amended

The amendments in this Part are to the Mining Act 1978*.

[* Reprinted as at 27 February 1996.

For subsequent amendments see 1997 Index to Legislation of

Western Australia, Table 1, pp. 156-7 and Acts Nos. 31 of

1997 and 10 of 1998.]

4.             Section 26 amended

(1)

Section 26(1)(d) is amended as follows:

(a)

by inserting after “Minister” —

, within such period as the Minister specifies in

writing,

”;

(b)

by deleting “in accordance with section 126”.

(2)

After section 26(1) the following subsection is inserted —

(1a)

A security referred to in subsection (1)(d) shall be in

accordance with and subject to section 126.

”.

5.             Section 49 amended

After section 49(2) the following subsections are inserted —

(3)

If, after an application is made under subsection (1) in respect of land the subject of a prospecting licence —

(a)

the holder of the licence transfers the licence; or

Acts Amendment (Mining and Petroleum) Act 1999

Part 2

Amendments to Mining Act 1978

s. 6

(b)

where there are 2 or more holders of the licence, a holder transfers the holder’s interest in the licence,

the application continues in the name of the transferee

of the licence or interest as if the transferee were the

applicant or one of the applicants, as the case requires.

(4)

For the purposes of subsection (3), where there are 2 or more transferees of the prospecting licence, each of the transferees is to be regarded as an applicant for an

interest in the relevant mining lease or general purpose

lease that corresponds to the interest held by that

transferee in the licence.

”.

6.             Section 52 amended and consequential amendments

(1)

After section 52(1) the following subsection is inserted —

(1a)

The Minister may require the holder of a prospecting

licence to lodge at the office of the mining registrar or

the Department at Perth, within such period as the

Minister specifies in writing, an additional security for

compliance with conditions imposed in relation to the

licence under section 46A.

”.

(2)

Section 52(2) is amended by inserting after “subsection (1)” —

“ or (1a) ”.

(3)

Section 92 is amended as follows:

(a)

by deleting “and 47” and inserting instead — “ , 47 and 52(1a) ”;

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Mining Act 1978

Part 2

s. 7

(b)

by deleting “an application for the grant of”;

(c)

by deleting “sections” and inserting instead — “ provisions ”.

(4)

Section 96(2) is amended as follows:

(a)

by deleting “or” after paragraph (b);

(b)

after paragraph (ba) by inserting —

(bb)

any requirement under section 52(1a) is not

complied with; or

”.

7.             Section 60 amended and consequential amendment

(1)

After section 60(1) the following subsection is inserted —

(1a)

The Minister may require the holder of an exploration licence to lodge at the office of the mining registrar or the Department at Perth, within such period as the

Minister specifies in writing, an additional security for compliance with conditions imposed in relation to the licence under section 63AA.

”.

(2)

Section 60(2) is amended by inserting after “subsection (1)” —

“ or (1a) ”.

(3)

After section 63A(a) the following paragraph is inserted —

(aa)

any requirement under section 60(1a) in relation to the exploration licence is not complied with;

”.

Acts Amendment (Mining and Petroleum) Act 1999

Part 2

Amendments to Mining Act 1978

s. 8

8.             Section 61 amended

After section 61(3) the following subsection is inserted —

(4)

If the holder of an exploration licence transfers the

licence after making an application for the extension of

the term of the licence under subsection (2), the

application continues in the name of the transferee of

the licence as if the transferee had made it.

”.

9.             Section 67 amended

After section 67(2) the following subsections are inserted —

(3)

If, after an application is made under subsection (1) in respect of land the subject of an exploration licence —

(a)

the holder of the licence transfers the licence; or

(b)

where there are 2 or more holders of the licence, a holder transfers the holder’s interest in the licence,

the application continues in the name of the transferee

of the licence or interest as if the transferee were the

applicant or one of the applicants, as the case requires.

(4)

For the purposes of subsection (3), where there are 2 or more transferees of the exploration licence, each of the transferees is to be regarded as an applicant for an

interest in the relevant mining lease or general purpose

lease that corresponds to the interest held by that

transferee in the licence.

”.

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Mining Act 1978

Part 2

s. 10

10.           Section 70C amended

After section 70C(6) the following subsections are inserted —

(7)

If, after an application is made under subsection (1) in

respect of land the subject of a primary tenement —

(a)

the holder of the tenement transfers the tenement; or

(b)

where there are 2 or more holders of the tenement, a holder transfers the holder’s interest in the tenement,

the application continues in the name of the transferee of the tenement or interest as if the transferee were the applicant or one of the applicants, as the case requires.

(8)

For the purposes of subsection (7), where there are 2 or

more transferees of the primary tenement, each of the

transferees is to be regarded as an applicant for an

interest in the relevant retention licence that

corresponds to the interest held by that transferee in the

primary tenement.

”.

11.           Section 70E amended

(1)

Section 70E(3) is amended by deleting “Where an application for the renewal of a retention licence is made by the holder of the licence” and inserting instead —

“ If an application for renewal is made under this section ”.

Acts Amendment (Mining and Petroleum) Act 1999

Part 2

Amendments to Mining Act 1978

s.

12

(2)

After section 70E(3) the following subsection is inserted —

(4)

If the holder of a retention licence transfers the licence

after making an application for renewal under this

section, the application continues in the name of the

transferee of the licence as if the transferee had made

it.

”.

12.           Section 70IA inserted and consequential amendments

(1)

After section 70I the following section is inserted —

70IA.

Programme of work

(1)

On the granting of a retention licence, or at any

subsequent time, the Minister may impose on the

holder of the licence a condition requiring the holder to

comply with a specified programme of work in respect

of the land the subject of the licence within a specified

period.

(2)

Before imposing a condition under subsection (1), the

Minister may require the applicant for the licence or

the holder of the licence, as the case requires, to submit

to the Minister a draft programme of work in a form

approved by the Minister and the applicant or the

holder, as the case requires, shall comply with that

requirement.

(3)

Subsections (2) and (3) of section 70I apply to a

condition imposed under subsection (1) as if it were a

condition imposed under that section.

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Mining Act 1978

Part 2

s. 13

(4)

In subsection (1) —

“specified” means specified in writing by the Minister.

”.

(2)

Section 70H(1)(c) is deleted.

(3)

Section 70H(2) is amended by deleting paragraph (a) and the

“or” after that paragraph.

(4)

Section 70K(b)(ii) is amended by inserting after “70I” —

“ or 70IA ”.

(5)

Section 70L(1)(b) is deleted and the following paragraph is

inserted instead —

(b)

subject to satisfactory compliance with any conditions imposed under section 70I or 70IA;

”.

13.           Section 70L amended

After section 70L(2) the following subsections are inserted —

(3)

If, after an application is made under subsection (1) in

respect of land the subject of a retention licence —

(a)

the holder of the licence transfers the licence; or

(b)

where there are 2 or more holders of the licence, a holder transfers the holder’s interest in the licence,

the application continues in the name of the transferee

of the licence or interest as if the transferee were the

applicant or one of the applicants, as the case requires.

Acts Amendment (Mining and Petroleum) Act 1999

Part 2

Amendments to Mining Act 1978

s. 14

(4)

For the purposes of subsection (3), where there are 2 or

more transferees of the retention licence, each of the

transferees is to be regarded as an applicant for an

interest in the relevant mining lease or general purpose

lease that corresponds to the interest held by that

transferee in the licence.

”.

14.           Section 78 amended

(1)

Section 78(3) is amended by deleting “Where an application for the renewal of a mining lease is made by the holder of the lease” and inserting instead —

“ If an application for renewal is made under this section ”.

(2)

After section 78(3) the following subsection is inserted —

(4)

If, after an application for renewal is made under this

section —

(a)

the holder of the mining lease transfers the lease; or

(b)

where there are 2 or more holders of the mining lease, a holder transfers the holder’s interest in the lease,

the application continues in the name of the transferee

of the lease or interest as if the transferee were an

applicant or one of the applicants, as the case requires.

”.

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Mining Act 1978

Part 2

s. 15

15.           Section 84A inserted and consequential amendment

(1)

After section 84 the following section is inserted —

84A.

Security relating to mining lease

(1)

The Minister may require the holder of a mining lease

to lodge at the office of the mining registrar or the

Department at Perth, within such period as the Minister

specifies in writing, a security for compliance with

conditions imposed in relation to the lease under

section 84.

(2)

A security referred to in subsection (1) shall be in

accordance with and subject to section 126.

”.

(2)

Section 82(1)(g) is amended by inserting after “the lease” in the

second place where it occurs the following —

, if he fails to comply with any requirement under

section 84A(1) in relation to the lease

”.

16.           Section 86 amended

(1)

Section 86(3) is amended by inserting after “10 hectares” —

, unless the Minister is satisfied that a larger area of

land is required for the purposes of the lease,

”.

Acts Amendment (Mining and Petroleum) Act 1999

Part 2

Amendments to Mining Act 1978

s.

17

(2)

After section 86(4) the following subsection is inserted —

(5)

An application for the grant of a general purpose lease in respect of an area of land which exceeds 10 hectares shall be accompanied by a statement specifying the

reasons why such an area of land is required for the

purposes of the lease.

”.

17.           Section 88 amended

(1)

Section 88(2) is repealed and the following subsection is

inserted instead —

(2)

Notwithstanding subsection (1), on receipt of an

application made in the prescribed manner during the

final year of the term of the lease, the Minister —

(a)

shall renew the term of the lease as to the whole of the land the subject of the lease —

(i) for one further period of 21 years; and

(ii) on the terms and conditions to which the lease was subject before its renewal;

and

(b)

may, in the case of a lease renewed under paragraph (a), renew or further renew the term of the lease as to the whole or any part of the land the subject of the lease —

(i) for a period not exceeding 21 years; and

(ii) on such terms and conditions as the Minister thinks fit.

”.

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Mining Act 1978

Part 2

s. 18

(2)

After section 88(3) the following subsection is inserted —

(4)

If, after an application for renewal is made under this

section —

(a)

the holder of the general purpose lease transfers the lease; or

(b)

where there are 2 or more holders of the general purpose lease, a holder transfers the holder’s interest in the lease,

the application continues in the name of the transferee

of the lease or interest as if the transferee were an

applicant or one of the applicants, as the case requires.

”.

18.           Section 90 amended

Section 90 is amended by inserting after “84,” —

“ 84A, ”.

19.           Section 126 amended

(1)

Section 126(1) is amended as follows:

(a)

by deleting “or 70F” and inserting instead — “ , 70F or 84A; ”;

(b)

by deleting paragraphs (a), (b) and (c) and inserting instead —

(a)

shall be for such amount —

(i) in the case of a security referred to in section 26, 52(1a), 60(1a), 70F or 84A, as the Minister in a particular case

Acts Amendment (Mining and Petroleum) Act 1999

Part 2

Amendments to Mining Act 1978

s. 19

approves (including any variation of

that amount under subsection (1a)); or

(ii) in the case of a security referred to in section 52(1) or 60(1), as is prescribed or as the Minister in a particular case approves;

(b)

shall be in the prescribed form or such other form as the Minister in a particular case approves; and

(c)

may, subject to the approval of the Minister, be by bond or such other method as the Minister allows, or be partly by bond and partly by such other method as the Minister allows.

”.

(2)

After section 126(1) the following subsection is inserted —

(1a)

The Minister may by instrument in writing vary an

amount approved under subsection (1)(a)(i).

”.

(3)

Section 126(7) is repealed and the following subsection is

inserted instead —

(7)

The Minister may discharge, in whole or in part, a

security given under this section —

(a)

on receipt of an application in writing by the person subscribing to the security accompanied by evidence satisfactory to the Minister showing cause why the security should be discharged; or

(b)

on the Minister’s own initiative, if the Minister considers it appropriate to do so.

”.

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Petroleum Act 1967

Part 3

s. 20

Part 3 — Amendments to Petroleum Act 1967

20.           The Act amended

The amendments in this Part are to the Petroleum Act 1967*.

[* Reprinted as at 17 December 1992.

For subsequent amendments see 1997 Index to Legislation of

Western Australia, Table 1, p. 177 and Act No. 31 of 1997.]

21.           Section 5 amended

Section 5(1) is amended in the definition of “Crown land” as follows:

(a)

by deleting paragraph (a);

(b)

by deleting paragraph (d) and inserting instead —

(d)

any land reserved, declared or otherwise dedicated under the Land Administration Act 1997 or any other written law;

”;

(c)

in paragraph (e) by inserting before “State” — “ without limiting paragraph (d), ”;

(d)

by deleting paragraphs (f) and (g).

22.           Section 15 amended and consequential amendments

(1)

Section 15(1) is amended by inserting after “Subject to this

Act” —

“ and to any condition referred to in section 91B(2) ”.

(2)

Section 15(2), (3) and (4) are repealed.

(3)

Section 28A(2) is repealed.

(4)

Section 152 is repealed.

Acts Amendment (Mining and Petroleum) Act 1999

Part 3

Amendments to Petroleum Act 1967

s. 23

23.           Section 15A inserted and saving provision

(1)

After section 15 the following section is inserted —

15A.

Consent of Minister required for entry on reserves

for purposes of exploration, etc.

(1)

A permittee, holder of a drilling reservation, access authority or special prospecting authority, lessee or licensee shall not enter upon any land that is —

(a)

comprised in the permit, drilling reservation, lease or licence of which he is the holder; and

(b)

reserved, declared or otherwise dedicated under the Land Administration Act 1997 or any other written law,

for the purpose of —

(c)

exploring for petroleum; or

(d)

carrying out operations for the recovery of petroleum,

unless the consent in writing of the Minister has been

first obtained.

(2)

Consent may be given for the purposes of

subsection (1) subject to the inclusion in the permit,

drilling reservation, access authority, special

prospecting authority, lease or licence of such

conditions as the Minister thinks fit and specifies in the

consent.

(3)

Before giving consent for the purposes of

subsection (1), the Minister shall consult with the

responsible Minister and obtain that Minister’s

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Petroleum Act 1967

Part 3

s. 23

recommendations on the conditions, if any, which

should be included in the permit, drilling reservation,

access authority, special prospecting authority, lease or

licence.

(4)

Without limiting subsection (2), the Minister may

specify in the consent conditions for the purpose of

ensuring, so far as is practicable, that any operations

carried out on the land under the authority of the

permit, drilling reservation, access authority, special

prospecting authority, lease or licence are carried out in

such a manner as to minimize the risk of damage to any

native fauna or flora on the land.

(5)

The responsible Minister for the purposes of

subsection (3) is the Minister responsible for the

administration of the land or the written law under

which the land is reserved, declared or dedicated, and if

any question arises as to who is the responsible

Minister under subsection (3), the question is to be

determined by the Governor whose decision is final.

(6)

Nothing in this section limits or otherwise affects the

operation of sections 13A(3) and 13B(9) of the

Conservation and Land Management Act 1984.

”.

(2)

Section 15A as inserted into the Petroleum Act 1967 by

subsection (1) does not prohibit operations being carried out

under the authority of —

(a)

a relevant licence on land that immediately before the commencement of section 22 was declared under section 15(2) of that Act to be Crown land and land to which that Act applied; or

(b)

the Barrow Island lease.

Acts Amendment (Mining and Petroleum) Act 1999

Part 3

Amendments to Petroleum Act 1967

s.

24

(3)

In subsection (2) —

“Barrow Island lease” has the meaning given in section 128 of

the Petroleum Act 1967;

“relevant licence” means a production licence for petroleum in force under Part III of the Petroleum Act 1967 immediately before the commencement of this section.

24.           Section 16 amended

Section 16(1) is repealed and the following subsections are inserted instead —

(1)

A permittee, holder of a drilling reservation, access authority or special prospecting authority, lessee or licensee shall not enter upon any land to which this section applies for the purpose of —

(a)

exploring for petroleum; or

(b)

carrying out operations for the recovery of petroleum,

unless the consent in writing of the owner or trustees, as the case may be, of the land has been first obtained.

(1a)

This section applies to land that is comprised in the permit, drilling reservation, access authority, special prospecting authority, lease or licence and is —

(a)

private land not exceeding 2 000 square metres in extent;

(b)

used as a cemetery or burial place; or

(c)

less than 150 metres in lateral distance from any cemetery or burial place, reservoir or any substantial improvement.

”.

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Petroleum Act 1967

Part 3

s. 25

25.           Section 43E amended

Section 43E(2) is amended by deleting “a period of 12 months” and inserting instead —

such period, not exceeding 3 years, as is specified by

the Minister

”.

26.           Section 43F amended and transitional provision

(1)

Section 43F(2) is amended by deleting “that is satisfactory”.

(2)

After section 43F(2) the following subsection is inserted —

(2a)

An extension of the period for which a drilling

reservation is effective shall not be granted if that

period has previously been extended under this section.

”.

(3)

Section 43F(3)(a) is deleted.

(4)

Section 43F(5) is repealed and the following subsection is

inserted instead —

(5)

Subject to subsections (2) and (2a), where —

(a)

an application has been made under subsection (1); and

(b)

the conditions to which the drilling reservation is, or has from time to time been, subject, and the provisions of this Part and the regulations, have been complied with,

the Minister shall grant an extension of a drilling

reservation for a period of 12 months commencing

Acts Amendment (Mining and Petroleum) Act 1999

Part 3

Amendments to Petroleum Act 1967

s. 27

from the expiration of the period for which the drilling

reservation is effective.

”.

(5)

Despite the amendments made by this section, section 43F of

the Petroleum Act 1967 continues to apply to and in relation to

the extension of a drilling reservation in force on the

commencement of this section.

27.           Section 91B inserted

After section 91A the following section is inserted —

91B.

Conditions prohibiting entry on certain land

(1)

In this section —

“holder” means the holder of the permit, drilling

reservation, lease or licence.

(2)

The conditions subject to which a permit, drilling

reservation, lease or licence is granted may include a

condition prohibiting the holder from entering

specified land within the permit area, drilling

reservation, lease area or licence area.

(3)

The Minister may, at any time, by instrument in writing

served on the holder, vary or revoke a condition

referred to in subsection (2).

”.

Acts Amendment (Mining and Petroleum) Act 1999

Amendments to Petroleum (Submerged Lands) Act 1982

Part 4

s. 28

Part 4 — Amendments to Petroleum (Submerged

Lands) Act 1982

28.           The Act amended

The amendments in this Part are to the Petroleum (Submerged

Lands) Act 1982*.

[* Reprinted as at 24 March 1992.

For subsequent amendments see 1997 Index to Legislation of

Western Australia, Table 1, p. 178.]

29.           Section 124 amended

Section 124 is amended as follows:

(a)

after paragraph (c) by deleting “or”;

(b)

after paragraph (d) by deleting the comma and inserting —

; or

(e)

the enjoyment of native title rights and interests Act 1993 of the Commonwealth),

”.

30.           Section 127 replaced

Section 127 is repealed and the following section is inserted instead —

127.         Property in petroleum

Subject to this Act, if petroleum is recovered by a permittee, lessee or licensee in the permit area, lease area or licence area —

(a)

the petroleum becomes the property of the permittee, lessee or licensee; and

Acts Amendment (Mining and Petroleum) Act 1999

Part 4

Amendments to Petroleum (Submerged Lands) Act 1982

s. 30

(b)

it is not subject to any rights of other persons (other than any person to whom the permittee, lessee or licensee transfers, assigns or otherwise disposes of the petroleum or an interest in the petroleum).

”.

By Authority: JOHN A. STRIJK, Government Printer

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

0