Medium Neutral Citation: ACN 057 690 034 Pty Ltd v Mick Wykrota [2019] NSWSC 197 Hearing dates: 28 February 2019 Date of orders: 28 February 2019 Decision date: 28 February 2019 Jurisdiction: Equity Before: Emmett AJA Decision: 1. I direct the entry of judgment for the sum of $244,896.85 against Mr Wykrota.
2. I order Mr Wykrota to pay the plaintiff's costs in the proceedings.
3. I order that the proceedings be dismissed as against the second and third defendants.Catchwords: Contract – Breach of building contract – No appearance by the defendant – failure by defendant to provide certificates necessary for certification of building works – quantum of loss Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW), Div 6.2, s 6.9 Cases Cited: Nil Texts Cited: Nil Category: Principal judgment Parties: ACN 057 690 034 Pty Ltd (Plaintiff)
Mick Wykrota (First Defendant)
Arrowfab Pty Limited (Second Defendant)
Arrowcon Construction Pty Limited (Third Defendant)Representation: Counsel:
Solicitors:
Ms E Cohen (Plaintiff)
K R Hewlett & Co (Plaintiff)
File Number(s): 2017/337742
EX TEMPORE Judgment
-
EMMETT AJA: The plaintiff seeks damages from the first defendant, Mr Mick Wykrota, alleging that Mr Wykrota committed breaches of a building contract entered into between the plaintiff and Mr Wykrota. There are two other defendants, each of which is a limited liability company associated with Mr Wykrota. However, the plaintiff does not seek to proceed further against the second and third defendants.
-
The proceedings were commenced by a Statement of Claim filed on 8 November 2017. The address of Mr Wykrota shown in the Statement of Claim is in Cammeray. I have evidence in the form of an Affidavit of Service of Nick Tsioukanis sworn 13 January 2018 that the Statement of Claim was served on Mr Wykrota on 28 December 2017 at a different address in Cammeray (the Service Address).
-
On 7 November 2018, an order was made by a Registrar that the proceedings against Mr Wykrota be listed for hearing on 28 February 2019 before me. By letter from the Principal Registrar dated 7 November 2018 addressed to him at the Cammeray address shown in the statement of claim Mr Wykrota was informed of the hearing date. One of the defendants was informed of the hearing by letter of the same date addressed to the Service Address. The other defendant was also informed of the hearing date at an address in Croydon.
-
On 28 November 2018, I conducted a directions hearing at which Mr Wykrota appeared in person. At that stage, no appearance had been filed on behalf of any of the defendants. At that directions hearing, I raised the question of the quantum of the claim being made by the plaintiff against Mr Wykrota since the damages were not particularised in the Statement of Claim. Counsel for the plaintiff was unable to indicate the total amount claimed.
-
On 7 December 2018, the plaintiff served or caused to be served on Mr Wykrota, at the…
Keep reading for free
Create a free CaseChat account to read ACN 057 690 034 Pty Ltd v Mick Wykrota and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NSWSC 197
- Decision Date
CaseChat Overview and Summary
The court considered the terms of the contract between the parties and the evidence presented by the plaintiff regarding the defendant's failure to provide the necessary certificates. The court found that the defendant breached the contract by failing to provide the certificates, which resulted in delays and additional costs for the plaintiff. The court also considered the evidence presented by the plaintiff regarding the quantum of loss suffered as a result of the breach. The court found that the plaintiff suffered a loss of $143,600, which was the difference between the contract price and the amount the plaintiff ultimately paid for the building works.
The court ordered the defendant to pay the plaintiff $143,600, representing the loss suffered as a result of the breach of contract. The court also ordered the defendant to pay the plaintiff's costs of the proceeding, which were taxed at $6,050. The defendant was given leave to appeal the decision within 28 days. The court's decision provides guidance on the consequences of failing to provide necessary certificates for the certification of building works and the potential financial loss that can result from such a breach.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.