Acer Forester Pty Ltd v Complete Crane Hire (NT) Pty Ltd & Ors [2013] NTSC 62
PARTIES:Acer Forester Pty Ltd
(ACN 081 108 868)
v
Complete Crane Hire (NT) Pty Ltd
(ACN 086 562 674)
and
SUTHERLAND, Bart Kenneth
and
A & K (NT) Pty Ltd
(ACN 109 540 150)
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT OF THE TERRITORY EXERCISING TERRITORY JURISDICTION
FILE NO:119 of 2011 (21132442)
DELIVERED: 4 OCTOBER 2013
HEARING DATES: 13 AUGUST 2013
JUDGMENT OF: KELLY J
REPRESENTATION:
Counsel:
Plaintiff:L McCrimmon
Defendants:A Young
Solicitors:
Plaintiff:David Francis & Associates
Defendants:Minter Ellison
Judgment category classification: C
Judgment ID Number: KEL13015
Number of pages: 23
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINAcer Forester Pty Ltd v Complete Crane Hire (NT) Pty Ltd & Ors [2013] NTSC 62
No. 119 of 2011 (21132442)
BETWEEN:
ACER FORESTER PTY LTD
(ACN 081 108 868)
Plaintiff
AND:
COMPLETE CRANE HIRE (NT) PTY LTD (ACN 086 562 674)
Third Defendant
AND:
BART KENNETH SUTHERLAND
Fourth Defendant
AND:
A & K (NT) PTY LTD
(ACN 109 540 150)
Fifth Defendant
CORAM: KELLY J
REASONS FOR JUDGMENT
(Delivered 4 October 2013)
The proceeding
In this proceeding, the plaintiff claimed damages in negligence against the third, fourth and fifth defendants (“the defendants”) for financial loss said to have been caused by disruption to the plaintiff’s business as a result of a crane collapsing onto the roof of the plaintiff’s business premises.
The plaintiff claimed that its business was disrupted by repairs to the roof, that that disruption caused a delay of 3½ months to a major project (the DHA project) which resulted in delays in receipt of payment for that project, and the loss of opportunities to earn income from other work during the period of the delay. The plaintiff also claimed re-imbursement of the cost of providing psychological counselling to staff members following the accident and of a payment made to a consultant on account of time lost during repairs. Those were minor matters and were admitted by the defendants. The major claim was the claim for loss of opportunity to earn income from other work as a result of the alleged delays to the DHA project.
The defendants admitted liability shortly before trial and the matter proceeded as an assessment of damages.
On 30 July 2013, I gave judgment for the plaintiff on the claim for:
(a)re-imbursement of an amount spent by the plaintiff in providing psychological counselling to staff members following the accident;
(b)re-imbursement of the payment made to a consultant on account of time lost during repairs;
(c)damages for a delay of eight days in receiving payment for the DHA project; and
(d)interest at a commercial rate on the above amounts.
In doing so I made a finding that except for a period of eight days, the plaintiff had not satisfied the onus of proving that the delay to the DHA project was caused by disruption to the business as a result…
Keep reading for free
Create a free CaseChat account to read Acer Forester Pty Ltd v Complete Crane Hire (NT) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2013] NTSC 62
- Decision Date
CaseChat Overview and Summary
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi