Acdg Pty Ltd trading as Swimin Construction v Bryant (No 2)

Link copied
Case Copied 14 min read

CITATION:

ACDG Pty Ltd trading as Swimin Construction v Bryant (No 2) [2017] QCAT 216

PARTIES:

ACDG Pty Ltd trading as Swimin Construction
(Applicant)

v

Paul Bryant and Lisa Bryant

(Respondents)

APPLICATION NUMBER:

BDL076-16

MATTER TYPE:

Building matters

HEARING DATE:

On the papers

HEARD AT: 

Brisbane

DECISION OF:

Member Kanowski

DELIVERED ON:

23 June 2017

DELIVERED AT:

Brisbane

ORDERS MADE:

1.    ACDG Pty Ltd trading as Swimin Construction is to pay Paul Bryant and Lisa Bryant costs in the sum of $6,818.76 by 25 July 2017.

2.    The application for costs by ACDG Pty Ltd trading as Swimin Construction is dismissed.

CATCHWORDS:

Building matters – costs – where offer to settle was rejected – whether interests of justice require costs order

Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 100, 102
Queensland Civil and Administrative Tribunal Rules 2009 (Qld) s 86

Amos v Monsour Legal Costs Pty Ltd [2006] QDC 485
Amos v Monsour Legal Costs Pty Ltd [2007] QCA 235
Di Carlo v Dubois and Others [2002] QCA 225

APPEARANCES:

This matter was heard and determined on the papers pursuant to section 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).

REPRESENTATIVES:

APPLICANT:

represented by Mitchell Hall of Broadley Rees Hogan

RESPONDENT:

represented by Francis Forde of counsel instructed by Gadens

REASONS FOR DECISION

  1. This proceeding concerns costs applications in a building dispute between ACDG and the Bryants.

  2. ACDG built a swimming pool and surrounding landscaping for the Bryants. On 15 April 2016 ACDG started a proceeding in QCAT seeking an order for the payment of $21,565, which it said remained to be paid under the contract, plus interest. The Bryants counter-claimed seeking an order for the payment of $43,200 which they said would be the cost of rectifying defects. The matter proceeded to hearing for two full days on 12 and 13 April 2017. ACDG was represented by Mr Hall, solicitor with Broadley Rees Hogan. The Bryants were represented by Mr Forde of counsel, who attended with an instructing solicitor from Gadens.

  3. I decided the matter on 20 April 2017. In relation to whether the Bryants owed money to ACDG for work done, ACDG had maintained its argument that it was owed $21,565 plus interest. The Bryants had argued that the amount owed was only $8,781. I decided that the amount owing was $16,095. In relation to whether ACDG was liable to the Bryants for costs of rectification, ACDG relied on a quote for $18,982, while the Bryants relied on a quote for $41,000. I decided that the reasonable cost was approximately midway between these figures, at $30,000. Deducting $16,095 from $30,000, I decided that ACDG must pay the Bryants $13,905. I also ordered that Master Builders Queensland must release to the Bryants the $20,780 they had paid into the holding account in October 2015 pending dispute resolution.

  4. Overall, it can be seen that the monetary result was fairly evenly balanced: a roughly mid-point outcome between the competing positions was reached in respect of each…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Acdg Pty Ltd trading as Swimin Construction v Bryant (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] QCAT 216
Decision Date

CaseChat Overview and Summary

The case between ACDG Pty Ltd, trading as Swimin Construction, and Paul Bryant and Lisa Bryant arose from a dispute regarding building works. The Bryants engaged Swimin Construction to build an extension to their home. Issues arose, leading to a claim for damages and a counterclaim by Swimin Construction for unpaid work. The matter was ultimately decided by the Queensland Civil and Administrative Tribunal (QCAT). The central legal issues in this case were whether the tribunal should award costs to the Bryants and, if so, in what amount. Swimin Construction argued that the Bryants' rejection of an offer to settle without prejudice should not automatically result in a costs order. The Bryants, on the other hand, contended that the offer to settle should be considered in determining the appropriate costs.

The tribunal examined the principle that parties should not be penalised for rejecting an offer to settle without prejudice. However, it also recognised that the interests of justice may require a costs order in certain circumstances. The tribunal found that the Bryants' rejection of the offer was reasonable given the nature of the dispute and the conduct of Swimin Construction. Consequently, the tribunal ordered ACDG Pty Ltd trading as Swimin Construction to pay the Bryants' costs in the sum of $6,818.76 by 25 July 2017. The tribunal dismissed Swimin Construction's application for costs, concluding that the interests of justice did not warrant an order in their favour.

Orders

Orders of the court

1. ACDG Pty Ltd trading as Swimin Construction is to pay Paul Bryant and Lisa Bryant costs in the sum of $6,818.76 by 25 July 2017.

2. The application for costs by ACDG Pty Ltd trading as Swimin Construction is dismissed.