Acciona Industrial Australia Pty Ltd v Kwinana WTE Project Co Pty Ltd

Link copied
Case Copied 84 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CIVIL

CITATION:   ACCIONA INDUSTRIAL AUSTRALIA PTY LTD -v- KWINANA WTE PROJECT CO PTY LTD [2022] WASC 380

CORAM:   SOLOMON J

HEARD:   22 & 23 JUNE 2022

DELIVERED          :   11 NOVEMBER 2022

PUBLISHED           :   14 NOVEMBER 2022

FILE NO/S:   CIV 2309 of 2021

BETWEEN:   ACCIONA INDUSTRIAL AUSTRALIA PTY LTD

First Plaintiff

ACCIONA CONSTRUCTION AUSTRALIA PTY LTD

Second Plaintiff

JOHN BEEVER (AUST.) PTY LTD

Third Plaintiff

AND

KWINANA WTE PROJECT CO PTY LTD

First Defendant

BTA INSTITUTIONAL SERVICES AUSTRALIA LTD

Second Defendant


Catchwords:

Application for declaratory relief – Construction issue – Definition of force majeure event – Whether COVID-19 a force majeure event – Whether issue too hypothetical – Whether relief will quell controversy between parties

Legislation:

Biosecurity Act 2015 (Cth)
Competition and Consumer Act 2010 (Cth), sch 2 ('Australian Consumer Law'), s 18
Emergency Management Act 2005 (WA)
Jurisdiction of Courts (Cross-vesting) Act 1987 (Cth), s 5(2)
Native Title Act 1993 (Cth)
Rules of the Supreme Court 1971 (WA), O 18 r 16
Supreme Court Act 1935 (WA), s 24(7), s 25(6)

Result:

Application dismissed
Declarations not granted

Category:    B

Representation:

Counsel:

First Plaintiff : JC Giles SC & R Young
Second Plaintiff : JC Giles SC & R Young
Third Plaintiff : JC Giles SC & R Young
First Defendant : B W Walker SC & T Boyle
Second Defendant : No appearance

Solicitors:

First Plaintiff : Corrs Chambers Westgarth
Second Plaintiff : Corrs Chambers Westgarth
Third Plaintiff : Corrs Chambers Westgarth
First Defendant : King & Wood Mallesons
Second Defendant : MinterEllison

Case(s) referred to in decision(s):

Ainsworth v Criminal Justice Commission [1992] HCA 10; 175 CLR 564

Aussie Airlines Pty Ltd v Australian Airlines Ltd [1996] FCA 813; (1996) 68 FCR 406

Bass v Permanent Trustee Company Ltd [1999] HCA 9; (1999) 198 CLR 334

Edwards v Santos Ltd [2011] HCA 8; (2011) 242 CLR 421

Forster v Jododex [1972] HCA 61; (1972) 127 CLR 421

Hobart International Airport Pty Ltd v Clarence City Council [2022] HCA 5; (2022) 399 ALR 214

Mine Trades and Maintenance-Electrical Pty Ltd v Freo [2012] WASC 78

Mineralogy Pty Ltd v Sino Iron Pty Ltd [2013] WASC 194 (S)

National Australia Bank Ltd v Nautilus Insurance Pte Ltd (No 2) [2019] FCA 1543; 377 ALR 627

Sanderson Computers Pty Ltd v Urica Library Systems BV (1998) 44 NSWLR 73

The Commonwealth v Sterling Nicholas Duty Free Pty Ltd [1972] HCA 19; (1972) 126 CLR 297

SOLOMON J:

Overview

  1. The first defendant, whom I shall refer to as Project Co, is developing a substantial thermal treatment plant to produce energy from waste, in the industrial suburb of Kwinana, Western Australia.  It is anticipated that the plant will process some 400,000 tonnes of waste annually and produce approximately 36MW of power to the grid.  The project is plainly a sophisticated and very substantial enterprise.

  2. By a written contract dated 16 October 2018 (EPC Contract), Project Co entered…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Acciona Industrial Australia Pty Ltd v Kwinana WTE Project C... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] WASC 380
Decision Date

CaseChat Overview and Summary

In the matter of Acciona Industrial Australia Pty Ltd v Kwinana WTE Project Co Pty Ltd, the parties were embroiled in a dispute over whether COVID-19 could be considered a force majeure event under their contractual agreement, and if so, whether the court should provide a declaratory judgment on the matter. The case was heard in the Supreme Court of Western Australia, where the primary legal issue was whether the court should grant a declaratory judgment on the hypothetical question of whether COVID-19 constituted a force majeure event under the contract. The applicant, Acciona, sought a declaration that COVID-19 was a force majeure event, which would entitle it to an extension of time and relief from certain obligations. The respondent, Project Co, objected to the declaratory judgment on the grounds that the question was hypothetical and would not resolve the controversy between the parties.

The court considered the statutory provisions that allowed it to grant a declaratory judgment, specifically Order 18 r 16 of the Rules of the Supreme Court 1971 (WA) and Section 24(7) of the Supreme Court Act. The court acknowledged that it had the power to grant a declaratory judgment but needed to exercise its discretion in a manner that was just and responsible. The court examined the relevant case law, including Forster v Jododex, where Gibbs J outlined the broad discretion given to the court in making a declaration, and the principles that should guide the exercise of that discretion. The court noted that while the power to grant a declaration was wide, it should not be exercised lightly and only when there were circumstances that called for it.

In reaching its decision, the court considered the arguments presented by both parties and the potential impact of a declaratory judgment on the ongoing dispute. The court concluded that the question of whether COVID-19 was a force majeure event was hypothetical and would not resolve the controversy between the parties. The court found that the declaratory judgment would not quell the controversy and would leave substantial aspects of the dispute unresolved. The court therefore exercised its discretion not to grant the declaratory judgment sought by Acciona.

The court's decision was based on the principle that the power to grant a declaration should be exercised with a proper sense of responsibility and a full realisation that judicial pronouncements ought not to be issued unless there are circumstances that call for their making. The court found that the circumstances in this case did not warrant the exercise of its discretion to grant a declaratory judgment. The court's decision was a careful consideration of the statutory provisions, relevant case law, and the specific facts of the case. The court's decision not to grant the declaratory judgment sought by Acciona was based on its assessment that the question was hypothetical and would not resolve the controversy between the parties. The court's decision was a balanced and responsible exercise of its discretion in the context of a complex and evolving legal issue.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Order 18 r 16 of the Rules of the Supreme Court 1971 (WA) provides, in materially identical terms:Declaratory judgment No action or other proceeding shall be open to objection on the ground that a merely declaratory judgment or order is sought, and the Court may make binding declarations of right whether or not any consequential relief is or could be claimed. Section 24(7) of the Supreme Court Act provides:The Court, in the exercise of the jurisdiction vested in it by this Act, in every cause or matter pending before it, shall have power to grant, and shall grant, either absolutely or on such reasonable terms and conditions as shall seem just, all such remedies whatsoever as any of the parties thereto may appear to be entitled to in respect of any and every legal or equitable claim properly brought forward by them in such cause or matter; so that, as far as possible, all matters so in controversy between the parties may be completely and finally determined, and all multiplicity of legal proceedings concerning any of such matters avoided. Notwithstanding the terms of s 24(7), it is tolerably clear that no objection can be advanced by Project Co (nor is it) that this court cannot, that is, does not have the power to grant the declaratory judgment sought because it will not be accompanied by consequential relief. Rather, Project Co objects to the declaratory judgment because the question it addresses is hypothetical in the sense that it will not resolve the controversy between the parties, and indeed, will leave very substantial aspects of the controversy yet to be resolved. Project Co accepts that this is not an issue of the court's power; the court has the relevant power. Rather, the issue is the proper exercise of the court's discretion to grant declaratory relief in the circumstances. Many cases have grappled with the nature of the discretion and its exercise in various circumstances. The equivalent legislative provision in New South Wales was considered by the High Court in Forster v Jododex, where Gibbs J said:The jurisdiction to make a declaration is a very wide one. Indeed, it has been said that, 'under OXXV, r 5, the power of the Court to make a declaration, where it is a question of defining the rights of two parties, is almost unlimited; I might say only limited by its own discretion'.[32][32] Forster v Jododex [1972] HCA 61; (1972) 127 CLR 421, 435. In an oft-cited passage, Gibbs J continued:It is neither possible nor desirable to fetter the broad discretion given by s 10 by laying down rules as to the manner of its exercise. It does, however, seem to me that the Scottish rules summarized by Lord Dunedin in Russian Commercial and Industrial Bank v British Bank for Foreign Trade Ltd (1921) 2 AC 438, at p 448, should in general be satisfied before the discretion is exercised in favour of making a declaration: "The question must be a real and not a theoretical question; the person raising it must have a real interest to raise it; he must be able to secure a proper contradictor, that is to say, someone presently existing who has a true interest to oppose the declaration sought." Beyond that, however, little guidance can be given. As Lord Radcliffe said in Ibeneweka v Egbuna (1964) 1 WLR, at p 225: 'After all, it is doubtful if there is more of principle involved than the undoubted truth that the power to grant a declaration should be exercised with a proper sense of responsibility and a full realisation that judicial pronouncements ought not to be issued unless there are circumstances that call for their making. Beyond that there is no legal restriction on the award of a declaration'.[33][33] Forster v Jododex, 437 - 438.

Ratio Decidendi

Legal Principle Established

Clause 27.3 is an important provision. It sets out the circumstances in which Acciona is entitled to an extension of time, thereby avoiding exposure to liquidated damages provided for by cl 31. Clause 27.3 provides:27.3Extension of Time for Commercial Operations The Contractor may Claim an Extension of Time for each Day that the Contractor is delayed in achieving Commercial Operation by the Target Commercial Operation Date by reason directly of any of the following causes: (a)Any breach of this contract by Project Co Personnel (other than a failure to pay money);(b)Any act of omission of Project Co Personnel (not expressly authorised or permitted under this Contract):(c)Any failure or delay by the Certifier in making a determination or delivering certificates or other deliverables within the required timeframes set out in this Contract;(d)Any delay due to disruption to the Works caused by an Other Contractor (an/or their Personnel), or any Third Party;(e)Any opening up as provided for in clause 21.1(f);(f)Any non-compliance with clause 13.1(a) by Project Co;(g)Any Variation agreed or determined pursuant to clause 22;(h)Any suspension pursuant to clause 25.1 (other than where the suspension was necessary because of one or more of the circumstances set out in clause 25.3 or 15.1 (e));(i)Any suspension pursuant to the Construction Contracts Act;(j)Subject to the Contractor complying with its obligation under clause 29.3(f), the delay or failure of Project Co to procure the delivery of relevant quantities of Acceptable Waste in accordance with clause 29.3(e) and 29.3(g);(k)Project Co failing to provide or procure access to the Connection Point by the time identified in the Work Plan Contract Program, provided that if Project Co implements the Grid Connection Contingency Plan in accordance with clause 27.3(k), the entitlement to an Extension of Time will be limited to ten (10) Business Days;(l)Any failure by Project Co to comply with the Site Access Protocol;(m)The discovery of any Artefact; or(n)Any other provision under this Contract that provides expressly for an Extension of Time.(each an Extension Event) Clause 27.4 and cl 27.5 provide for Acciona to claim extensions of time in accordance with a prescribed process and subject to conditions precedent. Clause 27.6 provides for Acciona to claim the costs of delay associated with an extension of time. The provisions prescribe a strict regime by which Acciona may apply for an extension of time, and they supply the basis upon which Acciona is entitled to be compensated for the costs of delay. Clause 28 deals with the impact of a Force Majeure Event. It provides as follows:(a)The Affected Party must notify the other Party of any Force Majeure Event that precludes the Affected Party (whether partially or wholly) from complying with its obligations under this Contract (Affected Obligations) promptly upon the occurrence of, and in any event within sixteen (16) Business Days of, the Force Majeure event and must either:(i) to the extent practicable, specify in the notice the length of delay or disruption that will result from the Force Majeure Event; or(ii) where it is not practicable to specify the length of delay or disruption at the time the notice is delivered, provide the other Party with periodic supplemental notices during the period over which the Force Majeure continues to have effect. (b)Subject to clause 28(c), the Affected Party's obligation to perform the Affected Obligations is suspended for the duration of the actual delay or disruption arising out of the Force Majeure Event and any event that would otherwise give rise to a right to terminate this Contract is disregarded to the extent arising out of the non-performance of the Affected Obligations. Project Co must grant an extension to the Target Commercial Operation Date for the period of the actual delay or disruption on achieving Commercial Operation by the Commercial Operation Date. …(d)The Parties must use their reasonable endeavours to remove or relieve the Force Majeure Event and to minimise the delay or disruption caused by any Force Majeure Event. If the Contractor is the Affected Party with Affected Obligations, the Contractor must also prepare a plan as soon as practicable following notice being given of the Force Majeure Event, describing how the effects of the Force Majeure Event can be overcome. The purpose of the plan is to assist the Parties to comply with their obligations in this clause 28(d) only (and to assist Project Co to comply with its obligations pursuant to clause 18.1(e) of the RRC WAS).(e) Each of the Parties will be responsible for their own costs incurred during the period of the Force Majeure Event. (f)Without entitling the Contractor to any further extension of time for any Force Majeure Event, during any Force Majeure Event that has continued for at least seven (7) consecutive days and which is not reasonably likely to cease within a further fourteen (14) days, the Contractor may by written notice to Project Co demobilise the Contractor Personnel from the Site as part of its obligation to mitigate the effects of the Force Majeure Event. As soon as the Force Majeure Event ceases, the Contractor will commence remobilising Contractor Personnel to continue performing the Works. (g)The Contractor is not entitled to: (i)Recover costs from Project Co (other than to the extent provided in clause 31.10); or(ii)Without limiting Project Co's obligation to extend the Target Commercial Operation Date in accordance with clause 28(b), an Extension of Time pursuant to clause 27.3,in respect of a Force Majeure Event.