Accent On Homes Pty Ltd and Ghiann Pty Ltd

Link copied
Case Copied 53 min read

JURISDICTION     :   STATE ADMINISTRATIVE TRIBUNAL

STREAM:   COMMERCIAL & CIVIL

ACT: BUILDERS' REGISTRATION ACT 1939 (WA)

CITATION:   ACCENT ON HOMES PTY LTD and GHIANN PTY LTD [2007] WASAT 22

MEMBER:   MR C RAYMOND (SENIOR MEMBER)

MR M SPILLANE (MEMBER)

HEARD:   27, 28 NOVEMBER 2006 AND 15 DECEMBER 2006

DELIVERED          :   30 JANUARY 2007

FILE NO/S:   VR 235 of 2005

BETWEEN:   ACCENT ON HOMES PTY LTD

Applicant

AND

GHIANN PTY LTD
Respondent

FILE NO/S              :VR 283 of 2005

BETWEEN             :GHIANN PTY LTD

Applicant

AND

ACCENT ON HOMES PTY LTD
Respondent

Catchwords:

Builders Registration Act 1939 (WA) - Review of decision of Building Disputes Tribunal - Determination of date for commencement and completion of works - Damages for delay - Risk of theft from site - Whether costs of brick build up subject to adjustment - Claim for damages for substitution of specified materials - Review of quantum of compensation for remedial and incomplete works

Legislation:

Builders' Registration Act 1939 (WA), s 12A, s 41
Home Building Contracts Act 1991 (WA), s 17
State Administrative Tribunal Act 2004 (WA), s 27

Result:

Application under VR 235 of 2005 dismissed
Application under VR 283 of 2005 partially successful

Category:    B

Representation:

VR 235 of 2005

Counsel:

Applicant:     Mr G Slattery

Respondent:     Mr G Wates and Ms J Wates (Acting as Agent)

Solicitors:

Applicant:     Minter Ellison

Respondent:     N/A

VR 283 of 2005

Counsel:

Applicant:     Mr G Wates (Acting as Agent)

Respondent:     Mr G Slattery

Solicitors:

Applicant:     N/A

Respondent:     Minter Ellison

Case(s) referred to in decision(s):

BCCI v Ali [2002] 1 AC 251

Homburg Houtimport BV v Agrosin Private Ltd (The Starsin) [2003] 2 WLR 711

State Rail Authority of New South Wales v Earthline Constructions Pty Ltd (In Liq) & Ors [1999] HCA 3

Tangent Nominees Pty Ltd and Edwards & Anor [2006] WASAT 243

REASONS FOR DECISION OF THE TRIBUNAL: 

Index

Page

1.

Summary of Tribunal's decision

5

2.

The consolidated proceedings

7

3.

The issues for determination and sources of evidence

8

4.

Background

12

5.

Commencement and completion dates

16

6.

Extension of time for completion

19

7.

Practical completion

21

(a)  The standard of completion required

21

(b)  Was practical completion achieved?

24

(c)  Whether practical completion was accepted or waived

31

8.

Delay damages

33

9.

Which party bears the risk of theft?

37

10.

Brick build ups

37

(a)  Survey costs

40

(b)  Engineers inspection fees

40

(c)  Propping costs

40

(d)  Engineers inspection after build ups

41

11.

Substitution of lime silica bricks

42

12.

Claims for additional compensation for defective or incomplete work

43

13.

Conclusion and orders

44

Summary of Tribunal's decision

  1. In this matter both parties to a hearing before the Building Disputes Tribunal were granted leave to review the decision and their respective applications were consolidated for the purposes of the review hearing. 

  2. The dispute arose out of four separate building contracts entered into between the property owner, Ghiann Pty Ltd, and the builder, Accent On Homes Pty Ltd, for the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Accent On Homes Pty Ltd and Ghiann Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2007] WASAT 22
Decision Date

CaseChat Overview and Summary

Accent On Homes Pty Ltd and Ghiann Pty Ltd were the parties to a legal dispute that was heard by the Building Disputes Tribunal and subsequently reviewed by the court. The central issue in the dispute was the determination of the date for the commencement and completion of construction works, along with damages for delays and substitution of materials. The tribunal had initially ruled on these matters, but Accent On Homes sought a review of the decision, and Ghiann Pty Ltd sought to review part of the tribunal’s decision. The court was required to decide on several legal issues, including whether the costs of brick build-ups were subject to adjustment, the claim for damages for substitution of specified materials, and the quantum of compensation for remedial and incomplete works.

The court's reasoning involved a detailed analysis of the contractual terms and the evidence presented regarding the costs and delays associated with the construction works. The court found that the tribunal had erred in its calculation of the costs for brick build-ups and the delay damages. The tribunal had allowed costs of $24,852 for brick build-ups, whereas the court determined that the actual expenditure was $17,823.20, leading to a refund of $7,028.80. Regarding the delay, the court calculated the delay period and assessed the builder's liability for the delay, resulting in a payment of $42,408.75. The court also upheld the tribunal's decision on the substitution of materials, awarding nominal damages of $40. After considering the payments already made by the builder, the court ordered the builder to pay the balance of $21,390.55.

The final orders of the court affirmed certain parts of the tribunal’s decision while setting aside others. The court substituted its own orders for the parts it set aside, detailing the specific amounts owed and the timeline for payment. The parties' other applications for review were dismissed, leaving the court's substituted orders as the final determination of the dispute.

Orders

Orders of the court

1. The decision under review reflected in the Order to Pay no 149/2004-05 issued by the Building Disputes Tribunal on 30 March 2005 is: (a) affirmed in respect of Orders 1, 2, 6 and 8; and (b) set aside in respect of Orders 3, 4, 5 and 7, and the decision of this Tribunal is substituted therefore as reflected in the following Orders, which are numbered to correspond with and to substitute for the Orders so set aside. "(3) As to the claim by the owner for excessive charges for brick build ups, a refund is applicable being the difference between the costs allowed in the contracts of $24 852 less the sum expended of $17 823.20, in a total amount of $7028.80. (4) As to the claim for delay in the completion of the contract works from 15 July 2003 to 15 December 2003 in respect of Unit 4, and to 6 May 2004 in respect of Units 1, 2 and 3, less a deduction of six weeks for works required to be undertaken by the owner, the builder is to pay the owner a total sum of $42 408.75. (5) The builder is to pay the owner nominal damages for breach of contract by substituting the specified internal clay bricks with calcium silica bricks and failing to adjust the contract sum, in an amount of $10 in respect of each contract, a total sum of $40. (7) Taking into account the sum of $33 945 already paid by the builder to the owner, the builder is to pay to the owner the balance of the amount found to be due in the sum of $21 390.55 on or before 27 February 2007." 2. Save for the above orders the parties' respective applications for review are dismissed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.