JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM: COMMERCIAL & CIVIL
ACT: BUILDERS' REGISTRATION ACT 1939 (WA)
CITATION: ACCENT ON HOMES PTY LTD and GHIANN PTY LTD [2007] WASAT 22
MEMBER: MR C RAYMOND (SENIOR MEMBER)
MR M SPILLANE (MEMBER)
HEARD: 27, 28 NOVEMBER 2006 AND 15 DECEMBER 2006
DELIVERED : 30 JANUARY 2007
FILE NO/S: VR 235 of 2005
BETWEEN: ACCENT ON HOMES PTY LTD
Applicant
AND
GHIANN PTY LTD
Respondent
FILE NO/S :VR 283 of 2005
BETWEEN :GHIANN PTY LTD
Applicant
AND
ACCENT ON HOMES PTY LTD
Respondent
Catchwords:
Builders Registration Act 1939 (WA) - Review of decision of Building Disputes Tribunal - Determination of date for commencement and completion of works - Damages for delay - Risk of theft from site - Whether costs of brick build up subject to adjustment - Claim for damages for substitution of specified materials - Review of quantum of compensation for remedial and incomplete works
Legislation:
Builders' Registration Act 1939 (WA), s 12A, s 41
Home Building Contracts Act 1991 (WA), s 17
State Administrative Tribunal Act 2004 (WA), s 27
Result:
Application under VR 235 of 2005 dismissed
Application under VR 283 of 2005 partially successful
Category: B
Representation:
VR 235 of 2005
Counsel:
Applicant: Mr G Slattery
Respondent: Mr G Wates and Ms J Wates (Acting as Agent)
Solicitors:
Applicant: Minter Ellison
Respondent: N/A
VR 283 of 2005
Counsel:
Applicant: Mr G Wates (Acting as Agent)
Respondent: Mr G Slattery
Solicitors:
Applicant: N/A
Respondent: Minter Ellison
Case(s) referred to in decision(s):
Homburg Houtimport BV v Agrosin Private Ltd (The Starsin) [2003] 2 WLR 711
State Rail Authority of New South Wales v Earthline Constructions Pty Ltd (In Liq) & Ors [1999] HCA 3
Tangent Nominees Pty Ltd and Edwards & Anor [2006] WASAT 243
REASONS FOR DECISION OF THE TRIBUNAL:
| Index | Page | |
| 1. | Summary of Tribunal's decision | 5 |
| 2. | The consolidated proceedings | 7 |
| 3. | The issues for determination and sources of evidence | 8 |
| 4. | Background | 12 |
| 5. | Commencement and completion dates | 16 |
| 6. | Extension of time for completion | 19 |
| 7. | Practical completion | 21 |
| (a) The standard of completion required | 21 | |
| (b) Was practical completion achieved? | 24 | |
| (c) Whether practical completion was accepted or waived | 31 | |
| 8. | Delay damages | 33 |
| 9. | Which party bears the risk of theft? | 37 |
| 10. | Brick build ups | 37 |
| (a) Survey costs | 40 | |
| (b) Engineers inspection fees | 40 | |
| (c) Propping costs | 40 | |
| (d) Engineers inspection after build ups | 41 | |
| 11. | Substitution of lime silica bricks | 42 |
| 12. | Claims for additional compensation for defective or incomplete work | 43 |
| 13. | Conclusion and orders | 44 |
Summary of Tribunal's decision
In this matter both parties to a hearing before the Building Disputes Tribunal were granted leave to review the decision and their respective applications were consolidated for the purposes of the review hearing.
The dispute arose out of four separate building contracts entered into between the property owner, Ghiann Pty Ltd, and the builder, Accent On Homes Pty Ltd, for the…
Keep reading for free
Create a free CaseChat account to read Accent On Homes Pty Ltd and Ghiann Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] WASAT 22
- Decision Date
CaseChat Overview and Summary
The court's reasoning involved a detailed analysis of the contractual terms and the evidence presented regarding the costs and delays associated with the construction works. The court found that the tribunal had erred in its calculation of the costs for brick build-ups and the delay damages. The tribunal had allowed costs of $24,852 for brick build-ups, whereas the court determined that the actual expenditure was $17,823.20, leading to a refund of $7,028.80. Regarding the delay, the court calculated the delay period and assessed the builder's liability for the delay, resulting in a payment of $42,408.75. The court also upheld the tribunal's decision on the substitution of materials, awarding nominal damages of $40. After considering the payments already made by the builder, the court ordered the builder to pay the balance of $21,390.55.
The final orders of the court affirmed certain parts of the tribunal’s decision while setting aside others. The court substituted its own orders for the parts it set aside, detailing the specific amounts owed and the timeline for payment. The parties' other applications for review were dismissed, leaving the court's substituted orders as the final determination of the dispute.
Orders
Orders of the court
1. The decision under review reflected in the Order to Pay no 149/2004-05 issued by the Building Disputes Tribunal on 30 March 2005 is: (a) affirmed in respect of Orders 1, 2, 6 and 8; and (b) set aside in respect of Orders 3, 4, 5 and 7, and the decision of this Tribunal is substituted therefore as reflected in the following Orders, which are numbered to correspond with and to substitute for the Orders so set aside. "(3) As to the claim by the owner for excessive charges for brick build ups, a refund is applicable being the difference between the costs allowed in the contracts of $24 852 less the sum expended of $17 823.20, in a total amount of $7028.80. (4) As to the claim for delay in the completion of the contract works from 15 July 2003 to 15 December 2003 in respect of Unit 4, and to 6 May 2004 in respect of Units 1, 2 and 3, less a deduction of six weeks for works required to be undertaken by the owner, the builder is to pay the owner a total sum of $42 408.75. (5) The builder is to pay the owner nominal damages for breach of contract by substituting the specified internal clay bricks with calcium silica bricks and failing to adjust the contract sum, in an amount of $10 in respect of each contract, a total sum of $40. (7) Taking into account the sum of $33 945 already paid by the builder to the owner, the builder is to pay to the owner the balance of the amount found to be due in the sum of $21 390.55 on or before 27 February 2007." 2. Save for the above orders the parties' respective applications for review are dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.