Administrative Appeals Tribunal
DECISION AND REASONS FOR DECISION [2007] AATA 1759
ADMINISTRATIVE APPEALS TRIBUNAL )
) No QT200600355
TAXATION APPEALS DIVISION ) Re A TAXPAYER Applicant
And
COMMISSIONER OF TAXATION
Respondent
DECISION
Tribunal Deputy President P E Hack SC Date13 September 2007
PlaceBrisbane
Decision The Tribunal:
1. sets aside the objection decision;
2. remits the matter to the respondent with a direction that:
(a) the applicant is entitled to an off-road credit for the use of diesel fuel in earthworks for the construction of a rail line to carry minerals from a mine site to a port;
(b) the applicant is entitled to an off-road credit for the use of diesel fuel in earthworks for the construction of a maintenance road alongside the rail line;
3. Certifies that the proceedings have terminated in a manner favourable to the applicant.
..............................................
Deputy President
Background
2.There is no dispute between the parties regarding the facts. What follows is, as I understand it, common ground.
3.The Rolleston mine is some 16 kilometres west of Rolleston in Central Queensland. The mine is operated by Xstrata Coal Australia Pty Ltd (“Xstrata”). It is an open cut thermal mine that produces power grade coal that is not subjected to any processing after it leaves the mine site. The mine commenced operations, in the sense of first extracting coal, shortly prior to October 2005.
4.The rail line in issue in this case is described as the Bauhinia Regional Rail Project. It was built to take coal from the Rolleston mine to the Port of Gladstone via the Kinrola Spur at Blackwater. The length of the new line is not entirely clear but seems to be in excess of 100 kilometres in length.
5.Construction of the rail line involved as well the construction of an 8 metre wide access road adjacent to the rail line for maintenance of, and access to, the rail line. Queensland Rail contracted the task of constructing the rail line and access road to Abigroup Contractors Pty Ltd (“Abigroup”). Abigroup, in turn, subcontracted to the applicant:
“The supply of all materials, labour, operators, plant and equipment to complete the Earthworks Mass Haul between chainage km 72.100 to chainage km 100.900.”
6.The works undertaken by the applicant comprised[1]:
[1] Taken from the applicant’s Statement of Facts and Contentions (Exhibit 3) at paragraph 6; see the respondent’s Statement of Facts and Contentions (Exhibit 4) at paragraph 6.
·the clearing of virgin land and the removal and stockpiling of topsoil;
·the earthworks to construct an 8 metre wide construction haul road for safe access to the site during the Works and remaining upon completion of the Works for the purpose of private access to and maintenance of the railway;
·the performance of necessary bulk earthworks to construct the rail formation and achieve the required vertical and horizontal alignment;
·the extraction and haulage of materials from within the wider easement and from adjoining properties due to a major shortfall in cut-to-fill balance;
·the earthworks for bridge…
Keep reading for free
Create a free CaseChat account to read A Taxpayer and Commissioner of Taxation and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2007] AATA 1759
- Decision Date
CaseChat Overview and Summary
The primary legal issues the Tribunal needed to address were whether the construction of the rail line and the access road constituted 'mining operations' as defined under the relevant legislation. This determination was crucial because the eligibility for off-road credits depended on whether the activities qualified as part of mining operations. The Tribunal also had to consider the statutory interpretation of terms such as'mining operations' and 'off-road credits' as outlined in the Energy Grants (Credits) Scheme Act 2003 and other relevant statutes.
In its decision, the Tribunal carefully examined the statutory language and relevant case law to determine that the construction of the rail line and the access road did indeed qualify as 'mining operations'. The Tribunal found that these activities were integral to the mining process, thus making the use of diesel fuel eligible for off-road credits. The Tribunal also noted that the legislative intent was to support energy-intensive industries, including mining, by providing credits for fuel used in operations that facilitate the extraction and transportation of minerals. Consequently, the Tribunal set aside the objection decision and remitted the matter back to the Commissioner with directions that the taxpayer was entitled to the claimed credits.
In light of the Tribunal's findings, it ordered that the objection decision be set aside, the matter be remitted to the Commissioner for reassessment, and certified that the proceedings had terminated in a manner favourable to the applicant. This outcome ensured that the taxpayer could claim the off-road credits for the diesel fuel used in the specified mining-related construction activities.
Orders
Orders of the court
The Tribunal:
1. sets aside the objection decision;
2. remits the matter to the respondent with a direction that:
(a) the applicant is entitled to an off-road credit for the use of diesel fuel in earthworks for the construction of a rail line to carry minerals from a mine site to a port;
(b) the applicant is entitled to an off-road credit for the use of diesel fuel in earthworks for the construction of a maintenance road alongside the rail line;
3. Certifies that the proceedings have terminated in a manner favourable to the applicant.
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi