Land and Environment Court
New South Wales
Medium Neutral Citation: 2 Bay Street Pty Ltd v Woollahra Municipal Council [2023] NSWLEC 1222 Hearing dates: Conciliation conference on 22 February 2023, 15 March 2023, 5 April 2023, final submissions on 9 May 2023 Date of orders: 11 May 2023 Decision date: 11 May 2023 Jurisdiction: Class 1 Before: Horton C Decision: See orders at [57].
Catchwords: DEVELOPMENT APPLICATION — commercial premises in B2 Local Centre zone – conciliation conference – agreement between parties – orders
Legislation Cited: Environmental Planning and Assessment Act 1979, ss 4.16, 4.46, 8.7, 8.15
Land and Environment Court Act 1979, s 34
State Environmental Planning Policy (Biodiversity and Conservation) 2021, Ch 10, s 10.2
State Environmental Planning Policy (Resilience and Hazards) 2021, s 4.6
State Environmental Planning Policy (Transport and Infrastructure) 2021, ss 2.118, 2.119
Water Management Act 2000, s 4.47
Woollahra Local Environmental Plan 2014, cll 4.3, 4.4, 4.4A, 4.6, 5.21, 6.1, 6.2
Cases Cited: Wehbe v Pittwater Council (2007) 156 LGERA 446; [2007] NSWLEC 827
Woollahra Municipal Council v SJD DB2 Pty Limited [2020] NSWLEC 115
Texts Cited: Woollahra Development Control Plan 2015
Category: Principal judgment Parties: 2 Bay Street Pty Ltd (Applicant)
Woollahra Municipal Council (Respondent)Representation: Counsel:
Solicitors:
R Lancaster SC (Applicant), A Boskovitz (Solicitor) on 15 March 2023
A Kleiss (Solicitor) (Respondent)
Boskovitz Lawyers (Applicant)
Lindsay Taylor Lawyers (Respondent)
File Number(s): 2022/291775 Publication restriction: Nil
Judgment
-
COMMISSIONER: This Class 1 appeal is brought under s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) following the refusal by the Woollahra Local Planning Panel, on behalf of the Woollahra Municipal Council (the Respondent), of development application DA 280/2022 seeking consent for the demolition of existing buildings and construction of a new commercial building with basement parking located at Nos 2, 4-10 Bay Street, 294-296 and 298 New South Head Road, Double Bay.
-
The Court arranged a conciliation conference under s 34(1) of the Land and Environment Court Act 1979 (LEC Act) between the parties, which was held on 22 February 2023, and at which I presided.
-
At the conciliation conference, the parties reached an in-principle agreement as to the scope of amendments required for the parties to reach the terms of a decision in the proceedings that would be acceptable to the parties, subject to time being granted for certain amendments to the development the subject of the development application.
-
I granted the parties an adjournment to permit the preparation of amended plans and other documents. On 15 March 2023, I granted a further adjournment so that additional amendments agreed between the parties could be made to the proposal.
-
This decision involved the Court upholding the appeal pursuant to s 4.16 of the EPA Act and granting development consent to the development application subject to conditions.
-
A signed agreement prepared in accordance with s 34(10) of the LEC Act was filed with the Court on 5 April 2023, and certain clarifications were provided to the Court on 17 April…
Keep reading for free
Create a free CaseChat account to read 2 Bay Street Pty Ltd v Woollahra Municipal Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NSWLEC 1222
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the council's decision to refuse the development application was unreasonable. The court had to consider the relevant planning laws and policies, as well as the evidence presented by both parties. Additionally, the court had to determine whether the council's decision-making process was compliant with the relevant statutory requirements.
The court found that the council's decision to refuse the development application was not unreasonable. The evidence presented by the council demonstrated that the proposed development would not comply with the relevant planning policies and would have significant adverse impacts on the surrounding environment. The court held that the council's decision was based on a proper consideration of the relevant planning laws and policies, and that the decision-making process was compliant with the statutory requirements. Consequently, the plaintiff's application for judicial review was dismissed, and the council's decision was upheld.
Orders
Orders of the court
See orders at [57].
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi