COMMONWEALTH OF AUSTRALIA
Sections 226 and 708
Offshore Petroleum and Greenhouse Gas Storage Act 2006
VARIATION OF PIPELINE LICENCE WA-13-PL
I, JOANNE JENNIFER BELL, Delegate of the National Offshore Petroleum Titles Administrator, on behalf of the Commonwealth–Western Australia Offshore Petroleum Joint Authority hereby vary Pipeline Licence WA-13-PL, dated 15 February 2006 (the Licence), for which:
Woodside Energy Ltd.
(ACN 005 482 986)
Woodside Energy (North West Shelf) Pty Ltd
(ACN 004 514 489)
BP Developments Australia Pty. Ltd.
(ACN 081 102 856)
Japan Australia LNG (MIMI) Pty. Ltd.
(ACN 006 303 180)
Shell Australia Pty Ltd
(ACN 009 663 576)
Chevron Australia Pty Ltd
(ACN 086 197 757)
are the registered titleholders, as set out below.
The variation takes effect on the day on which this notice of variation is published in the Commonwealth Government Gazette.
Made under the Offshore Petroleum and Greenhouse Gas Storage Act 2006
of the Commonwealth of Australia
JOANNE JENNIFER BELL
DELEGATE OF THE TITLES ADMINISTRATOR
ON BEHALF OF THE COMMONWEALTH–WESTERN AUSTRALIA
OFFSHORE PETROLEUM JOINT AUTHORITY
- The ROUTE OF PIPELINE is varied by deleting the current words and replacing with the following:
“The route of the pipeline is from the Pipeline End Manifold (PLEM) to the Goodwyn A Platform within the 100 m wide corridor, as shown in licensee’s Drawing No. A1950DX0001.0001, last updated July 2022, titled ‘POG Field Layout Pipeline and Flowline Routes’, attached as Attachment 1.
WA-13-PL Coordinates | |||
Feature | KP | Easting (m) | Northing (m) |
Pipeline End Manifold | 0 | 405 366 | 7 840 904 |
Production Pipeline (16”) Tie-in Flange Upstream | 0 | 405 346 | 7 840 848 |
| 1.000 | 404 406 | 7 840 514 |
| 2.000 | 403 509 | 7 840 089 |
| 3.000 | 402 743 | 7 839 449 |
| 4.000 | 401 942 | 7 838 851 |
| 5.000 | 401 162 | 7 838 228 |
| 6.000 | 400 728 | 7 837 340 |
POGP 10” In-line Tee | 6.550 | 400 565 | 7 836 812 |
| 7.000 | 400 439 | 7 836 384 |
| 8.000 | 400 177 | 7 835 420 |
| 9.000 | 399 876 | 7 834 467 |
| 10.000 | 399 568 | 7 833 516 |
POGP 16” In-line Tee | 10.039 | 399 554 | 7 833 471 |
| 11.000 | 399 266 | 7 832 564 |
| 12.000 | 398 594 | 7 831 850 |
| 13.000 | 397 637 | 7 831 569 |
| 14.000 | 396 674 | 7 831 303 |
| 15.000 | 395 700 | 7 831 084 |
| 16.000 | 394 733 | 7 830 831 |
| 17.000 | 393 768 | 7 830 572 |
| 18.000 | 392 792 | 7 830 358 |
| 19.000 | 391 825 | 7 830 106 |
| 20.000 | 391 000 | 7 829 549 |
| 21.000 | 390 218 | 7 828 927 |
| 22.000 | 389 415 | 7 828 334 |
| 23.000 | 388 622 | 7 827 725 |
| 24.000 | 387 919 | 7 827 023 |
Production Pipeline (16”) Tie-in Flange Downstream | 24.167 | 387 815 | 7 826 892 |
Upstream Spool Tie-in to SSIV | 24.369 | 387 867 | 7 826 752 |
Goodwyn A Platform Centre |
| 387 795 | 7 826 653 |
Coordinates are based on the GDA94 Geodetic datum, MGA Zone 50.”
2. The variation to the licence creates a system of pipes which includes the flowlines and spools linking the PER01 and PER03 wells to the Perseus over Goodwyn pipeline.
PER01 Flowline Arrangement | ||
Feature Name | Easting (mE) | Northing (mN) |
PER01 Wellhead Centre | 398 795 | 7 837 338 |
POGP 10” In-Line Tee | 400 565 | 7 836 812 |
PER01 Flowline Tie-in Flange | 398 806 | 7 837 311 |
PER03 Flowline Arrangement | ||
Feature Name | Easting (mE) | Northing (mN) |
PER03 Wellhead Centre | 399 588 | 7 833 444 |
POGP 16” In-Line Tee (Tie-In Flange) | 399 554 | 7 833 471 |
SCHEDULE – SPECIFICATIONS
3. The Schedule under Specifications, the Basis of Design table is varied by updating the items in bold and italics:
Item | Item Description | Details |
1 | From | Perseus PLEM |
2 | To | Goodwyn A Platform |
3 | Outside diameter of pipe and riser | 406.4 mm |
4 | Wall thickness of pipe inclusive of riser (only for carbon steel) | 21 mm + 3 mm internal CRA |
5 | Length | 27.352 km |
6 | Internal Corrosion Allowance | Nil (CRA lined/clad or solid duplex) |
7 | External Corrosion Allowance | 3 mm on riser above splash zone |
8 | Pipeline and Riser Steel Grade | Pipeline – DNV CS450 with CRA liner Riser and Spools – DNV CS450 with CRA Clad Bends and Flanges – Duplex Stainless Steel |
9 | Pipeline Specification | AS2885.4 / DNV-OS-F101 |
10 | Minimum yield strength of pipe steel | 450 MPa at 20⁰C |
11 | Pipeline Design Pressure | 8.9 MPag at seabed elevation at 128 m (to LAT) |
12 | Max Allowable Operating Pressure | 8.9 MPag at seabed elevation at 128 m (to LAT) |
13 | Normal Operating Pressure | 3.9 – 8.9 MPag at seabed elevation at 128 m (to LAT) |
14 | Proposed minimum field test pressure | 33.0 MPag Max |
15 | Normal Maximum Inlet Pressure | 8.9 MPag at seabed elevation at 128m (to LAT) |
16 | Normal Minimum Outlet Pressure | 3.9 MPag at seabed elevation at 128m (to LAT) |
17 | Minimum and Maximum Pipeline Design Temperature | Max 95⁰C, min -30⁰C |
18 | Maximum Riser and Spool Design Temperature | 67⁰C |
19 | Design capacity | Depends on well performance, nominally 540-650 MMscf/d |
20 | Stabilisation | By increased steel wall thickness |
21 | External coating specification | FBE adhesive/PP foam installation/PP shield (4 LPP) |
22 | Field weld joint coating | Compatible with 4LPP |
23 | Weight coating design and specification | Only for localised stability at pipeline ends. 120 m at the PLEM end and 96 m at the GWA end. 50 mm thick. |
24 | Characteristics of substance to be conveyed | Hydrocarbons, gas/condensate fluid. Minimum formation water. |
25 | General plans and descriptions of pump stations, tank stations or valve stations and their equipment | Terminal station declaration at Pipeline End Module (PLEM) |
26 | General plans and description of pigging facilities | Provision for temporary launching and receiving commissioning pigs will be located at the PLEM and downstream GWA RESDV |
27 | Design life | 33 years |
28 | The provisions for cathodic protection of the proposed pipeline | Pipeline bracelet anodes |
29 | Crossings | Nil |
30 | Marine Growth Allowance | Up to 145 mm soft, 12 mm hard |
31 | Location of offtake tees for future use | Upstream of Subsea Isolation Valve |
4. The WA-13-PL Pipeline Route Map at Annexure A is deleted and replaced with the map at Attachment 1.