Variation of Pipeline Licence VIC/PL17 (Flounder to Tuna) (RH95WT)

Administered by Department of Industry, Science and Resources

Legislation au C2025G00172 In force Gazette

Legislation content

 

COMMONWEALTH OF AUSTRALIA

 

Sections 226, 264 and 708

Offshore Petroleum and Greenhouse Gas Storage Act 2006

 

VARIATION OF PIPELINE LICENCE VIC/PL17

(FLOUNDER TO TUNA) (RH95WT)

 

I, NICOLE LYNETTE FILBAY, the Delegate of the National Offshore Petroleum Titles Administrator, on behalf of the Commonwealth-Victoria Offshore Petroleum Joint Authority hereby vary Pipeline Licence VIC/PL17, dated 10 August 1983 (the Licence), for which:

 

Esso Australia Resources Pty Ltd

(ACN 091 829 819)

 

Woodside Australia Resources Pty Ltd

(ACN 004 228 004)

 

 

are the registered titleholders, as set out below.

 

The variation takes effect on the day on which this notice of variation is published in the Australian Government Gazette.

 

Made under the Offshore Petroleum and Greenhouse Gas Storage Act 2006
of the Commonwealth of Australia

 

NICOLE LYNETTE FILBAY

DELEGATE OF THE TITLES ADMINISTRATOR

ON BEHALF OF THE COMMONWEALTH-VICTORIA

OFFSHORE PETROLEUM JOINT AUTHORITY

 

 


 

FIRST SCHEDULE  

ROUTE OF PIPELINE

 

The route of the pipeline is described in the table below, and displayed in the map below (Attachment A), commencing at cut spool location at the Flounder A platform and terminating at the first flange upstream of the First Valve On (FVO) on the Tuna A platform.  

 

ID

DESCRIPTION

Easting (m)

Northing (m)

1 

Cut spool location at Flounder platform  

625859.5 

5758705.0 

2 

Inflection Point 01  

625866.6 

5758705.4 

3 

Flexible Pipeline – Section 1 begin  

625869.6 

5758720.0 

4 

Inflection Point 02  

625873.3 

5758735.3 

5 

Inflection Point 03  

625867.5

5758784.4 

6 

Inflection Point 04  

625833.0 

5758787.0 

7 

Inflection Point 05  

625876.0

5758799.0 

8 

Inflection Point 06  

625783.0 

5758817.0 

9 

Flexible Pipeline – Section 1 End  

625783.0 

5758820.5 

10 

Flexible Pipeline – Section 2 Begin  

625829.0 

5762200.6 

11 

Inflection Point 07 

625829.0 

5762223.0 

12 

Inflection Point 08  

625863.0 

5762244.0 

13 

Flexible Pipeline – Section 2 End  

625863.7 

5762252.3 

14 

Flexible Pipeline – Section 3 Begin  

626088.7 

5765623.2 

15 

Inflection Point 09 

626086.7 

5765652.0 

16 

Inflection Point 10 

626118.3 

5765644.9 

17 

Flexible Pipeline – Section 3 End  

626115.6 

5765674.0 

18 

West Tuna Fluid Umbilical Crossing 

625459.8 

5772194.2 

19 

KPA350 South Gas Pipeline Crossing 

625455.8 

5772214.9 

20 

KPA350 North Gas Pipeline Crossing 

625446.1 

5772265.8 

21 

West Tuna Electrical Umbilical Crossing 

625441.2 

5772291.4 

22 

Inflection Point 11  

625214.0 

5773082.0 

23 

Inflection Point 12 

624587.1 

5774202.3 

24 

Inflection Point 13 

624365.9 

5774389.1 

25 

FVO Tuna Manifold 

624358.2 

5774389.1 

Coordinate set above is based on GDA 94/MGA Zone 55, survey of pipeline centreline.

 


SECOND SCHEDULE 

 

SPECIFICATION 

 

  1.         Design 

 

The pipeline design is based on the following parameters – 

 

  1.                  a 250 mm nominal diameter pipeline for the conveyance of gaseous and liquid hydrocarbons;
  2.               a flow rate of 8000 sm3/d (0.050 MMbbl/d) of liquid hydrocarbons & 0.85 MMsm3/d (30.02 MMscf/d) of gaseous hydrocarbons;
  3.             an internal design pressure of 13,790 kPag;
  4.             a flexible jumper design temperature of 85⁰C;
  5.                a specific gravity of 2.2 for the 250 mm weight coated pipeline (including contents);
  6.             a pipeline length of approximately 16.152 km.

 

  1.         Materials of Construction 

 

  1.                  Steel Pipe 

 

The line pipe shall be in accordance with the requirements of the American Petroleum Institute Specification – API Spec 5L, 38th Edition 1990 for Grade X52 seamless pipe and Esso Australia Limited Supplemental pipe specification accompanying the pipeline licence application, and the pipeline shall have the dimensions 273.1 mm O.D. and 12.7 mm W.T.

 

  1.                Protective Coating

 

The line pipe shall be protected by a coating of Coal Tar Enamel to a thickness of not less than 3.50 mm or Fusion Bonded Epoxy corrosion coating.

 

Primary external corrosion protection for the pipeline is provided by a 3.5 mm Coal Tar Enamel coating.

 

  1.             Weight Coating 

 

The specification for the steel mesh reinforced weight coating and the shop application of this material to the pipe shall be in accordance with the Esso Australia Limited Protective Coatings Specifications accompanying the original pipeline licence application. 


Attachment A


 

Interactions

Authorises

All Versions

Sourced from the Federal Register of Legislation at 26 August 2026. For the latest information on Australian Government law please go to https://www.legislation.gov.au.