States Grants (Tertiary Education Assistance) Amendment Act (No. 2) 1980
No. 136 of 1980
An Act to amend the States Grants (Tertiary Education Assistance) Act 1978, and for related purposes
[Assented to 19 September 1980]
BE IT ENACTED by the Queen, and the Senate and the House of Representatives of the Commonwealth of Australia as follows:
Short title, &c.
1. (1) This Act may be cited as the States Grants (Tertiary Education Assistance) Amendment Act (No. 2) 1980.
(2) The States Grants (Tertiary Education Assistance) Act 1978 is in this Act referred to as the Principal Act.
Commencement
2. This Act shall come into operation on the day on which it receives the Royal Assent.
Approval of, and directions relating to, building projects
3. Section 4 of the Principal Act is amended—
(a) by omitting sub-section (2) and substituting the following sub-section:
“(2) The building projects that may be approved by the Minister under sub-section (1) in respect of a year to which this Act applies are building projects additional to the building projects specified in Schedule 7, Schedule 7a or Schedule 7b, whichever is applicable to that year.”; and
(b) by inserting in sub-section (5) “, Schedule 7a or Schedule 7b” after “Schedule 7”.
Grants for equipment
4. Section 8 of the Principal Act is amended—
(a) by omitting from sub-section (2) “this section” and substituting “this Act”;
(b) by omitting from sub-section (3) “this section” and substituting “this Act”;
(c) by omitting from sub-section (4) “this section” (second occurring) and substituting “this Act”;
(d) by omitting from sub-section (5) “this section” (second occurring) and substituting “this Act”; and
(e) by omitting sub-section (6).
Recurrent grants in respect of student residences and affiliated colleges
5. Section 9 of the Principal Act is amended—
(a) by omitting sub-sections (2a) and (2b) and substituting the following sub-sections:
“(2a) In relation to each student residence of a University, there is payable to the State in which the University is situated, in respect of the year 1980—
(a) an amount equal to the sum of $10,865 and the amount ascertained by multiplying $169.49 by the prescribed number of students for that year in relation to that student residence; or
(b) an amount ascertained by multiplying $383.92 by the prescribed number of students for that year in relation to that student residence,
whichever is the lesser amount.
“(2b) In relation to each student residence of a University, there is payable to the State in which the University is situated, in respect of the year 1981—
(a) an amount equal to the sum of $11,175 and the amount ascertained by multiplying $174.32 by the prescribed number of students for that year in relation to that student residence; or
(b) an amount ascertained by multiplying $394.84 by the prescribed number of students for that year in relation to that student residence,
whichever is the lesser amount.”; and
(b) by omitting sub-sections (4a) and (4b) and substituting the following sub-sections:
“(4a) For the purposes of sub-section (3), the basic grant in respect of an affiliated college for the year 1980 is—
(a) if the prescribed number of students for that year in relation to that college is less than 50—$383.92;
(b) if the prescribed number of students for that year in relation to that college is more than 49 but less than 75—$383.92 reduced by $2.90 for each student by which the prescribed number of students exceeds 50;
(c) if the prescribed number of students for that year in relation to that college is more than 74 but less than 100—$311.47 reduced by $1.45 for each student by which the prescribed number of students exceeds 75; and
(d) if the prescribed number of students for that year in relation to that college is more than 99—$275.27 reduced by $0.23 for each student by which the prescribed number of students exceeds 100.
“(4b) For the purposes of sub-section (3), the basic grant in respect of an affiliated college for the year 1981 is—
(a) if the prescribed number of students for that year in relation to that college is less than 50—$394.84;
(b) if the prescribed number of students for that year in relation to that college is more than 49 but less than 75—$394.84 reduced by $2.98 for each student by which the prescribed number of students exceeds 50;
(c) if the prescribed number of students for that year in relation to that college is more than 74 but less than 100—$320.34 reduced by $1.49 for each student by which the prescribed number of students exceeds 75; and
(d) if the prescribed number of students for that year in relation to that college is more than 99—$283.11 reduced by $0.23 for each student by which the prescribed number of students exceeds 100.”; and
6. After section 11c of the Principal Act the following section is inserted:
Building projects in respect of the year 1981, &c.
“11d. (1) Subject to sub-section (3), in relation to each building project specified, in relation to a University, in column 2 of Part I of Schedule 7b, there is payable to the State in which the University is situated, for the purpose of financial assistance in relation to the building project in respect of the year 1981, the amount specified in column 4 of that Part of that Schedule in relation to the description of the project in column 2.
“(2) The Commission may approve a minor building project submitted to it by a University as an approved minor building project of the University in respect of the year 1981 and, where it does so, it shall also approve an amount, being an amount equal to the estimated cost of the project, as the approved cost of the project and an amount as the amount of the approved expenditure on the project in respect of the year 1981.
“(3) Subject to sub-section (4), where the Commission approves, under sub-section (2), a minor building project of a University in respect of the year 1981, there is payable to the State in which the University is situated, for the purpose of financial assistance in relation to the project in respect of the year 1981, an amount equal to the amount of the approved expenditure on the project in respect of the year 1981.
“(4) The total of the amounts payable to a State under sub-section (3), in relation to a University specified in column 1 of Part II of Schedule 7b, shall not exceed the amount specified in column 2 of that Part of that Schedule in relation to the University.
“(5) The Commission may approve an amount as the amount of the approved expenditure in respect of the year 1981 on a design project of a University specified in Part III of Schedule 7b.
“(6) Subject to sub-section (7), where the Commission approves an amount as the amount of the approved expenditure, in respect of the year 1981, on a design project of a University specified in Part III of Schedule 7b, there is payable to the State in which the University is situated, for the purposes of financial assistance in relation to the project in respect of the year 1981, an amount equal to the amount of that approved expenditure.
“(7) The total of the amounts payable to all the States under sub-section (6) shall not exceed the amount set out in Part III of Schedule 7b as the total of the grants payable in respect of design projects specified in that Part.
“(8) The Commission may revoke or vary an approval given under sub-section (2) or (5) and, if it varies the amount of the approved expenditure on a project in respect of the year 1981, then, for the purposes of this Act, the amount as so varied shall be deemed—
(a) in the case of a project approved under sub-section (2)—as from the date on which the project was so approved; or
(b) in the case of a design project specified in Part III of Schedule 7b—as from the date on which approval was given under sub-section (5) in respect of the project,
to have been the amount of the approved expenditure on the project in respect of the year 1981.
“(9) Financial assistance is granted to a State under this section in relation to an approved building project of a University on the conditions that—
(a) the State will pay each amount paid to it under this section in relation to the project to the University without undue delay;
(b) the State will ensure that the amount expended in relation to work carried out before 1 January 1982 in connection with the project will be not less than the sum of the amounts paid to the State in relation to the project under this Act or any previous Act that granted financial assistance to the States in relation to Universities;
(c) the State will ensure that information in respect of the project is furnished to the Commission in accordance with any relevant direction under paragraph 4(1)(d);
(d) the State will ensure that the project will be carried out in accordance with the directions (if any) given by the Commission under sub-section 4(5);
(e) the State will ensure that, if the Commission so requests a University, there will be furnished to the Commission by the University, as soon as practicable after such date as the Commission specifies, such particulars as are specified by the Commission concerning the progress or expected progress of the work or matter constituting the project; and
(f) the State will cause to be furnished to the Commission, not later than 30 September 1982, a statement by a qualified auditor, in accordance with a form approved by the Commission, as to the amounts expended in respect of work carried out before 1 January 1982 in connection with the approved project.
“(10) In sub-section (9), a reference to an approved building project of a University shall be read as a reference to—
(a) a building project specified in column 2 of Part I of Schedule 7b in relation to the University;
(b) a project approved by the Commission under sub-section (2) as an approved minor building project of the University in respect of the year 1981; or
(c) a design project of a University specified in Part III of Schedule 7b.”.
Grants for equipment
7. Section 16 of the Principal Act is amended—
(a) by omitting from sub-section (2) “this section” and substituting “this Act”;
(b) by omitting from sub-section (3) “this section” and substituting “this Act”;
(c) by omitting from sub-section (4) “this section” and substituting “this Act”;
(d) by omitting from sub-section (6) “this section” and substituting “this Act”; and
(e) by omitting sub-section (9).
Recurrent grants in respect of student residences and affiliated colleges
8. Section 17 of the Principal Act is amended—
(a) by omitting sub-sections (2a) and (2b) and substituting the following sub-sections:
“(2a) In relation to each college of advanced education providing collegiate accommodation at a student residence or at student residences, there is payable to the State in which the college is situated, in respect of the year 1980—
(a) an amount equal to the sum of $10,865 and the amount ascertained by multiplying $169.49 by the number of resident full-time students at the student residence or at the student residences, as the case may be, in that year; or
(b) an amount ascertained by multiplying $383.92 by the number of resident full-time students at the student residence or at the student residences, as the case may be, in that year,
whichever is the lesser amount.
“(2b) In relation to each college of advanced education providing collegiate accommodation at a student residence or at student residences, there is payable to the State in which the college is situated, in respect of the year 1981—
(a) an amount equal to the sum of $11,175 and the amount ascertained by multiplying $174.32 by the number of resident full-time students at the student residence or at the student residences, as the case may be, in that year; or
(b) an amount ascertained by multiplying $394.84 by the number of resident full-time students at the student residence or at the student residences, as the case may be, in that year,
whichever is the lesser amount.”; and
(b) by omitting sub-sections (4a) and (4b) and substituting the following sub-sections:
“(4a) For the purposes of sub-section (3), the basic grant in respect of an affiliated college for the year 1980 is—
(a) if the number of resident full-time students at the college in that year is less than 50—$383.92;
(b) if the number of resident full-time students at the college in that year is more than 49 but less than 75—$383.92 reduced by $2.90 for each student by which that number of students exceeds 50;
(c) if the number of resident full-time students at the college in that year is more than 74 but less than 100—$311.47 reduced by $1.45 for each student by which that number of students exceeds 75; or
(d) if the number of resident full-time students at the college in that year is more than 99—$275.27 reduced by $0.23 for each student by which that number of students exceeds 100.
“(4b) For the purposes of sub-section (3), the basic grant in respect of an affiliated college for the year 1981 is—
(a) if the number of resident full-time students at the college in that year is less than 50—$394.84;
(b) if the number of resident full-time students at the college in that year is more than 49 but less than 75—$394.84 reduced by $2.98 for each student by which that number of students exceeds 50;
(c) if the number of resident full-time students at the college in that year is more than 74 but less than 100—$320.34 reduced by $1.49 for each student by which that number of students exceeds 75; or
(d) if the number of resident full-time students at the college in that year is more than 99—$283.11 reduced by $0.23 for each student by which that number of students exceeds 100.”.
Grants for courses of teacher education provided by non-Government teachers colleges
9. Section 19 of the Principal Act is amended by omitting paragraphs (a) and (b) of sub-section (2) and substituting the following paragraphs:
“(a) in respect of the year 1980—$1,347,000; and
“(b) in respect of the year 1981—$1,455,000.”.
Grants in respect of contributions to National Institute of Dramatic Art
10. Section 20 of the Principal Act is amended by omitting paragraphs (b) and (c) of sub-section (1a) and substituting the following paragraphs:
“(b) in the case of the year 1980—$554,000; and
“(c) in the case of the year 1981—$571,000.”.
11. After section 21c of the Principal Act the following section is inserted:
Building projects in respect of the year 1981, &c.
“21d. (1) In relation to the building projects specified in column 2 of Part IV of Schedule 7b in relation to colleges of advanced education in a State, in respect of the year 1981, there is payable to that State, for the purpose of financial assistance in relation to those building projects, an amount equal to the amount specified in Column 4 of that Part as the total amount for the State.
“(2) The Commission may approve a minor building project submitted to it by a State as an approved minor building project of a college of advanced education in respect of the year 1981, and, if it approves such a project, it shall also approve an amount, being an amount equal to the estimated cost of the project, as the approved cost of the project and an amount as the amount of the approved expenditure on the project in respect of the year 1981.
“(3) Subject to sub-section (4), where the Commission approves, under sub-section (2), a minor building project of a college of advanced education in respect of the year 1981, there is payable to the State in which the college is situated, for the purpose of financial assistance in relation to the project in respect of the year 1981, an amount equal to the amount of the approved expenditure on the project in respect of the year 1981.
“(4) The total of the amounts payable to a State under sub-section (3), in relation to minor building projects of colleges of advanced education situated in that State that are approved under sub-section (2) shall not exceed the amount specified in column 2 of Part V of Schedule 7b in relation to that State.
“(5) The Commission may approve an amount as the amount of the approved expenditure in respect of the year 1981 on a design project of a college of advanced education specified in Part VI of Schedule 7b.
“(6) Subject to sub-section (7), where the Commission approves an amount as the amount of the approved expenditure, in respect of the year 1981, on a design project of a college of advanced education specified in Part VI of Schedule 7b, there is payable to the State in which the college is situated, for the purposes of financial assistance in relation to the project in respect of the year 1981, an amount equal to the amount of that approved expenditure.
“(7) The total of the amounts payable under sub-section (6) shall not exceed the amount set out in Part VI of Schedule 7b as the total of all grants payable in respect of design projects specified in that Part.
“(8) The Commission may revoke or vary an approval given under sub-section (2) or (5), and, if it varies the amount of the approved expenditure on a project in respect of the year 1981, then, for the purposes of this Act, the amount as so varied shall be deemed—
(a) in the case of a project approved under sub-section (2)—as from the date on which the project was so approved; or
(b) in the case of a design project specified in Part VI of Schedule 7b—as from the date on which an approval was given under sub-section (5) in respect of the project,
to have been the amount of the approved expenditure on the project in respect of the year 1981.
“(9) Financial assistance is granted to a State under sub-section (1) in relation to the building projects of colleges of advanced education situated in that State, being building projects specified in column 2 of Part IV of Schedule 7b, on the conditions that—
(a) the State will, in respect of each amount of the financial assistance paid to it—
(i) pay that amount to a college of advanced education in respect of a building project of the college; or
(ii) pay amounts aggregating that amount to colleges of advanced education in respect of the building projects of those colleges according to the respective needs of those projects,
without undue delay;
(b) the State will ensure that, in respect of the year 1981, it pays to each college in respect of which such a project is specified, in relation to that project, an amount that does not exceed, or amounts that, in the aggregate, do not exceed, the amount specified in column 4 of Part IV of Schedule 7b in relation to that project;
(c) the State will ensure, in respect of each of those projects, that the amount expended in relation to the work carried out before 1 January 1982 in relation to the project will be not less than the sum of—
(i) the amounts paid by the State to the college concerned in relation to the project under this section, section 21b or section 21c;and
(ii) the amounts (if any) paid to the State in relation to the project under section 21 or 21a or under any previous Act that granted financial assistance to the States in relation to colleges of advanced education;
(d) the State will ensure that information in respect of each of those projects is furnished to the Commission in accordance with any relevant direction given under paragraph 4(1)(d);
(e) the State will ensure that each of those projects will be carried out in accordance with the directions (if any) given by the Commission under sub-section 4 (5);
(f) the State will, if the Commission so requests, cause to be furnished to the Commission, as soon as practicable after such date as the Commission specifies, such particulars as are specified by the Commission concerning the progress or expected progress of the work or matter constituting each of those projects; and
(g) the State will cause to be furnished to the Commission, not later than 30 September 1982, a statement by a qualified auditor, in accordance with a form approved by the Commission, as to the amounts expended in respect of work carried out before 1 January 1981 in connection with each of those projects.
“(10) Financial assistance is granted to a State under this section in relation to an approved building project of a college of advanced education referred to in sub-section (11) on the conditions that—
(a) the State will, without undue delay, pay to the college each amount paid to it under this section in relation to the project;
(b) the State will ensure that the amount expended in relation to work carried out before 1 January 1982 in connection with the project will be not less than the sum of the amounts paid to the State in relation to the project under this Act or under any previous Act that granted financial assistance to the States in relation to colleges of advanced education;
(c) the State will ensure that information in respect of the project is furnished to the Commission in accordance with any relevant direction given under paragraph 4(1)(d);
(d) the State will ensure that the project will be carried out in accordance with the directions (if any) given by the Commission under sub-section 4(5);
(e) the State will, if the Commission so requests, cause to be furnished to the Commission, as soon as practicable after such date as the Commission specifies, such particulars as are specified by the Commission concerning the progress or expected progress of the work or matter constituting the project; and
(f) the State will cause to be furnished to the Commission, not later than 30 September 1982, a statement by a qualified auditor, in accordance with a form approved by the Commission, as to the amount expended in respect of work carried out before 1 January 1982 in connection with the approved project.
“(11) For the purposes of sub-section (10), a reference to an approved building project of a college of advanced education is—
(a) a project approved by the Commission under sub-section (2) of this section as an approved minor building project of the college in respect of the year 1981;or
(b) a design project of a college of advanced education specified in Part VI of Schedule 7b.”.
Interpretation
12. Section 23 of the Principal Act is amended by omitting from sub-section (1) the definition of “year to which this Act applies”.
Grants for recurrent expenditure
13. Section 24 of the Principal Act is amended—
(a) by omitting from sub-section (1) “this Part” and substituting “this Act”; and
(b) by omitting from sub-section (2) “this Part” and substituting “this Act”.
Proposals for expenditure on staff training and data processing
14. Section 25 of the Principal Act is amended—
(a) by omitting from sub-section (1) “this Part” and substituting “this Act”;
(b) by omitting sub-sections (2) and (3) and substituting the following sub-sections:
“(2) The Commission—
(a) may approve a proposal submitted to it by a State under sub-section (1) as an approved proposal for expenditure by the State in respect of a year to which this Act applies;
(b) shall, in the case of a proposal for expenditure in respect of the year 1981 in connection with a program referred to in paragraph (1)(a), approve the proposal for the purpose of sub-section (3) or (3a); and
(c) may revoke or vary any such approval.
“(2a) Subject to sub-section (2b), where a Commission approves a proposal for the purpose of sub-section (3a), it shall approve an amount as the amount of approved expenditure on that proposal.
“(2b) The aggregate of the amounts approved by the Commission under sub-section (2a) as amounts of approved expenditure on proposals approved for the purposes of sub-section (3a) shall not exceed the amount specified in Part IV of Schedule 11.
“(3) There is payable to the State, for the purpose of financial assistance in respect of expenditure incurred or to be incurred by the State or by an instrumentality of the State in accordance with an approved proposal or approved proposals (not being a proposal or proposals approved for the purposes of sub-section (3a)) for expenditure by the State in respect of a year to which this Act applies in connection with a program or programs referred to in paragraph (1)(a), the amount specified in relation to the State in column 2 of Part I, column 2 of Part II, or column 2 of Part III, of Schedule 11, whichever is applicable to that year.”;
(c) by inserting after sub-section (3) the following sub-section:
“(3a) There is payable to a State for the purpose of financial assistance in respect of expenditure incurred or to be incurred by the State or by an instrumentality of the State in relation to a proposal approved for the purposes of this sub-section, an amount equal to the amount of the approved expenditure on the proposal.”;
(d) by omitting from sub-section (4) all the words after “a year to which” and substituting “this Act applies in connection with a program or programs referred to in paragraph (1)(b), the amount specified in relation to the State in column 3 of Part I, column 3 of Part II, or column 3 of Part III, of Schedule 11, whichever is applicable to that year”;
(e) by omitting from sub-section (5) “this Part” and substituting “this Act”;
(f) by inserting after sub-section (5) the following sub-section:
“(5a) Financial assistance is granted to a State under sub-section (3a) on the conditions that—
(a) the State will ensure that the total of the amounts expended in respect of the year 1981 by the State and by instrumentalities of the State in accordance with proposals of expenditure by the State in respect of that year (approved for the purpose of sub-section (3a)) is not less than the sum of the amounts of financial assistance paid to the State under that sub-section in respect of that year; and
(b) the State will furnish to the Commission, not later than 30 September in the next following year, a statement by an approved auditor, in accordance with a form approved by the Commission, as to the expenditure by the State and by instrumentalities of the State in accordance with such approved proposals for expenditure.”; and
(g) by omitting from sub-section (6) “this Part” and substituting “this Act”.
Variations of amounts in Schedule 11
15. Section 26 of the Principal Act is amended—
(a) by omitting from sub-section (1) “this Part” and substituting “this Act”;
(b) by omitting from that sub-section “or in columns 2 and 3 of Part II,” and substituting “columns 2 and 3 of Part II, or columns 2 and 3 of Part III,”;
(c) by omitting from sub-section (2) “this Part” and substituting “this Act”;
(d) by omitting from that sub-section “or in columns 2 and 3 of Part II,” and substituting “columns 2 and 3 of Part II, or columns 2 and 3 of Part III,”;
(e) by omitting from paragraph (a) of sub-section (3) “or in columns 2 and 3 of Part II” and substituting “columns 2 and 3 of Part II, or columns 2 and 3 of Part III”;
(f) by omitting from paragraph (b) of sub-section (3) “or in column 2 or 3 of Part II” and substituting “column 2 or 3 of Part II, or column 2 or 3 of Part III”;
(g) by omitting from sub-section (4) “or Part II” and substituting “, Part II, or Part III,”;
(h) by omitting from paragraph (a) of sub-section (5) “and”; and
(j) by adding after paragraph (b) of sub-section (5) the following word and paragraph:
“; and (c) in the case of the variation of amounts specified in Part III of Schedule 11—the date on which the States Grants (Tertiary Education Assistance) Amendment Act (No. 2) 1980 receives the Royal Assent.”.
Other recurrent grants
16. Section 27 of the Principal Act is amended—
(a) by inserting in sub-section (2b) “or the year 1981” after “the year 1980”;
(b) by omitting from sub-section (3) “this Part” and substituting “this Act”; and
(c) by omitting from sub-section (4) “this Part” and substituting “this Act”.
Grants for recurrent expenditure in connection with programs of expenditure on voluntary adult education
17. Section 28 of the Principal Act is amended—
(a) by omitting from sub-section (3) “this Part” and substituting “this Act”; and
(b) by omitting from sub-section (4) “this Part” and substituting “this Act”.
18. After section 29c the following section is inserted:
Building projects in respect of the year 1981, &c.
“29d. (1) In relation to each building project specified, in relation to a technical and further education institution, in column 2 of Part VII of Schedule 7b, there is payable to the State in which the institution is situated, for the purpose of financial assistance in relation to the project in respect of the year 1981, the amount specified in column 4 of that Part in relation to the description of the project in column 2.
“(2) Financial assistance is granted to a State under this section in relation to a building project specified in column 2 of Part VII of Schedule 7b in relation to a technical and further education institution situated in that State subject to the conditions that—
(a) the State will ensure that the amount expended in relation to work carried out before 1 January 1982 in connection with the project will be not less than the sum of the amounts paid to the State in relation to the project under this Act or any previous Act that granted financial assistance to the State in relation to technical and further education institutions;
(b) the State will ensure that information in respect of the project is furnished to the Commission in accordance with any relevant direction under paragraph 4(1)(d);
(c) the State will ensure that the project will be carried out in accordance with the directions (if any) given by the Commission under sub-section 4 (5);
(d) the State will, if the Commission so requests, furnish to the Commission, as soon as practicable after such date as the Commission specifies, such particulars as are specified by the Commission concerning the progress or expected progress of the work or matter constituting the project; and
(e) the State will furnish to the Commission, not later than 30 September 1982, a statement by an approved auditor, in accordance with a form approved by the Commission, as to the amounts expended, in relation to work carried out before 1 January 1982, in connection with the project.”.
Grants for minor building projects and equipment
19. Section 30 of the Principal Act is amended—
(a) by omitting from sub-section (2) “this Part” and substituting “this section”;
(b) by omitting from sub-section (3) “this Part” and substituting “this section”; and
(c) by adding at the end thereof the following sub-section:
“(4) In this section, ‘year to which this section applies’ means the year 1979 or the year 1980.”.
Grants for approved courses provided by non-Government business colleges
20. Section 30d of the Principal Act is amended by omitting from sub-section (2) “$61.46” and substituting “$63.57”.
Grants for special teacher training initiatives
21. Section 30e of the Principal Act is amended—
(a) by omitting from sub-section (8) “$878,000” and substituting “$889,000”;
(b) by inserting after sub-section (8) the following sub-section:
“(8a) The aggregate of—
(a) the amounts approved by the Minister under sub-section (2) of section 19 of this Act, before that section was repealed, in respect of the year 1979; and
(b) the amounts approved by the Minister under sub-section (2) of this section, in respect of the years 1979, 1980 and 1981,
shall not exceed $1,668,000.”; and
(c) by omitting from sub-section (11) of the Principal Act “or the year 1980” and substituting “, the year 1980 or the year 1981”.
Variation of building grants
22. Section 31 of the Principal Act is amended—
(a) by omitting from sub-paragraph (i) of paragraph (a) of sub-section (3) “or” (second occurring);
(b) by inserting after sub-paragraph (ii) the following word and sub-paragraph:
“; or (iii) if that Schedule is Schedule 7b—by including in Part I, Part IV or Part VII, as the case requires”;
(c) by omitting from paragraph (a) of sub-section (4) “or” (second occurring);
(d) by inserting after paragraph (b) of sub-section (4) the following sub-section:
“; or (c) that will have the effect of increasing or decreasing the aggregate amounts that may be paid to a State under section 11d, 21d and 29d,”;
(e) by omitting from sub-paragraph (iii) of paragraph (c) of sub-section (5) “or”;
(f) by inserting after paragraph (d) of sub-section (5) the following word and paragraph:
“; or (e) that will have the effect of increasing or decreasing the aggregate of the amounts that may be paid to a State in respect of the year 1981 under section 11d, 21d or 29d.”;
(g) by omitting from paragraph (b) of sub-section (6) “$132,760,000; or” and substituting “$132,891,000;”;
(h) by inserting after paragraph (b) of sub-section (6) the following paragraph:
“(ba) that could result in the aggregate of the amounts payable to the States under sections 11d, 21d and 29d being greater or less than $125,344,000; or”; and
(j) by omitting sub-section (10) and substituting the following sub-section:
“(10) In this section—
‘commencing day’ means—
(a) in relation to a variation of Schedule 7—4 December 1978;
(b) in relation to a variation of Schedule 7a—the day on which the States Grants (Tertiary Education Assistance) Amendment Act (No. 2) 1979 came into operation; or
(c) in relation to a variation of Schedule 7b—the day on which the States Grants (Tertiary Education Assistance) Amendment Act (No. 2) 1980 comes into operation;
‘relevant Schedule’ means Schedule 7, Schedule 7a or Schedule 7b.”.
Payments to be made out of Consolidated Revenue Fund or Loan Fund
23. Section 36 of the Principal Act is amended by omitting from paragraph (a) “16, 21, 21a, 21b, 21c, 29, 29a, 29b, 29c” and substituting “11d, 16, 21, 21a, 21b, 21c, 21d, 29, 29a, 29b, 29c, 29d”.
Authority to borrow
24. Section 37 of the Principal Act is amended by omitting “16, 21, 21a, 21b, 21c, 29, 29a, 29b, 29c” and substituting “11d, 16, 21, 21a, 21b, 21c, 21d, 29, 29a, 29b, 29c, 29d”.
Application of moneys borrowed
25. Section 38 of the Principal Act is amended by omitting “16, 21, 21a, 21b, 21c, 29, 29a, 29b, 29c” and substituting “11d, 16, 21, 21a, 21b, 21c, 21d, 29, 29a, 29b, 29c, 29d”.
Reimbursement of Consolidated Revenue Fund from Loan Fund
26. Section 39 of the Principal Act is amended by omitting “16, 21, 21a, 21b, 21c, 29, 29a, 29b, 29c” and substituting “11d, 16, 21, 21a, 21b, 21c, 21d, 29, 29a, 29b, 29c, 29d”.
Substitution of Schedules
27. (1) Schedules 1, 2, 3, 4, 5 and 6 to the Principal Act are repealed and the Schedules set out in Schedule 1 to this Act are substituted.
(2) Schedules 7a, 8, 8a, 9, 10, 11, 12 and 13 to the Principal Act are repealed and the Schedules set out in Schedule 2 to this Act are substituted.
Directions under Principal Act
28. A direction given by the Minister under sub-section 6(5), 14(4) or (5), 15(1), 26(1) or 31 (1) or (3) of the Principal Act or by the Tertiary Education Commission under sub-section 6(4), 14(3), 15(2), 26(2) or 31(2) of that Act shall, by force of this section, cease to have effect upon the commencement of this Act, but this section shall not be taken to affect the previous operation of the direction.
Payments made before Royal Assent
29. Payments (including advances) by way of financial assistance made to a State under the Principal Act shall be deemed to have been made for the purposes of the Principal Act as amended by this Act.
————————
SCHEDULE 1 Section 27(1)
New Schedules 1, 2, 3, 4, 5 and 6 to be inserted in the States Grants (Tertiary Education Assistance) Act 1978
——————
SCHEDULE 1 Section 6
GRANTS FOR EXPENDITURE BY UNIVERSITIES ON UNIVERSITY PURPOSES
Column 1 | Column 2 | Column 3 | Column 4 |
University | Amount of grant in respect of 1979 | Amount of grant in respect of 1980 | Amount of grant in respect of 1981 |
| $ | $ | $ |
New South Wales— |
|
|
|
University of Sydney.......................... | 77,789,000 | 83,990,000 | 86,205,000 |
The University of New South Wales................ | 75,417,000 | 81,467,000 | 83,732,000 |
University of New England...................... | 23,618,000 | 25,587,000 | 26,315,000 |
The University of Newcastle..................... | 19,717,000 | 21,691,000 | 22,526,000 |
The Macquarie University....................... | 29,252,000 | 31,510,000 | 32,291,000 |
The University of Wollongong.................... | 11,686,000 | 13,081,000 | 13,820,000 |
Total......................... | 237,479,000 | 257,326,000 | 264,889,000 |
Victoria— |
|
|
|
University of Melbourne........................ | 66,347,000 | 71,955,000 | 73,856,000 |
Monash University........................... | 55,153,000 | 59,404,000 | 60,864,000 |
La Trobe University........................... | 28,371,000 | 30,563,000 | 31,317,000 |
Deakin University............................ | 12,470,000 | 14,162,000 | 14,828,000 |
Total......................... | 162,341,000 | 176,084,000 | 180,865,000 |
Queensland— |
|
|
|
The University of Queensland.................... | 62,401,000 | 67,561,000 | 69,469,000 |
James Cook University of North Queensland.......... | 11,965,000 | 13,075,000 | 13,558,000 |
Griffith University............................ | 9,401,000 | 10,777,000 | 11,304,000 |
Total......................... | 83,767,000 | 91,413,000 | 94,331,000 |
South Australia— |
|
|
|
The University of Adelaide...................... | 40,570,000 | 43,665,000 | 44,739,000 |
The Flinders University of South Australia............ | 18,823,000 | 20,276,000 | 20,783,000 |
Total......................... | 59,393,000 | 63,941,000 | 65,522,000 |
Western Australia— |
|
|
|
The University of Western Australia................ | 38,216,000 | 41,249,000 | 42,336,000 |
Murdoch University........................... | 11,905,000 | 13,022,000 | 13,454,000 |
Total......................... | 50,121,000 | 54,271,000 | 55,790,000 |
Tasmania— |
|
|
|
University of Tasmania........................ | 19,055,000 | 20,581,000 | 21,136,000 |
TOTAL—ALL STATES............ | 612,156,000 | 663,616,000 | 682,533,000 |
————————
SCHEDULE 1—continued
SCHEDULE 2 Section 6(3)
SPECIAL PURPOSES IN RELATION TO GRANTS FOR EXPENDITURE BY UNIVERSITIES ON UNIVERSITY PURPOSES
Column 1 | Column 2 | Column 3 | Column 4 | Column 5 |
University | Purpose | Amount of Expenditure in respect of 1979 | Amount of Expenditure in respect of 1980 | Amount of Expenditure in respect of 1981 |
|
| $ | $ | $ |
University of Sydney......... | General Development or other University purposes, approved by the Commission | 521,000 | 564,000 | 580,000 |
| Law Extension Committee | 196,000 | 283,000 | 291,000 |
The University of New South Wales | Australian Graduate School of Management, for teaching and research | 1,332,000 | 1,574,000 | 1,753,000 |
| General Development or other University purposes, approved by the Commission | 493,000 | 534,000 | 550,000 |
The University of Newcastle.... | School of Medicine, for teaching and research | 1,862,000 | 2,463,000 | 2,831,000 |
University of Melbourne...... | General Development, or other University purposes, approved by the Commission | 439,000 | 475,000 | 489,000 |
Monash University.......... | Legal Workshop Course | 219,000 | 238,000 | 244,000 |
The University of Queensland | General Development, or other University purposes, approved by the Commission | 411,000 | 445,000 | 458,000 |
The University of Adelaide..... | General Development, or other University purposes, approved by the Commission | 274,000 | 297,000 | 305,000 |
The Flinders University of South Australia | School of Medicine, for teaching and research | 2,829,000 | .. | .. |
The University of Western Australia | General Development, or other University purposes, approved by the Commission | 274,000 | 297,000 | 305,000 |
Murdoch University......... | School of Veterinary Studies, for teaching and research | 2,061,000 | .. | .. |
University of Tasmania....... | General Development, or other University purposes, approved by the Commission | 219,000 | 238,000 | 244,000 |
—————
SCHEDULE 1—continued
SCHEDULE 3 Section 7
SPECIAL RESEARCH GRANTS FOR UNIVERSITIES
Column 1 | Column 2 | Column 3 | Column 4 |
University | Amount of grant in respect of 1979 | Amount of grant in respect of 1980 | Amount of grant in respect of 1981 |
| $ | $ | $ |
New South Wales— |
|
|
|
University of Sydney...................... | 828,000 | 897,000 | 922,000 |
The University of New South Wales............ | 735,000 | 796,000 | 818,000 |
University of New England.................. | 175,000 | 190,000 | 195,000 |
The University of Newcastle................. | 126,000 | 137,000 | 140,000 |
The Macquarie University................... | 225,000 | 243,000 | 250,000 |
The University of Wollongong................ | 71,000 | 77,000 | 79,000 |
Total....................... | 2,160,000 | 2,340,000 | 2,404,000 |
Victoria— |
|
|
|
University of Melbourne.................... | 844,000 | 914,000 | 940,000 |
Monash University....................... | 652,000 | 707,000 | 727,000 |
La Trobe University....................... | 219,000 | 238,000 | 244,000 |
Deakin University........................ | 33,000 | 36,000 | 37,000 |
Total....................... | 1,748,000 | 1,895,000 | 1,948,000 |
Queensland— |
|
|
|
The University of Queensland................ | 641,000 | 695,000 | 715,000 |
James Cook University of North Queensland...... | 66,000 | 71,000 | 73,000 |
Griffith University........................ | 49,000 | 53,000 | 55,000 |
Total....................... | 756,000 | 819,000 | 843,000 |
South Australia— |
|
|
|
The University of Adelaide.................. | 548,000 | 594,000 | 611,000 |
The Flinders University of South Australia........ | 121,000 | 131,000 | 134,000 |
Total....................... | 669,000 | 725,000 | 745,000 |
Western Australia— |
|
|
|
The University of Western Australia............ | 280,000 | 303,000 | 311,000 |
Murdoch University....................... | 55,000 | 59,000 | 61,000 |
Total....................... | 335,000 | 362,000 | 372,000 |
Tasmania— |
|
|
|
University of Tasmania.................... | 126,000 | 137,000 | 140,000 |
TOTAL—ALL STATES......... | 5,794,000 | 6,278,000 | 6,452,000 |
SCHEDULE 1—continued
SCHEDULE 4 Section 8
GRANTS FOR EQUIPMENT FOR UNIVERSITIES
Column 1 | Column 2 | Column 3 | Column 4 |
University | Grant for approved proposals in respect of 1979 | Grant for approved proposals in respect of 1980 | Grant for approved proposals in respect of 1981 |
| $ | $ | $ |
New South Wales— |
|
|
|
University of Sydney.......................... | 4,000,000 | 4,357,000 | 4,484,000 |
The University of New South Wales................ | 3,134,000 | 3,614,000 | 3,844,000 |
University of New England...................... | 658,000 | 772,000 | 846,000 |
The University of Newcastle..................... | 1,067,000 | 1,259,000 | 1,285,000 |
The Macquarie University....................... | 620,000 | 755,000 | 846,000 |
The University of Wollongong.................... | 675,000 | 709,000 | 712,000 |
Total......................... | 10,154,000 | 11,466,000 | 12,017,000 |
Victoria— |
|
|
|
University of Melbourne........................ | 3,265,000 | 3,591,000 | 3,715,000 |
Monash University........................... | 1,600,000 | 1,832,000 | 1,997,000 |
La Trobe University........................... | 560,000 | 743,000 | 862,000 |
Deakin University............................ | 778,000 | 783,000 | 764,000 |
Total......................... | 6,203,000 | 6,949,000 | 7,338,000 |
Queensland— |
|
|
|
The University of Queensland.................... | 3,232,000 | 3,602,000 | 3,767,000 |
James Cook University of North Queensland.......... | 522,000 | 567,000 | 568,000 |
Griffith University............................ | 305,000 | 312,000 | 372,000 |
Total......................... | 4,059,000 | 4,481,000 | 4,707,000 |
South Australia— |
|
|
|
The University of Adelaide...................... | 2,090,000 | 2,281,000 | 2,322,000 |
The Flinders University of South Australia............ | 642,000 | 715,000 | 717,000 |
Total......................... | 2,732,000 | 2,996,000 | 3,039,000 |
Western Australia— |
|
|
|
The University of Western Australia................ | 1,458,000 | 1,685,000 | 1,801,000 |
Murdoch University........................... | 337,000 | 420,000 | 464,000 |
Total......................... | 1,795,000 | 2,105,000 | 2,265,000 |
Tasmania— |
|
|
|
University of Tasmania........................ | 571,000 | 635,000 | 666,000 |
TOTAL—ALL STATES............ | 25,514,000 | 28,632,000 | 30,032,000 |
SCHEDULE 1—continued
SCHEDULE 5 Section 8(5)
SPECIFIED EQUIPMENT IN RELATION TO GRANTS FOR EQUIPMENT FOR UNIVERSITIES
Column 1 | Column 2 | Column 3 | Column 4 | Column 5 |
University | Equipment | Amount of expenditure on approved proposals in respect of 1979 | Amount of expenditure on approved proposals in respect of 1980 | Amount of expenditure on approved proposals in respect of 1981 |
|
| $ | $ | $ |
The University of Newcastle | Equipment for Medical School. | 386,00 | 578,000 | 364,000 |
| Library material for Medical Library | 62,000 | 69,000 | 72,000 |
——————
SCHEDULE 6 Section 10
GRANTS FOR RECURRENT EXPENDITURE OF TEACHING HOSPITALS OF UNIVERSITIES
Column 1 | Column 2 | Column 3 | Column 4 |
University | Grant in respect of 1979 | Grant in respect of 1980 | Grant in respect of 1981 |
| $ | $ | $ |
New South Wales— |
|
|
|
University of Sydney.......................... | 353,000 | 382,000 | 393,000 |
The University of New South Wales................ | 339,000 | 367,000 | 377,000 |
The University of Newcastle..................... | .. | 24,000 | 49,000 |
Total......................... | 692,000 | 773,000 | 819,000 |
Victoria— |
|
|
|
University of Melbourne........................ | 369,000 | 400,000 | 412,000 |
Monash University........................... | 218,000 | 236,000 | 243,000 |
Total......................... | 587,000 | 636,000 | 655,000 |
Queensland— |
|
|
|
The University of Queensland.................... | 248,000 | 268,000 | 276,000 |
South Australia— |
|
|
|
The University of Adelaide...................... | 225,000 | 243,000 | 250,000 |
The Flinders University of South Australia............ | 57,000 | 62,000 | 64,000 |
Total......................... | 282,000 | 305,000 | 314,000 |
Western Australia— |
|
|
|
The University of Western Australia................ | 121,000 | 131,000 | 134,000 |
Tasmania— |
|
|
|
University of Tasmania........................ | 60,000 | 65,000 | 67,000 |
TOTAL—ALL STATES............ | 1,990,000 | 2,178,000 | 2,265,000 |
—————
SCHEDULE 2 Section 27(2)
New Schedules 7a, 7b, 8, 8a, 9, 10, 11, 12 and 13 to be inserted in the States Grants (Tertiary Education Assistance) Act 1978
—————
SCHEDULE 7a Section 11b, 21b and 29b
PART I—GRANTS FOR SPECIFIED BUILDING PROJECTS OF UNIVERSITIES IN RESPECT OF 1980
Column 1 | Column 2 | Column 3 | Column 4 |
University | Project | Estimated cost to complete | Maximum grant in respect of 1980 |
New South Wales— |
| $ | $ |
University of Sydney............. | Westmead Hospital—Clinical teaching facilities | 3,461,000 | 3,122,000 |
The University of New South Wales... | Australian Graduate School of Management Building | 3,180,000 | 2,693,000 |
The University of Newcastle........ | Medical School—Clinical teaching facilities | 4,921,000 | 2,604,000 |
The University of Wollongong....... | Social Science Stage II Building | 1,183,000 | 1,027,000 |
Victoria— |
|
|
|
Monash University.............. | Microbiology Building............ | 1,572,000 | 1,354,000 |
Deakin University............... | Lecture Theatre................. | 11,000 | 11,000 |
Queensland— |
|
|
|
James Cook University of North Queensland | Tropical Veterinary Science Building | 292,000 | 211,000 |
| Electrical Engineering Building | 719,000 | 644,000 |
Griffith University............... | Lecture Theatre................. | 364,000 | 285,000 |
South Australia— |
|
|
|
The University of Adelaide......... | Medical School Building........... | 116,000 | 116,000 |
Western Australia— |
|
|
|
Murdoch University.............. | Animal Breeding Centre........... | 957,000 | 851,000 |
PART II—GRANTS FOR MINOR BUILDING PROJECTS OF UNIVERSITIES APPROVED BY THE COMMISSION IN RESPECT OF 1980
Column 1 | Column 2 |
University | Grant in respect of 1980 |
| $ |
University of Sydney......................................................... | 630,000 |
The University of New South Wales............................................... | 429,000 |
University of New England..................................................... | 259,000 |
The University of Newcastle.................................................... | 259,000 |
The Macquarie University..................................................... | 172,000 |
The University of Wollongong.................................................. | 172,000 |
University of Melbourne...................................................... | 630,000 |
Monash University.......................................................... | .. |
La Trobe University......................................................... | 172,000 |
Deakin University........................................................... | 298,000 |
The University of Queensland................................................... | 497,000 |
James Cook University of North Queensland......................................... | 172,000 |
SCHEDULE 2—continued
SCHEDULE 7a—continued
Column 1 | Column 2 |
University | Grant in respect of 1980 |
| $ |
Griffith University.......................................................... | 166,000 |
The University of Adelaide.................................................... | 298,000 |
The Flinders University of South Australia.......................................... | 166,000 |
The University of Western Australia.............................................. | 259,000 |
Murdoch University......................................................... | 166,000 |
University of Tasmania...................................................... | 314,000 |
PART III—GRANTS FOR SPECIFIED BUILDING PROJECTS OF COLLEGES OF ADVANCED EDUCATION IN RESPECT OF 1980
Column 1 | Column 2 | Column 3 | Column 4 |
College of Advanced Education | Project | Estimated cost to complete | Maximum grant in respect of 1980 |
New South Wales |
| $ | $ |
Alexander Mackie College of Advanced Education | Completion of Teaching and Administration building | 1,148,000 | 1,088,000 |
Newcastle College of Advanced Education | Art building................... | 557,000 | 528,000 |
Northern Rivers College of Advanced Education | Relocation on new campus......... | 9,251,000 | 422,000 |
Riverina College of Advanced Education | Information Resources Centre | 334,000 | 317,000 |
The New South Wales Institute of Technology | Extension of Building 2 | 1,226,000 | 1,162,000 |
Union building | 1,081,000 | 1,024,000 | |
| Design of building for joint use with Sydney Teachers College | .. | 211,000 |
Total New South Wales............................. |
| 4,752,000 | |
Victoria |
|
|
|
Bendigo College of Advanced Education | Education building | 981,000 | 929,000 |
Library/Union—Stage 2 | 2,876,000 | 1,985,000 | |
Footscray Institute of Technology | Physical Education Centre | 1,338,000 | 1,267,000 |
Refurbishing of existing building | 1,115,000 | 211,000 | |
Royal Melbourne Institute of Technology | Erection of Union............... | 4,728,000 | 2,450,000 |
The Victorian College of the Arts | Academic building............... | 2,975,000 | 2,482,000 |
Warrnambool Institute of Advanced Education | Buildings for Art and Design, Administration, Computer and Student Amenities | 167,000 | 158,000 |
Total—Victoria................................... |
| 9,482,000 | |
SCHEDULE 2—continued
SCHEDULE 7a—continued
Column 1 | Column 2 | Column 3 | Column 4 |
College of Advanced Education | Project | Estimated cost to complete | Maximum grant in respect of 1980 |
|
| $ | $ |
Queensland |
|
|
|
Queensland Agricultural College | Animal Products Technology facilities | 713,000 | 676,000 |
Queensland Institute of Technology | Business Studies building......... | 3,567,000 | 422,000 |
Total Queensland................................. |
| 1,098,000 | |
South Australia |
|
|
|
Adelaide College of the Arts and Education | Completion of Underdale campus | 2,062,000 | 1,954,000 |
Total South Australia............................... |
| 1,954,000 | |
Western Australia - |
|
|
|
Churchlands College............ | Lecture theatre | 290,000 | 275,000 |
Western Australian Institute of Technology | Health Science building | 111,000 | 106,000 |
Applied Science building | 78,000 | 74,000 | |
Total— Western Australia............................ |
| 455,000 | |
Tasmania— |
|
|
|
Tasmanian College of Advanced Education | Engineering facilities. | 892,000 | 634,000 |
Total—Tasmania.................................. |
| 634,000 | |
TOTAL—ALL STATES............................ |
| 18,375,000 | |
PART IV—GRANTS FOR MINOR BUILDING PROJECTS FOR COLLEGES OF ADVANCED EDUCATION IN RESPECT OF 1980
Column 1 | Column 2 |
State | Grant in respect of 1980 |
| $ |
New South Wales.......................................................... | 1,560,000 |
Victoria................................................................. | 2,173,000 |
Queensland.............................................................. | 892,000 |
South Australia............................................................ | 669,000 |
Western Australia.......................................................... | 502,000 |
Tasmania................................................................ | 167,000 |
TOTAL—ALL STATES........................................ | 5,963,000 |
SCHEDULE 2—continued
SCHEDULE 7a—continued
PART V—GRANTS FOR SPECIFIED DESIGN PROJECTS OF COLLEGES OF ADVANCED EDUCATION
Column 1 | Column 2 |
College of Advanced Education | Project |
New South Wales |
|
Hawkesbury Agricultural College....................... | Design of Applied Science building |
Western Australia - |
|
Western Australian Institute of Technology................. | Design of Technology building at Western Australian School of Mines |
Total of all grants payable in respect of design projects specified in this Part of this Schedule— $211,000.
PART VI—GRANTS FOR SPECIFIED BUILDING PROJECTS OF TECHNICAL AND FURTHER EDUCATION INSTITUTIONS IN RESPECT OF 1980
Column 1 | Column 2 | Column 3 | Column 4 |
Institutions Providing Technical and Further Education | Project | Estimated Commonwealth Contribution Toward Cost to Complete | Maximum Grant in Respect of 1980 |
|
| $ | $ |
New South Wales— |
|
|
|
Brookvale Technical College | Stages II and III: Buildings for trade and fashion courses | 5,684,000 | 1,355,000 |
Campbelltown Technical College | Buildings for secretarial, fashion and trade courses | 2,878,000 | 2,300,000 |
Glendale Technical College | Buildings for engineering trades and commercial courses | 6,729,000 | 4,486,000 |
Gymea Technical College | Stage IV: Replacement buildings for automotive and engineering trades | 2,714,000 | 560,000 |
Hornsby Technical College | Buildings for automotive and electrical trades and for student services | 1,078,000 | 1,012,000 |
Miller Technical College | Stage II: Building for metal fabrication courses | 860,000 | 634,000 |
Mount Druitt Technical College | Stage I: Buildings for student services, electrical and building trades | 356,000 | 327,659 |
| Stage II: Buildings for automotive and commercial courses | 3,791,000 | 3,100,000 |
| Stage III: Building for metal fabrication courses | 648,000 | 530,000 |
North Sydney Technical College | Stage V: Building for trade courses | 1,105,000 | 1,022,838 |
Padstow Technical College | Buildings for automotive, commercial and horticulture courses | 2,651,000 | 2,400,000 |
Shellharbour Technical College | Stage II: Buildings for student services, trade and commercial courses | 5,176,000 | 1,465,000 |
Sydney Technical College | Stage II: Building for business and administrative studies | 2,409,000 | 2,100,000 |
| Reconstruction of building 13; admissions and information centre | 1,479,000 | 850,000 |
| Buildings 38 and 39 Stage I: Reconstruction for business, engineering and navigation studies | 2,147,000 | 1,400,000 |
| Stage IIIa: Building for library, general studies and chiropody | 7,904,000 | 1,373,000 |
SCHEDULE 2—continued
SCHEDULE 7a—continued
Column 1 | Column 2 | Column 3 | Column.4 |
Institutions Providing Technical and Further Education | Project | Estimated Commonwealth Contribution Toward Cost to Complete | Maximum Grant in Respect of 1980 |
|
| $ | $ |
Tamworth Technical College | Stage IV: Building for student services and metal fabrication courses | 2,319,000 | 528,000 |
Wetherill Park Technical College | Buildings for trade courses, college services and administration | 2,640,000 | 1,250,000 |
Wollongong Technical College | Stage VI: Building for foundry and laboratories | 1,354,000 | 1,007,000 |
| Stage VII: Building for secretarial studies and extension to Union building | 2,152,000 | 520,000 |
Victoria— |
|
|
|
Ballarat School of Mines | Stage I: Buildings for trade courses and student services | 3,060,000 | 1,876,000 |
Box Hill Technical College | Stage I: Buildings for engineering, building trades and metal fabrication courses | 2,617,000 | 2,274,000 |
| Stage II: Building for humanities, science studies, food catering and student services | 6,684,000 | 3,506,000 |
| Stage III: Building for technician courses | 3,521,000 | 1,400,000 |
Collingwood Technical College | Stage II: Building for mid-level courses, student and staff services | 2,339,000 | 2,000,000 |
Longerenong Agricultural College | Stage II: Building for library | 314,000 | 305,000 |
McMillan Rural Studies Centre | Stage I: Building for base facility containing teaching areas, library, college administration and subsidiary teaching centres | 3,479,000 | 300,000 |
Newport Technical College | Stage II: Buildings for electrical and building courses | 3,028,000 | 2,699,000 |
Preston Technical College | Stage I: Buildings for library and classrooms | 444,000 | 364,000 |
| Stage II: Building for applied science and business studies courses | 2,240,000 | 2,048,000 |
Royal Melbourne Institute of Technology | Stage IIb: Building for engineering studies | 10,173,000 | 2,201,000 |
Sunraysia College of Technical and Further Education | Stage I: Buildings for commercial, applied science, food and trade courses | 5,377,000 | 1,400,000 |
Yallourn Technical College | Buildings for trade courses | 4,491,000 | 1,400,000 |
Queensland- |
|
|
|
Bald Hills College of Technical | Stage I: Buildings for school of technology | 1,340,000 | 839,000 |
and Further Education | Stage II: Site development | 1,473,000 | 1,369,000 |
| Stage III: Buildings for library, catering and science courses | 3,417,000 | 845,000 |
Gladstone College of Technical and Further Education | Stage I: Buildings for trade and commercial courses, library and amenities areas | 3,670,000 | 739,000 |
Gold Coast College of Technical and Further Education | Stage I: Building for tourist industry, business and general studies courses, library, student and staff services | 3,833,000 | 845,000 |
Ipswich College of Technical | Stage I: Building for trade courses | 606,000 | 286,000 |
and Further Education | Stage II: Building for library, commercial studies, arts and crafts courses | 3,043,000 | 3,043,000 |
SCHEDULE 2—continued
SCHEDULE 7a—continued
Column 1 | Column 2 | Column 3 | Column 4 |
Institutions Providing Technical and Further Education | Project | Estimated Commonwealth Contribution Toward Cost to Complete | Maximum Grant in Respect of 1980 |
|
| $ | $ |
| Stage III: Design of buildings for commercial studies, catering and applied science courses | .. | 211,000 |
Mount Gravatt College of Technical and Further | Stage II: Building for engineering trades and secretarial studies | 1,855,000 | 1,695,000 |
Education | Stage III: Design of building for applied science, food and craft courses, commercial studies, staff and student services | .. | 106,000 |
| Stage IV: Design of building for library and art studies courses | .. | 106,000 |
South Australia— |
|
|
|
Elizabeth Community College | Stage III: Building for business studies courses, cafeteria, staff and student services | 1,774,000 | 1,467,000 |
Gillies Plains Community College | Stage I: Buildings for paradental, applied science, commercial and building courses | 1,718,000 | 1,659,000 |
| Stage II: Building for building trades courses | 1,422,000 | 1,373,000 |
Kilkenny Open College of Further Education | Design for reconstruction of vacated building to provide for Open College of Further Education | .. | 53,000 |
Marleston College of Further Education | Design for reconstruction of college | .. | 106,000 |
Noarlunga Community College | Stage I: Construction of multi-purpose college | 9,940,000 | 3,908,000 |
Regency Park Community College | Design of building for plumbing trades | .. | 53,000 |
Riverland Community College; Loxton Branch | Design of multi-purpose facility for commercial, rural and technical studies | .. | 11,000 |
South East Community College | Stage II: Building for rural and timber studies courses | 389,000 | 337,000 |
Western Australia— |
|
|
|
Bentley Technical College | Stage IV: Buildings for forestry, horticulture, animal care and fashion studies courses | 2,009,000 | 1,861,000 |
Carine Technical College | Stage II: Buildings for catering trades and arts/crafts courses | 1,597,000 | 1,499,000 |
Hedland College | Design of regional college for electrical, automotive and metal trades courses, commercial science and art studies | .. | 222,000 |
Rockingham Technical College | Stage II: Buildings for fitting and machining and automotive studies and student amenities | 2,322,000 | 1,559,000 |
Technical Education Division—Technical Extension Service | Stage II: Building to accommodate teaching staff | 2,626,000 | 100,000 |
Thornlie Technical College | Stage I: Buildings for electrical, metal trades and heavy plant and equipment maintenance courses | 4,614,000 | 4,118,000 |
SCHEDULE 2—continued
SCHEDULE 7a—continued
Column 1 | Column 2 | Column 3 | Column 4 |
Institutions Providing Technical and Further Education | Project | Estimated Commonwealth Contribution Toward Cost to Complete | Maximum Grant in Respect of 1980 |
|
| $ | $ |
Tasmania— |
|
|
|
Hobart Technical College | Stage II: Building for technical and general courses | 8,309,000 | 4,120,000 |
Northern Territory— |
|
|
|
Darwin Community College | Extensions to the school of trades | 2,197,000 | 1,373,000 |
| Technology and science building | 1,112,000 | 1,056,000 |
Batchelor College | Replacement for Aboriginal teacher education centre | 3,634,000 | 739,000 |
PART VII—SUMMARY OF GRANTS TO STATES FOR SPECIFIED BUILDING PROJECTS OF TECHNICAL AND FURTHER EDUCATION INSTITUTIONS IN RESPECT OF 1980
Column 1 | Column 2 |
State | Total grant in respect of 1980 |
| $ |
New South Wales......................................................... | 28,220,497 |
Victoria................................................................ | 21,773,000 |
Queensland............................................................. | 10,084,000 |
South Australia........................................................... | 8,967,000 |
Western Australia......................................................... | 9,359,000 |
Tasmania............................................................... | 4,120,000 |
Northern Territory......................................................... | 3,168,000 |
Total—All States................................................. | 85,691,497 |
PART VIII—ADDITIONAL GRANTS FOR MAJOR BUILDING PROJECTS OF UNIVERSITIES
Total of additional grants—$717,000
SCHEDULE 2—continued
SCHEDULE 7a—continued
PART IX—ADDITIONAL GRANTS FOR MAJOR BUILDING PROJECTS OF COLLEGES OF ADVANCED EDUCATION AND TECHNICAL AND FURTHER EDUCATION INSTITUTIONS
Column 1 | Column 2 | Column 3 |
State | Total of additional grants for major building projects of colleges of advanced education | Total of additional grants for major building projects of technical and further education institutions |
| $ | $ |
New South Wales.......................................... | 267,000 | 791,503 |
Victoria................................................. | 527,000 | 892,000 |
Queensland.............................................. | 61,000 | 558,000 |
South Australia............................................ | 108,000 | 496,000 |
Western Australia.......................................... | 32,000 | 9,000 |
Tasmania................................................ | 35,000 | 4,000 |
Northern Territory.......................................... | .. | 176,000 |
Total—All States............................. | 1,030,000 | 2,926,503 |
—————
SCHEDULE 7b Sections 11d, 21d and 29d
PART I—GRANTS FOR SPECIFIED BUILDING PROJECTS OF UNIVERSITIES IN RESPECT OF 1981
Column 1 | Column 2 | Column 3 | Column 4 |
University | Project | Estimated cost to complete | Maximum grant in respect of 1981 |
|
| $ | $ |
New South Wales— |
|
|
|
The University of New South Wales | Australian Graduate School of Management Building | 428,000 | 428,000 |
University of New England....... | Dixon Library Extension............ | 2,590,000 | 482,000 |
The University of Newcastle | Medical School—Clinical Teaching Facilities | 2,034,000 | 2,034,000 |
Victoria— |
|
|
|
University of Melbourne......... | Refurbishing of Chemistry Building—Stage I | 1,070,000 | 321,000 |
Queensland— |
|
|
|
The University of Queensland | Social Sciences (Psychology) Building—Stage II | 2,676,000 | 589,000 |
SCHEDULE 2—continued
SCHEDULE 7b—continued
PART II—GRANTS FOR MINOR BUILDING PROJECTS OF UNIVERSITIES APPROVED BY THE COMMISSION IN RESPECT OF 1981
Column 1 | Column 2 |
University | Grant in respect of 1981 |
| $ |
University of Sydney.......................................... | 642,000 |
The University of New South Wales................................ | 428,000 |
University of New England...................................... | 268,000 |
The University of Newcastle..................................... | 268,000 |
The Macquaric University ,...................................... | 161,000 |
The University of Wollongong................................... | 214,000 |
University of Melbourne....................................... | 642,000 |
Monash University........................................... | 268,000 |
La Trobe University.......................................... | 214,000 |
Deakin University .,.......................................... | 321,000 |
The University of Queensland.................................... | 535,000 |
James Cook University of North Queensland.......................... | 214,000 |
Griffith University .,.......................................... | 161,000 |
The University of Adelaide...................................... | 321,000 |
The Flinders University of South Australia........................... | 161,000 |
The University of Western Australia................................ | 268,000 |
Murdoch University.......................................... | 161,000 |
University of Tasmania........................................ | 375,000 |
PART III—SPECIFIED DESIGN PROJECTS OF UNIVERSITIES
Column 1 | Column 2 |
University | Project |
New South Wales— |
|
University of Newcastle.................. | Design of Animal House |
Queensland— |
|
The University of Queensland.............. | Design of Clinical Sciences Building |
Western Australia— |
|
The University of Western Australia......... | Design of Human Performance Building |
Tasmania— |
|
The University of Tasmania............... | Design of Clinical Sciences Building |
Total of all grants payable in respect of design projects specified in this Part of this Schedule—$268,000.
SCHEDULE 2—continued
SCHEDULE 7b—continued
PART IV—GRANTS FOR SPECIFIED BUILDING PROJECTS OF COLLEGES OF ADVANCED EDUCATION IN RESPECT OF 1981
Column 1 | Column 2 | Column 3 | Column 4 |
College of Advanced Education | Project | Estimated Cost to Complete | Maximum Grant in Respect of 1981 |
|
| $ | $ |
New South Wales— |
|
|
|
Northern Rivers College of Advanced Education | Relocation on new campus—Stage 1 | 2,783,000 | 1,827,000 |
The New South Wales Institute of Technology | Building for joint use with Sydney Teachers College | 12,266,000 | 428,000 |
Total—New South Wales.................... |
| 2,255,000 | |
Victoria— |
|
|
|
Bendigo College of Advanced Education | Library/union—Stage 2 | 856,000 | 856,000 |
Footscray Institute of Technology | Refurbishing of existing building | 856,000 | 856,000 |
Royal Melbourne Institute of | Erection of union | 2,740,000 | 2,141,000 |
Technology | Renovation of buildings 5, 7 & | 1,070,000 | 428,000 |
| 9—Stage 1 |
|
|
The Victorian College of the Arts | Academic building . | 535,000 | 535,000 |
Total—Victoria.......................... |
| 4,816,000 | |
Queensland— |
|
|
|
Queensland Institute of Technology | Business studies building . | 3,425,000 | 3,211,000 |
Total—Queensland........................ |
| 3,211,000 | |
South Australia— |
|
|
|
Adelaide College of the Arts and Education | Fire protection, Kintore Avenue campus | 514,000 | 268,000 |
Total—South Australia..................... |
| 268,000 | |
Western Australia— |
|
|
|
Western Australian Institute of Technology | Technology building at School of Mines—Kalgoorlie | 1,755,000 | 428,000 |
Total—Western Australia.................... |
| 428,000 | |
Tasmania— |
|
|
|
Tasmanian College of Advanced Education | Engineering facilities. | 225,000 | 225,000 |
Total—Tasmania......................... |
| 225,000 | |
TOTAL—ALL STATES.................... |
| 11,203,000 | |
SCHEDULE 2—continued
SCHEDULE 7b—continued
PART V—GRANTS FOR MINOR BUILDING PROJECTS FOR COLLEGES OF ADVANCED EDUCATION IN RESPECT OF 1981
Column 1 | Column 2 |
State | Grant in respect of 1981 |
| $ |
New South Wales........................................................ | 1,632,000 |
Victoria............................................................... | 2,274,000 |
Queensland............................................................. | 963,000 |
South Australia.......................................................... | 696,000 |
Western Australia........................................................ | 535,000 |
Tasmania.............................................................. | 161,000 |
Total—All States........................................... | 6,261,000 |
PART VI—GRANTS FOR SPECIFIED DESIGN PROJECTS OF COLLEGES OF ADVANCED EDUCATION
Column 1 | Column 2 |
College of Advanced Education | Project |
New South Wales— |
|
Alexander Mackie College of Advanced Education | Refurbishing Albion Avenue Campus |
Nepean College of Advanced Education.................. | Teaching Building, Westmead |
Northern Rivers College of Advanced Education............ | Relocation on New Campus—Stage 2 |
Total of all grants payable in respect of design projects specified in this Part of this Schedule-$207,000.
PART VII—GRANTS FOR SPECIFIED BUILDING PROJECTS OF TECHNICAL AND FURTHER EDUCATION INSTITUTIONS IN RESPECT OF 1981
Column 1 | Column 2 | Column 3 | Column 4 |
Institutions providing technical and further education | Project | Estimated Commonwealth contribution toward cost to complete | Maximum grant in respect of 1981 |
|
| $ | $ |
New South Wales— |
|
|
|
Baulkham Hills Technical College | Stage I: Buildings for secretarial, fashion, home science courses, library and college administration | 3,824,000 | 409,000 |
Blacktown Technical College | Stage III: Reconstruction of factory for automotive, carpentry and secretarial courses and student services | 5,617,000 | 1,222,000 |
Brookvale Technical College | Stages II and III: Buildings for trade and fashion courses | 4,310,000 | 3,904,000 |
Campbelltown Technical College | Building for secretarial, fashion and trade courses | 499,000 | 499,000 |
SCHEDULE 2—continued
SCHEDULE 7b—continued
Column 1 | Column 2 | Column 3 | Column 4 |
Institutions providing technical and further education | Project | Estimated Commonwealth contribution toward cost to complete | Maximum grant in respect of 1981 |
|
| $ | $ |
Forbes Technical College........ | Stage II: Extension to existing building for secretarial and fashion courses and student services | 1,040,000 | 249,000 |
Glendale Technical College | Buildings for engineering trades and commercial courses | 2,351,000 | 2,351,000 |
Gymea Technical College........ | Stage IV: Replacement buildings for automotive and engineering trades | 2,225,000 | 2,195,000 |
Hornsby Technical College | Buildings for automotive and electrical trades and student services | 61,000 | 61,000 |
Miller Technical College......... | Stage II: Building for metal fabrication courses | 228,000 | 228,000 |
Mount Druitt Technical College | Stage II: Buildings for automotive and commercial courses | 760,000 | 760,000 |
| Stage III: Building for metal fabrication courses | 164,000 | 164,000 |
Newcastle Technical College (Tighes Hill) | Stage X: Building for electrical trades courses | 6,373,000 | 724,000 |
North Sydney Technical College | Stage V: Building for trade courses | 81,000 | 81,000 |
Padstow Technical College | Buildings for automotive, commercial and horticulture courses | 603,000 | 603,000 |
Petersham Technical College | Stage III: Building for secretarial and hairdressing courses, library and student services | 4,137,000 | 1,493,000 |
Shellharbour Technical College | Stage II: Buildings for student services, trade and commercial courses | 3,668,000 | 3,324,000 |
Sydney Technical College........ | Stage II: Building for business and administrative studies | 241,000 | 241,000 |
| Reconstruction of building 13; admissions and information centre | 675,000 | 675,000 |
| Buildings 38 and 39 Stage I: Reconstruction for business, engineering and navigation studies | 366,000 | 366,000 |
| Stage III A: Building for library, general studies and chiropody | 6,970,000 | 3,958,000 |
| Buildings 38 and 39 Stage II: Reconstruction for secretarial studies and general classrooms | 2,721,000 | 1,900,000 |
Tamworth Technical College | Stage IV: Building for student services and metal fabrication courses | 1,931,000 | 1,931,000 |
| Stage V: Buildings for plumbing, plant mechanics and general classrooms | 2,394,000 | 615,000 |
Wagga Wagga Technical College | Stage IV: Building for panel-beating and spray-painting workshops | 2,306,000 | 348,000 |
Wetherill Park Technical College | Buildings for trade courses, college services and administration | 1,467,000 | 1,467,000 |
Wollongong Technical College | Stage VI: Building for foundry and laboratories | 303,000 | 303,000 |
| Stage VII: Building for secretarial studies and extension to Union building | 1,884,000 | 1,794,000 |
SCHEDULE 2—continued
SCHEDULE 7b—continued
Column 1 | Column 2 | Column 3 | Column 4 |
Institutions providing technical and further education | Project | Estimated Commonwealth Contribution toward cost to complete | Maximum grant in respect of 1981 |
|
| $ | $ |
| Stage VIII: Building for panel-beating and spray-painting workshops | 2,420,000 | 372,000 |
Wyong Technical College........... | Stage I: Buildings for plumbing, secretarial, home science and fashion courses, student services and college administration | 4,249,000 | 1,583,000 |
Victoria— |
|
|
|
Ballarat School of Mines | Stage I: Buildings for trade courses and student services | 1,340,000 | 1,249,000 |
Box Hill Technical College | Stage II: Building for humanities, science studies, food catering and student services | 3,712,000 | 2,778,000 |
| Stage III: Building for technician courses | 2,026,000 | 1,924,000 |
Central Metropolitan Regional College (La Trobe Street) | Stage I: Building for library, computer centre, student services and college administration | 4,076,000 | 1,531,000 |
Dandenong Valley Regional College | Stage II: Design of buildings for trade, computer studies and applied art courses, student services and college administration | .. | 369,000 |
Goulburn Valley Regional College (Shepparton) | Stage II: Design of buildings for trade courses, library, student services and college administration | .. | 274,000 |
Loddon Valley Regional College (Bendigo) | Stage I: Buildings for trade, farm mechanics, art and design courses | 5,756,000 | 1,320,000 |
McMillan Rural Studies Centre (Warragul, Sale, Bairnsdale, Leongatha) | Stage I: Buildings for base facility containing teaching areas, library, college administration and subsidiary teaching centres | 3,371,000 | 2,934,000 |
North-Eastern Regional College (Wangaratta) | Stage II: Buildings for business studies, science and art courses, library and student services | 5,167,000 | 1,531,000 |
Royal Melbourne Institute of Technology | Stage 11b: Building for engineering studies | 8,476,000 | 3,962,000 |
Sunraysia College of Technical and Further Education | Stage I: Buildings for commercial, applied science, food and trade courses | 4,209,000 | 2,988,000 |
Western Metropolitan Regional College (Footscray) | Stage II: Building for engineering, humanities and social science courses, library, student services and college administration | 8,385,000 | 1,320,000 |
Yallourn Technical College | Buildings for trade courses................ | 3,064,000 | 2,768,000 |
Queensland— |
|
|
|
Bald Hills College of Technical and Further Education | Stage I: Buildings for school of technology | 109,000 | 109,000 |
| Stage III: Buildings for library, catering and science courses | 2,800,000 | 2,217,000 |
College of Catering and Hospitality Services (Coorparoo) | Stage II: Extension to provide additional practical and demonstration kitchens | 528,000 | 528,000 |
College of Hospitality and Tourism (South Brisbane) | Stage I: Building for school of catering and hospitality services | 8,443,000 | 1,161,000 |
SCHEDULE 2—continued
SCHEDULE 7b—continued
Column 1 | Column 2 | Column 3 | Column 4 |
Institutions providing technical and further education | Project | Estimated Commonwealth contribution toward cost to complete | Maximum grant in respect of 1981 |
|
| $ | $ |
Gladstone College of Technical and Further Education | Stage I: Buildings for trade and commercial courses, library and amenities areas | 3,074,000 | 2,321,000 |
Gold Coast College of Technical and Further Education | Stage I: Building for tourist industry, business and general studies courses, library, student and staff services | 3,135,000 | 2,217,000 |
| Stage II: Buildings for automotive, electrical and building trades | 2,455,000 | 1,477,000 |
Ipswich College of Technical and Further Education | Stage I: Building for trade courses Stage III: Design of buildings for commercial studies, catering and applied science courses | 256,000 | 256,000 211,000 |
Mount Gravatt College of Technical and Further Education | Stage III: Building for applied science, food course, commercial studies, student services and college administration | 5,175,000 | 1,266,000 |
| Stage IV: Building for library and arts and crafts courses | 1,788,000 | 422,000 |
Townsville College of Technical and Further Education (Pimlico) | Stage II: Design of buildings for school of catering and hospitality services | .. | 317,000 |
South Australia— |
|
|
|
Elizabeth Community College | Stage III: Building for business studies courses, cafeteria, staff and student services | 342,000 | 342,000 |
Gilles Plains Community College | Stage I: Buildings for paradental, applied science, commercial and building courses | 11,000 | 11,000 |
| Stage II: Building for building trades courses | 22,000 | 22,000 |
Marleston College of Further Education | Stage I: Reconstruction of college for building trades | 3,855,000 | 1,269,000 |
Noarlunga Community College | Stage I: Construction of multi-purpose college | 6,100,000 | 3,719,000 |
Port Adelaide Community College | Stage I: Reconstruction of building for business and commercial studies, library and college administration | 844,000 | 844,000 |
Regency Park Community College | Stage V: Building for plumbing trades | 2,727,000 | 2,410,000 |
Riverland Community College (Loxton) | Stage I: Multi-purpose facility for commercial, rural and technical studies | 578,000 | 147,000 |
South East Community College | Stage II: Building for rural and timber studies courses | 59,000 | 59,000 |
Western Australia— |
|
|
|
Albany Technical College...... | Stage VI: Extension to existing automotive workshop | 264,000 | 264,000 |
Bentley Technical College | Stage IV: Buildings for forestry, horticulture, animal care and fashion studies courses | 196,000 | 196,000 |
Carine Technical College...... | Stage II: Buildings for catering trades and arts/crafts courses | 127,000 | 127,000 |
SCHEDULE 2—continued
SCHEDULE 7b—continued
Column 1 | Column 2 | Column 3 | Column 4 |
Institutions providing technical and further education | Project | Estimated Commonwealth contribution toward cost to complete | Maximum grant in respect of 1981 |
|
| $ | $ |
Hedland Community College | Stage I: Buildings for electrical, automotive, metal trades, commercial, science and art courses | 6,108,000 | 1,583,000 |
Rockingham Technical College | Stage II: Buildings for fitting and machining and automotive studies and student amenities | 3,614,000 | 2,721,000 |
Technical Education Division—Technical Extension Service | Stage II: Building to accommodate teaching staff | 2,683,000 | 2,184,000 |
Thornlie Technical College | Stage I: Buildings for electrical, metal trades and heavy plant and equipment maintenance courses | 506,000 | 506,000 |
| Stage II: Buildings for furniture and building trades courses and a pump test facility | 2,825,000 | 2,321,000 |
Tasmania— |
|
|
|
Alanvale Community College | Stage I: Design of building for electrical and electronic trade courses | .. | 107,000 |
Hobart Technical College....... | Stage II: Building for technical and general courses | 4,480,000 | 4,480,000 |
Northern Territory— |
|
|
|
Darwin Community College | Extensions to the school of trades | 871,000 | 871,000 |
Batchelor College............ | Replacement for Aboriginal teacher education centre | 2,929,000 | 2,476,000 |
PART VIII—SUMMARY OF GRANTS TO STATES FOR SPECIFIED BUILDING PROJECTS OF TECHNICAL AND FURTHER EDUCATION INSTITUTIONS IN RESPECT OF 1981
Column 1 | Column 3 |
State | Total grant in respect of 1981 |
| $ |
New South Wales....................................................... | 33,820,000 |
Victoria............................................................. | 24,948,000 |
Queensland........................................................... | 12,502,000 |
South Australia........................................................ | 8,823,000 |
Western Australia....................................................... | 9,902,000 |
Tasmania............................................................ | 4,587,000 |
Northern Territory...................................................... | 3,347,000 |
Total—All States............................................ | 97,929,000 |
———————
SCHEDULE 2—continued
SCHEDULE 8 Section 14
PART 1—GRANTS FOR EXPENDITURE BY COLLEGES OF ADVANCED EDUCATION ON COLLEGE PURPOSES
Column 1 | Column 2 | Column 3 | Column 4 |
Colleges of Advanced Education | Grant in respect of 1979 | Grant in respect of 1980 | Grant in respect of 1981 |
| $ | $ | $ |
New South Wales— |
|
|
|
Alexander Mackie College of Advanced Education | 5,020,000 | 5,433,000 | 5,600,000 |
Armidale College of Advanced Education............ | 3,857,000 | 4,186,000 | 4,309,000 |
Catholic College of Education.................... | 1,289,000 | 1,431,000 | 1,432,000 |
Catholic Teachers College...................... | 2,418,000 | 2,579,000 | 2,654,000 |
Cumberland College of Health Sciences............. | 5,408,000 | 5,874,000 | 6,054,000 |
Good Samaritan Teachers College................. | 397,000 | 343,000 | 405,000 |
Goulburn College of Advanced Education............ | 3,104,000 | 3,234,000 | 3,288,000 |
Hawksbury Agricultural College.................. | 4,864,000 | 5,345,000 | 5,504,000 |
Kuring-gai College of Advanced Education........... | 6,875,000 | 7,322,000 | 7,541,000 |
Mitchell College of Advanced Education............ | 8,027,000 | 8,741,000 | 9,008,000 |
Nepean College of Advanced Education............. | 3,326,000 | 3,591,000 | 3,702,000 |
New South Wales Conservatorium of Music.......... | 1,918,000 | 2,106,000 | 2,170,000 |
Newcastle College of Advanced Education........... | 7,876,000 | 8,305,000 | 8,580,000 |
Northern Rivers College of Advanced Education....... | 2,665,000 | 2,898,000 | 2,986,000 |
Nursery School Teachers College................. | 781,000 | 833,000 | 858,000 |
Orange Agricultural College..................... | 1,195,000 | 1,436,000 | 1,488,000 |
Riverina College of Advanced Education............ | 8,865,000 | 9,724,000 | 10,022,000 |
Sydney College of the Arts...................... | 2,661,000 | 2,879,000 | 2,974,000 |
Sydney Kindergarten Teachers College.............. | 1,101,000 | 1,184,000 | 1,219,000 |
Sydney Teachers College....................... | 8,439,000 | 9,130,000 | 9,398,000 |
The Guild Teachers College..................... | 1,143,000 | 1,221,000 | 1,256,000 |
The Milperra College of Advanced Education......... | 2,217,000 | 2,467,000 | 2,542,000 |
The New South Wales Institute of Technology......... | 18,922,000 | 20,739,000 | 21,366,000 |
Wollongong Institute of Education................. | 3,284,000 | 3,440,000 | 3,449,000 |
Total............................ | 105,652,000 | 114,441,000 | 117,805,000 |
Victoria— |
|
|
|
State College of Victoria— |
|
|
|
State College of Victoria, Burwood............. | 4,964,000 | 5,323,000 | 5,443,000 |
State College of Victoria, Coburg............... | 3,861,000 | 4,199,000 | 4,249,000 |
State College of Victoria, Frankston............. | 3,530,000 | 3,738,000 | 3,832,000 |
State College of Victoria, Hawthorn............. | 4,323,000 | 4,736,000 | 4,798,000 |
State College of Victoria, Institute of Catholic Education | 3,879,000 | 4,343,000 | 4,398,000 |
|
|
| |
State College of Victoria, Institute of Early Childhood Development | 2,384,000 | 2,601,000 | 2,656,000 |
|
|
| |
State College of Victoria, Melbourne............ | 12,806,000 | 13,551,000 | 13,884,000 |
State College of Victoria, Rusden............... | 6,748,000 | 7,303,000 | 7,442,000 |
State College of Victoria, Toorak............... | 4,184,000 | 4,543,000 | 4,638,000 |
Total............................ | 46,679,000 | 50,337,000 | 51,340,000 |
Victoria Institute of Colleges— |
|
|
|
Ballarat College of Advanced Education............. | 6,783,000 | 6,938,000 | 7,070,000 |
Bendigo College of Advanced Education............ | 7,249,000 | 7,780,000 | 7,928,000 |
SCHEDULE 2—continued
SCHEDULE 8—continued
Column 1 | Column 2 | Column 3 | Column 4 | |
Colleges of Advanced Education | Grant in respect of 1979 | Grant in respect of 1980 | Grant in respect of 1981 | |
| $ | $ | $ | |
Caulfield Institute of Technology..................... | 11,673,000 | 12,712,000 | 13,043,000 | |
Footscray Institute of Technology..................... | 6,907,000 | 7,543,000 | 7,747,000 | |
Gippsland Institute of Advanced Education............... | 4,797,000 | 5,184,000 | 5,314,000 | |
Lincoln Institute................................ | 6,610,000 | 7,144,000 | 7,326,000 | |
Prahran College of Advanced Education................. | 3,984,000 | 4,403,000 | 4,400,000 | |
Preston Institute of Technology....................... | 6,594,000 | 7,268,000 | 7,545,000 | |
Royal Melbourne Institute of Technology................ | 28,840,000 | 31,338,000 | 32,163,000 | |
Swinbourne College of Technology.................... | 13,108,000 | 14,236,000 | 14,604,000 | |
The Victorian College of the Arts..................... | 2,041,000 | 2,187,000 | 2,224,000 | |
Victorian College of Pharmacy....................... | 2,061,000 | 2,235,000 | 2,292,000 | |
Warrnambool Institute of Advanced Education............ | 3,174,000 | 3,416,000 | 3,498,000 | |
Total............................ | 103,821,000 | 112,384,000 | 115,154,000 | |
PART I—GRANTS FOR EXPENDITURE BY COLLEGES OF ADVANCED EDUCATION ON COLLEGE PURPOSES
Column 1 | Column 2 | Column 3 | Column 4 |
Colleges of Advanced Education | Grant in respect of 1979 | Grant in respect of 1980 | Grant in respect of 1981 |
| $ | $ | $ |
Queensland— |
|
|
|
Brisbane Kindergarten Teachers College............. | 1,472,000 | 1,503,000 | 1,498,000 |
Capricornia Institute of Advanced Education.......... | 6,254,000 | 6,920,000 | 7,171,000 |
Darling Downs Institute of Advanced Education........ | 9,032,000 | 9,789,000 | 10,138,000 |
Kelvin Grove College of Advanced Education......... | 7,718,000 | 8,411,000 | 8,731,000 |
Mount Gravatt College of Advanced Education........ | 5,779,000 | 6,266,000 | 6,472,000 |
North Brisbane College of Advanced Education........ | 5,015,000 | 5,525,000 | 5,785,000 |
Queensland Agricultural College.................. | 4,924,000 | 5,218,000 | 5,371,000 |
Queensland Conservatorium of Music.............. | 1,160,000 | 1,256,000 | 1,330,000 |
Queensland Institute of Technology................ | 18,502,000 | 19,962,000 | 20,780,000 |
Townsville College of Advanced Education........... | 2,726,000 | 3,010,000 | 3,123,000 |
Total............................ | 62,582,000 | 67,860,000 | 70,399,000 |
South Australia— |
|
|
|
Adelaide College of the Arts and Education........... | 12,108,000 | 13,091,000 | 13,315,000 |
Hartley College of Advanced Education............. | 5,545,000 | 5,978,000 | 6,031,000 |
Roseworthy Agricultural College.................. | 2,330,000 | 2,601,000 | 2,731,000 |
Salisbury College of Advanced Education............ | 3,948,000 | 4,288,000 | 4,347,000 |
South Australian Institute of Technology............ | 15,337,000 | 16,564,000 | 17,407,000 |
Sturt College of Advanced Education............... | 4,584,000 | 5,130,000 | 5,253,000 |
Total............................ | 43,852,000 | 47,652,000 | 49,084,000 |
Western Australia— |
|
|
|
Churchlands College.......................... | 6,011,000 | 6,775,000 | 6,875,000 |
Claremont Teachers College..................... | 2,883,000 | 3,292,000 | 3,340,000 |
SCHEDULE 2—continued
SCHEDULE 8—continued
Column 1 | Column 2 | Column 3 | Column 4 |
Colleges of Advanced Education | Grant in respect of 1979 | Grant in respect of 1980 | Grant in respect of 1981 |
| $ | $ | $ |
Graylands Teachers College..................... | 312,000 | .. | .. |
Mount Lawley College........................ | 4,855,000 | 5,236,000 | 5,338,000 |
Nedlands College............................ | 4,779,000 | 5,356,000 | 5,489,000 |
Western Australian Institute of Technology........... | 31,715,000 | 34,309,000 | 35,550,000 |
Total............................ | 50,555,000 | 54,968,000 | 56,592,000 |
Tasmania— |
|
|
|
Tasmanian College of Advanced Education........... | 9,489,000 | 10,302,000 | 10,603,000 |
TOTAL—ALL STATES.............. | 422,630,000 | 457,944,000 | 470,977,000 |
PART II—GRANTS FOR EXPENDITURE BY STATES ON ADVANCED EDUCATION
Column 1 | Column 2 | Column 3 |
State | Grant in respect of 1980 | Grant in respect of 1981 |
| $ | $ |
New South Wales............................................. | 2,428,000 | 2,438,000 |
Victoria................................................... | 1,067,000 | 1,099,000 |
Queensland................................................. | 1,007,000 | 975,000 |
PART III—UNALLOCATED MONEYS FOR EXPENDITURE BY COLLEGES OF ADVANCED EDUCATION AND BY STATES ON ADVANCED EDUCATION
Column 1 | Column 2 | Column 3 | Column 4 |
State | Unallocated moneys in respect of 1979 | Unallocated moneys in respect of 1980 | Unallocated moneys in respect of 1981 |
| $ | $ | $ |
New South Wales.................................... | Nil | 31,000 | 31,000 |
Victoria.......................................... | .. | 228,000 | 1,227,000 |
Victoria— |
|
|
|
State Colleges of Victoria System........................ | Nil | .. | .. |
Victoria Institute of Colleges System...................... | Nil | .. | .. |
Queensland........................................ | Nil | 48,000 | 49,000 |
South Australia..................................... | Nil | Nil | 109,000 |
Western Australia.................................... | Nil | Nil | 147,000 |
Tasmania......................................... | Nil | Nil | Nil |
Total—All States.......................... | Nil | 307,000 | 1,613,000 |
SCHEDULE 2—continued
SCHEDULE 8—continued
PART IV—AGGREGATES OF MONEYS FOR EXPENDITURE BY COLLEGES OF ADVANCED EDUCATION AND BY STATES ON ADVANCED EDUCATION
Column 1 | Column 2 | Column 3 | Column 4 |
State | State aggregates in respect of 1979 | State aggregates in respect of 1980 | State aggregates in respect of 1981 |
| $ | $ | $ |
New South Wales......................... | 105,652,000 | 116,900,000 | 120,274,000 |
Victoria............................... | 150,500,000 | 164,016,000 | 168,870,000 |
Queensland............................. | 62,582,000 | 68,915,000 | 71,423,000 |
South Australia.......................... | 43,852,000 | 47,652,000 | 49,193,000 |
Western Australia......................... | 50,555,000 | 54,968,000 | 56,739,000 |
Tasmania.............................. | 9,489,000 | 10,302,000 | 10,603,000 |
Total—All States...................... | 422,630,000 | 462,753,000 | 477,102,000 |
———————
SCHEDULE 8a Section 15b
GRANTS FOR EXPENDITURE BY THE NORTHERN TERRITORY ON ADVANCED EDUCATION PURPOSES
Column 1 | Column 2 |
Grants for expenditure by the Northern Territory in respect of 1980 | Grants for expenditure by the Northern Territory in respect of 1981 |
$ | $ |
3,067,000 | 3,159,000 |
——————
SCHEDULE 9 Section 16
PART I—GRANTS FOR EQUIPMENT FOR COLLEGES OF ADVANCED EDUCATION
Column 1 | Column 2 | Column 3 | Column 4 |
State | Grant in respect of 1979 | Grant in respect of 1980 | Grant in respect of 1981 |
| $ | $ | $ |
New South Wales......................... | 4,168,000 | 3,631,000 | 3,922,000 |
Victoria............................... | .. | 5,786,000 | 6,244,000 |
Victoria— |
|
|
|
State College of Victoria System............... | 1,197,000 | .. | .. |
Victoria Institute of Colleges System............ | 5,224,000 | .. | .. |
Queensland............................. | 2,503,000 | 2,723,000 | 2,425,000 |
South Australia.......................... | 1,415,000 | 1,588,000 | 1,703,000 |
Western Australia......................... | 1,632,000 | 1,815,000 | 1,909,000 |
Tasmania.............................. | 239,000 | 284,000 | 206,000 |
Total All States................. | 16,378,000 | 15,827,000 | 16,409,000 |
SCHEDULE 2—continued
SCHEDULE 9—continued
PART II—SPECIFIED EQUIPMENT IN RELATION TO GRANTS FOR EQUIPMENT FOR COLLEGES OF ADVANCED EDUCATION
Column 1 | Column 2 | Column 3 |
College of Advanced Education | Equipment | Grant in respect of 1979 |
|
| $ |
New South Wales— |
|
|
The New South Wales Institute of Technology....... | Computer | 903,000 |
Victoria- |
|
|
Victoria Institute of Colleges System............. | Computer network | 1,415,000 |
Queensland— |
|
|
Queensland Institute of Technology.............. | Computer | 544,000 |
Total—All States............... |
| 2,862,000 |
—————
SCHEDULE 10 Section 24
GENERAL PURPOSE RECURRENT GRANTS IN CONNECTION WITH TECHNICAL AND FURTHER EDUCATION
Column 1 | Column 2 | Column 3 | Column 4 |
State | Amount of grant in respect of 1979 | Amount of grant in respect of 1980 | Amount of grant in respect of 1981 |
| $ | $ | $ |
New South Wales..................... | 15,254,000 | 17,634,000 | 18,959,000 |
Victoria............................ | 9,585,000 | 11,809,000 | 12,831,000 |
Queensland.......................... | 3,992,000 | 4,590,000 | 4,722,000 |
South Australia....................... | 4,144,000 | 4,668,000 | 4,978,000 |
Western Australia..................... | 3,968,000 | 4,711,000 | 4,917,000 |
Tasmania........................... | 1,380,000 | 1,502,000 | 1,660,000 |
Northern Territory..................... | .. | 324,000 | 385,000 |
Total—All States.............. | 38,323,000 | 45,238,000 | 48,452,000 |
——————
SCHEDULE 2—continued
SCHEDULE 11 Section 25
GRANTS FOR STAFF TRAINING AND DATA PROCESSING IN CONNECTION WITH TECHNICAL AND FURTHER EDUCATION
PART I—GRANTS IN RESPECT OF THE YEAR 1979
Column 1 | Column 2 | Column 3 | Column 4 |
State | Maximum grant for staff training | Maximum grant for data processing | Aggregate amount in respect of 1979 |
| $ | $ | $ |
New South Wales............................. | 930,000 | 118,000 | 1,048,000 |
Victoria.................................... | 404,000 | 269,000 | 673,000 |
Queensland................................. | 405,000 | 119,000 | 524,000 |
South Australia............................... | 292,000 | 137,000 | 429,000 |
Western Australia............................. | 317,000 | 94,000 | 411,000 |
Tasmania................................... | 95,000 | 13,000 | 108,000 |
Total—All States................... | 2,443,000 | 750,000 | 3,193,000 |
PART II—GRANTS IN RESPECT OF THE YEAR 1980
Column 1 | Column 2 | Column 3 | Column 4 |
State | Maximum grant for staff training | Maximum grant for data processing | Aggregate amount in respect of 1980 |
| $ | $ | $ |
New South Wales............................. | 1,169,000 | 138,000 | 1,307,000 |
Victoria.................................... | 471,000 | 198,000 | 669,000 |
Queensland ,................................ | 447,000 | 114,000 | 561,000 |
South Australia............................... | 333,000 | 91,000 | 424,000 |
Western Australia............................. | 329,000 | 83,000 | 412,000 |
Tasmania................................... | 104,000 | 28,000 | 132,000 |
Northern Territory............................. | 29,000 | 11,000 | 40,000 |
Total—All States................... | 2,882,000 | 663,000 | 3,545,000 |
PART III—GRANTS IN RESPECT OF THE YEAR 1981
Column 1 | Column 2 | Column 3 | Column 4 |
State | Maximum grant for staff training | Maximum grant for data processing | Aggregate amount in respect of 1981 |
| $ | $ | $ |
New South Wales............................. | 1,147,000 | 175,000 | 1,322,000 |
Victoria.................................... | 538,000 | 180,000 | 718,000 |
Queensland................................. | 472,000 | 129,000 | 601,000 |
South Australia............................... | 353,000 | 84,000 | 437,000 |
Western Australia............................. | 337,000 | 85,000 | 422,000 |
Tasmania................................... | 162,000 | 32,000 | 194,000 |
Northern Territory............................. | 41,000 | 16,000 | 57,000 |
Total—All Stales................... | 3,050,000 | 701,000 | 3,751,000 |
SCHEDULE 2—continued
SCHEDULE 11—continued
PART IV—UNALLOCATED GRANT FOR STAFF TRAINING IN RESPECT OF 1981
Total unallocated grant—$54,000
—————
SCHEDULE 12 Section 27
OTHER RECURRENT GRANTS IN CONNECTION WITH TECHNICAL AND FURTHER EDUCATION
Column 1 | Column 2 | Column 3 | Column 4 |
State | Maximum grant in respect of 1979 | Maximum grant in respect of 1980 | Maximum grant in respect of 1981 |
| $ | $ | $ |
New South Wales............................. | 4,982,000 | 5,058,000 | 5,145,000 |
Victoria.................................... | 3,498,000 | 3,865,000 | 3,918,000 |
Queensland................................. | 1,496,000 | 1,612,000 | 1,580,000 |
South Australia............................... | 1,282,000 | 1,357,000 | 1,349,000 |
Western Australia............................. | 1,135,000 | 1,252,000 | 1,263,000 |
Tasmania................................... | 414,000 | 405,000 | 352,000 |
Northern Territory............................. |
| 125,000 | 92,000 |
Total—All States................... | 12,807,000 | 13,674,000 | 13,699,000 |
—————
SCHEDULE 13 Section 28
GRANTS FOR PROGRAMS OF ADULT EDUCATION RELATED TO TECHNICAL AND FURTHER EDUCATION
Column 1 | Column 2 | Column 3 | Column 4 |
State | Maximum grant in respect of 1979 | Maximum grant in respect of 1980 | Maximum grant in respect of 1981 |
| $ | $ | $ |
New South Wales............................. | 109,000 | 156,000 | 209,000 |
Victoria.................................... | 78,000 | 118,000 | 157,000 |
Queensland................................. | 47,000 | 68,000 | 90,000 |
South Australia............................... | 33,000 | 41,000 | 54,000 |
Western Australia............................. | 33,000 | 35,000 | 45,000 |
Tasmania................................... | 16,000 | 19,000 | 26,000 |
Total—All States................... | 316,000 | 437,000 | 581,000 |