Notification of extension to time in which to make a decision whether to approve a controlled action – Robbins Island Renewable Energy Park, Robbins Island, Tasmania (EPBC reference 2018/8096)

Administered by Department of Climate Change, Energy, the Environment and Water

Legislation au C2023G00022 In force Gazette

Legislation content

 

 

Department of Climate Change, Energy, the Environment and Water

 

Notification of extension to time in which to make a decision whether to approve a controlled action – Robbins Island Renewable Energy Park, Robbins Island, Tasmania (EPBC reference 2018/8096)

This specification is made under section 130(1A) of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).

Proposed action

designated proponent

ACEN ROBBINS ISLAND PTY LTD

ABN 35 618 734 277

proposed action

To construct and operate a wind farm, including associated infrastructure, on Robbins Island, Tasmania [See EPBC Act referral 2017/8096 & variation request dated 18 September 2019].

Specified longer period

specified longer period

The relevant period in which the Minister must make a decision whether or not to approve the controlled action is extended by 60 business days (to a total of 90 business days beginning on the first business day after the Minister received the assessment report).

Person authorised to make decision

name and position

Mike Smith

Acting Branch Head

Environment Assessments (Vic, Tas) and Post Approvals Branch

signature

date of decision

23 December 2022

 