AUSTRALIAN COMMUNICATIONS AND MEDIA AUTHORITY
Telecommunications Act 1997
Subsection 81(1)
NOMINATED CARRIER DECLARATION
After considering an application dated 14 August 2015 made to the Australian Communications and Media Authority (ACMA) under section 77 of the Telecommunications Act 1997 by TransGrid (ABN: 19 622 755 774) (the applicant) in relation to network unit or units (the network unit or units) owned by TransGrid (ABN: 19 622 755 774), I, Paul Nicholas, Section Manager, delegate of the ACMA, acting under subsection 81(1) of the Telecommunications Act 1997, being satisfied that:
(a) if the applicant were declared to be the nominated carrier in relation to the network unit or units, it would be in a position to comply with all of the obligations imposed on the applicant in the applicant’s capacity as the nominated carrier in relation to the network unit or units; and
(b) the making of the declaration will not impede the efficient administration of:
(i) the Telecommunications Act 1997;
(ii) the Telecommunications (Consumer Protection and Service Standards) Act 1999 and regulations under that Act; or
(iii) the Telecommunications Universal Service Management Agency Act 2012;
declare that TransGrid is the nominated carrier in relation to network units owned by TransGrid, used for non-prescribed purposes only, and located:
- between Canberra Substation on Parkwood Road, Macgregor ACT and NextDC C1 data centre, 19 Battye St, Bruce ACT;
between NextDC C1 data centre, 19 Battye St, Bruce ACT and Verizon data centre, 7-9 Braybrooke St, Bruce ACT;
between NextDC C1 data centre, 19 Battye St, Bruce ACT and TransAct Data Centre, 470 Northbourne Ave, Dickson ACT;
between TransAct Data Centre, 470 Northbourne Ave, Dickson ACT and 50 Mort St, Braddon ACT;
between Sydney West Substation, 200 Old Wallgrove Road, Eastern Creek NSW and HP Aurora Data Centre, Roberts Road, Eastern Creek NSW;
between Springhill Substation, Glastonbury Ave, Unanderra NSW and Metronode data centre, Lathe Place, Unanderra NSW;
between Equinix ME1 data centre, 600 Lorimer St, Port Melbourne VIC and NextDC M1 data centre, 826 Lorimer St, Port Melbourne VIC;
between Fishermans Bend Substation, Turner St, Port Melbourne VIC and NextDC M1 data centre, 826 Lorimer St, Port Melbourne VIC;
between Mt Spring Radio Site and Tarago Radio Site in NSW;
between Tarago Radio Site and Woodlawn Bioreactor in NSW;
between Bayswater Power Station and Elderslie Radio Site in NSW;
between Elderslie Radio Site and Mt Sugarloaf Radio Site in NSW; and
between Mt Sugarloaf Radio Site and Ipera Data Centre in NSW.
Dated the 12th day of October 2015
Signed Paul Nicholas,
Delegate of the Australian Communications and Media Authority