EPBC Act Part 7-9 decisions published, 28/04/2025 to 4/05/2025

Administered by Department of Climate Change, Energy, the Environment and Water

Legislation au C2025G00251 In force Gazette

Legislation content

 

DEPARTMENT OF CLIMATE CHANGE, ENERGY, THE ENVIRONMENT AND WATER

Environment Protection and Biodiversity Conservation Act 1999

 

EPBC Act Part 7-9 decisions published, 28/04/2025 to 4/05/2025

 

For further information see the referrals list at https://epbcpublicportal.environment.gov.au/all-referrals/

and type the reference number in the Filter by Referral Number box

 

actions determined as requiring approval (EPBC Act s.75)

Reference

Title

Controlling Provisions

Date

2025/10134

Bookham Wind Farm Pty Ltd / Energy Generation and Supply (renewable) / 2 Fagan Drive, Bookham NSW and 1170 Burrinjuck Road - Appendix A Section 2.2.1 and Appendix E, Figure 1, Page 81 / New South Wales / Bookham Wind Farm and Battery (SSD-79885459)

  • Listed threatened species and communities (sections 18 & 18A)
  • Listed migratory species (sections 20 & 20A)

22/04/2025

2024/10088

Great Eastern Offshore Wind Farm Project Co Pty Ltd / Energy Generation and Supply (renewable) / McGaurans Beach Road 3851 / Victoria / Great Eastern Offshore Wind

  • Wetlands of international importance

(sections 16 & 17B)

  • Listed threatened species and communities (sections 18 & 18A)
  • Listed migratory species (sections 20 & 20A)
  • Commonwealth marine areas (sections 23 & 24A)

28/04/2025

2025/10105

Wilpinjong Coal Pty Ltd / Mining / 1434 Ulan-Wollar Road, Wilpinjong NSW 2850 (Latitude: -32.341742, Longitude: 149.944800) / New South Wales / Wilpinjong Coal Mine - Pit 8 Extension

  • Listed threatened species and communities (sections 18 & 18A)
  • A water resource, in relation to coal seam gas development and large coal mining development (sections 24D & 24E)

1/05/2025

 

actions determined as NOT requiring approval (EPBC Act s.75)

Reference

Title

Date

2024/10096

BHP Olympic Dam Corporation Pty Ltd / Mining / OD mine SML (CT Volume 5140 Folio 575) and Clause 28 land (see Att 1 Section 1.2.1, pg 9). / South Australia / Olympic Dam Smelter Refinery Expansion (SRE) Project

29/04/2025

2025/10136

Edify Energy Pty. Ltd. / Energy Generation and Supply (renewable) / Payten's Bridge Road, Mulyandry NSW 2871 / New South Wales / Peninsula Solar Farm

30/04/2025

2024/10004

Arkar Arkar / Energy Generation and Supply (renewable) / 117 Cowcher Rd, Mingin / Western Australia / Narrogin Wind Farm

1/05/2025

 

Assessment Approach (EPBC Act s.87)

Reference

Title

Assessment Approach

Date

2024/10088

Great Eastern Offshore Wind Farm Project Co Pty Ltd / Energy Generation and Supply (renewable) / McGaurans Beach Road 3851 / Victoria / Great Eastern Offshore Wind

Environmental Impact Statement

28/04/2025

 

variation of conditions of approval (EPBC Act s.143)

Reference

Title

Date

2020/8773

Acciona Energy Australia Global Pty Ltd / Energy Generation and Supply (renewable) / Lot 2 SP301578 and Lot 1 SP157677 / Queensland / Aldoga Solar Farm Project

24/04/2025

 


NOTICE OF EXTENSION OF TIME (EPBC Act s.130(4))

Reference

Title

Extended to

Date

2023/09527

Australia Pacific Airports (Melbourne) Pty Limited / Transport - Air and Space / Gate 22 Operations Rd, Tullamarine VIC 3043 / Victoria / Melbourne Airport Pavement Maintenance Program 2

28/05/2025

30/04/2025

 

lapsed proposals (EPBC Act s.155)

Reference

Title

Date

2014/7232

Anthony Koutesis / Agriculture and Forestry / City of Swan / Western Australia / Rural Development, Lot 1983 North Ellenbrook, WA

22/04/2025

2007/3543

Gulf Harbour Pty Ltd / Residential Development / Port Wakefield / South Australia / Residential Marina Development

24/04/2025

 

Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.

 

Interactions

Authorises

All Versions

Sourced from the Federal Register of Legislation at 26 August 2026. For the latest information on Australian Government law please go to https://www.legislation.gov.au.