actions determined as requiring approval (EPBC Act s.75)
Reference | Title | Controlling Provisions | Date |
2024/09880 | Woolnorth Wind Farm Holding Pty Ltd (Woolnorth Renewables) / Energy Generation and Supply (renewable) / 1665 Woolnorth Rd, Woolnorth / Tasmania / Woolnorth Wind Farm Repowering | - Listed threatened species and communities (sections 18 & 18A)
- Listed migratory species (sections 20 & 20A)
| 9/09/2024 |
2024/09917 | Laree Walker / Energy Generation and Supply (non-renewable) / Kemerton substation, Wokalup to Marriott Road, Wellesley / Western Australia / Kemerton Substation to Kemerton Renewable Energy Node – 132 kV Over Head Transmission Line | - Listed threatened species and communities (sections 18 & 18A)
| 16/09/2024 |
2024/09919 | PORT OF BRISBANE PTY LTD / Transport - Water / Moreton Bay, in and adjacent to the existing Port of Brisbane navigational channels / Queensland / Port of Brisbane Channel Enhancement Project | - Ramsar wetlands (sections 16 and 17B)
- Listed threatened species and communities (sections 18 & 18A)
- Listed migratory species (sections 20 & 20A)
- Commonwealth marine areas (sections 23 & 24A)
| 19/09/2024 |
actions determined as NOT requiring approval (EPBC Act s.75)
Reference | Title | Date |
2024/09944 | Tim Kildea / Water Management and Use / Lot 10, St Andrews Drive, Port Lincoln / South Australia / Eyre Peninsula Desalination Plant | 24/09/2024 |
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2024/09917 | Laree Walker / Energy Generation and Supply (non-renewable) / Kemerton substation, Wokalup to Marriott Road, Wellesley / Western Australia / Kemerton Substation to Kemerton Renewable Energy Node – 132 kV Over Head Transmission Line | Preliminary Documentation | 16/09/2024 |
2024/09919 | PORT OF BRISBANE PTY LTD / Transport - Water / Moreton Bay, in and adjacent to the existing Port of Brisbane navigational channels / Queensland / Port of Brisbane Channel Enhancement Project | Accredited Assessment Process under the State Development and Public Works Organisation Act 1971. | 19/09/2024 |
DECISION ON APPROVAL (EPBC Act s.133)
Reference | Title | Approval Decision | Date |
2019/8427 | Narrabri Coal Operations Pty Ltd / Mining / 10 Kurrajong Creek Road, Baan Baa, NSW, 2390 / New South Wales / Narrabri Underground Mine Stage 3 Extension Project, NSW | Approved with conditions | 24/09/2024 |
2020/8735 | MACH Energy Australia Pty Ltd / Mining / 1100 Wybong Road, Muswellbrook / New South Wales / Mount Pleasant Optimisation Project | Approved with conditions | 24/09/2024 |
2022/09208 | Ashton Coal Operations Pty Limited / Mining / Ravensworth Underground Mine, Lemington Road, Ravensworth, NSW, 2330. / New South Wales / Ashton Coal Operations Ravensworth Underground Mine | Approved with conditions | 24/09/2024 |
NOTICE OF EXTENSION OF TIME (EPBC Act s.130(4))
Reference | Title | Extended to | Date |
2017/8096 | UPC ROBBINS ISLAND PTY LTD / Energy Generation and Supply (renewable) / Lot 110402/1 (Robbins Island) and some areas of Crown land. The locati / Tasmania / Robbins Island Renewable Energy Park, Robbins Island, Tasmania | 9/12/2024 | 20/09/2024 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.
Overview
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) was enacted to provide for the protection of the environment, particularly matters of national environmental significance, by establishing a framework for the assessment and approval of activities that may have significant environmental impacts. The EPBC Act was introduced to address the need for a comprehensive and integrated approach to environmental protection in Australia, considering both federal and state jurisdictions. The Act is administered by the Parliament of Australia and aims to ensure that significant environmental impacts are properly assessed and mitigated. Recent decisions under the EPBC Act, published from 23 to 29 September 2024, include both approvals and refusals for various projects, such as the Woolnorth Wind Farm Repowering in Tasmania and the Kemerton Substation to Kemerton Renewable Energy Node in Western Australia, reflecting the Act's role in balancing development with environmental protection.
Scope and Application
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) applies to actions that may have a significant impact on matters of national environmental significance, including listed threatened species and communities, listed migratory species, Ramsar wetlands, and Commonwealth marine areas. This Act applies to entities and individuals proposing actions that could affect these environmental matters, spanning various industries such as energy generation, transport, and water management. The EPBC Act has a national jurisdictional reach, regulating activities across all states and territories in Australia. The Act includes provisions for determining whether certain actions require approval and provides mechanisms for assessing and approving or disapproving actions based on their potential environmental impact. Subordinate instruments may extend or refine the application of the Act, but the primary legislation sets out the core requirements and processes. Certain actions may be exempt from the need for approval if they are deemed to have no significant impact on matters of national environmental significance, as determined by the responsible Minister.
Key Provisions
The key sections of the EPBC Act that pertain to the decisions published in this Gazette relate primarily to sections 75, 87, 130(4), and 133. Section 75 of the Act governs the determination of whether an action requires approval, which is specified in the Gazette entries for actions 2024/09880 and 2024/09917. Section 87 outlines the approach to be taken in assessing whether an action is a controlled action, as seen in the entries for actions 2024/09917 and 2024/09919. Section 130(4) allows for the extension of time for certain decisions, such as the notice for 2017/8096. Section 133 is the section under which approvals are granted, and it applies to the decisions made on actions 2019/8427, 2020/8735, and 2022/09208.
The obligations and requirements imposed by the EPBC Act on the entities involved in these actions include the need to provide detailed information and documentation about the proposed actions. This includes information on potential impacts on listed threatened species and communities, listed migratory species, Ramsar wetlands, and Commonwealth marine areas, as required under sections 18, 18A, 20, 20A, 16, 17B, 23, and 24A of the Act. The entities must also follow the prescribed assessment approaches as specified in sections 87 and 130(4), which may include preliminary documentation or accredited assessment processes. Approvals granted under section 133 are subject to conditions designed to mitigate the environmental impacts of the proposed actions.
In terms of consequences for non-compliance, breaches of the EPBC Act can lead to civil and criminal penalties. The Act allows for fines of up to $666,000 for individuals and $3,330,000 for corporations for offences related to the destruction or adverse modification of listed threatened species or communities, listed migratory species, or Ramsar wetlands. Criminal penalties can include imprisonment for up to two years for individuals and five years for corporations. Additionally, actions that result in significant harm to the environment can attract further penalties under the Act. It is important for entities to adhere to the requirements and conditions imposed by the Act to avoid these penalties.