DEPARTMENT OF CLIMATE CHANGE, ENERGY, THE ENVIRONMENT AND WATER

Environment Protection and Biodiversity Conservation Act 1999

 

EPBC Act Part 7-9 decisions published, 16/06/2025 to 22/06/2025

 

For further information see the referrals list at https://epbcpublicportal.environment.gov.au/all-referrals/

and type the reference number in the Filter by Referral Number box

 

actions determined as requiring approval (EPBC Act s.75)

Reference

Title

Controlling Provisions

Date

2025/10181

Corvus Resources Pty Ltd / Mining / Gregory Highway, Emerald, QLD, 4720, Australia / Queensland / Corvus Metallurgical Coal Project

  • Listed threatened species and communities (sections 18 & 18A)
  • A water resource, in relation to coal seam gas development and large coal mining development (sections 24D & 24E)

10/06/2025

 

OUTCOME OF REQUEST FOR RECONSIDERATION OF S75(1) DECISION (EPBC Act s.78C)

Reference

Title

Reconsideration Decision

Date

2008/4620

Hunter Gas Pipeline Pty Ltd / Energy Generation and Supply (non-renewable) / Wallumbilla, Surat Basin, to Hunter River, Newcastle / New South Wales / Queensland Hunter Gas Pipeline, approximately 833 km in length

Not a Controlled Action

16/06/2025

 

NOTICE OF EXTENSION OF TIME (EPBC Act s.130(4))

Reference

Title

Extended to

Date

2022/9164

Karuah East Quarry Pty Limited / Mining / Lot 13 DP 1024564 and Lot 12 DP 1024564, Karuah / New South Wales / Karuah East Quarry - Modification 10

3/07/2025

11/06/2025

 

Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.

 

Interactions

Authorises

All Versions

Sourced from the Federal Register of Legislation at 26 August 2026. For the latest information on Australian Government law please go to https://www.legislation.gov.au.