actions determined as requiring approval (EPBC Act s.75)
Reference | Title | Controlling Provisions | Date |
2024/09935 | CQ-H2 INDUSTRIAL WATER PTY LTD / Energy Generation and Supply (renewable) / from 172 The Narrows Road, Aldoga to Lot 510 on SP305597 / Queensland / CQ-H2 Surplus Industrial Water Pipeline (SIWP) Project | - World Heritage (sections 12 & 15A)
- National Heritage (sections 15B & 15C)
- Great Barrier Reef Marine Park
(sections 24B & 24C) - Listed threatened species and communities (sections 18 & 18A)
- Listed migratory species (sections 20 & 20A)
| 15/10/2024 |
2024/09902 | CQ-H2 HPF Pty Ltd / Energy Generation and Supply (renewable) / 172 The Narrows Road, Aldoga / Queensland / CQ-H2 Hydrogen Production Facility (HPF) Project | - World Heritage (sections 12 & 15A)
- National Heritage (sections 15B & 15C)
- Listed threatened species and communities (sections 18 & 18A)
- Great Barrier Reef Marine Park
(sections 24B & 24C) | 16/10/2024 |
actions determined as NOT requiring approval (EPBC Act s.75)
Reference | Title | Date |
2024/09941 | WPH Cranbourne Investments Pty Ltd / Commercial Development / 690 Western Port Highway, Cranbourne West / Victoria / Cranbourne West Commercial and Industrial Development | 15/10/2024 |
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2024/09935 | CQ-H2 INDUSTRIAL WATER PTY LTD / Energy Generation and Supply (renewable) / from 172 The Narrows Road, Aldoga to Lot 510 on SP305597 / Queensland / CQ-H2 Surplus Industrial Water Pipeline (SIWP) Project | Preliminary Documentation | 15/10/2024 |
2024/09902 | CQ-H2 HPF Pty Ltd / Energy Generation and Supply (renewable) / 172 The Narrows Road, Aldoga / Queensland / CQ-H2 Hydrogen Production Facility (HPF) Project | Preliminary Documentation | 16/10/2024 |
DECISION ON APPROVAL (EPBC Act s.133)
Reference | Title | Approval Decision | Date |
2023/09569 | Major Transport Infrastructure Authority (MTIA) / Transport - Land / 377 Calder Freeway, Calder Park / Victoria / Calder Park Drive and Holden Road Level Crossing Removal Project | Approved with conditions | 9/10/2024 |
variation of conditions of approval (EPBC Act s.143)
Reference | Title | Date |
2022/09327 | Department of Industry, Science and Resources (DISR) / Commonwealth / in the Timor Sea approximately 550 km west-northwest from Darwin / Commonwealth Marine / Northern Endeavour Phase 1 Decommissioning | 20/09/2024 |
2018/8236 | MARDIE MINERALS PTY LTD / Mining / Mining Tenements E08/2741, E08/2943, E08/2740 and E08/2836 / Western Australia / Mardie Project, 80 km southwest of Karratha, WA | 9/10/2024 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.
Overview
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) was enacted by the Australian Parliament to provide for the protection of the environment, particularly with respect to matters of national environmental significance. The Act addresses a critical gap by offering a comprehensive framework to manage and protect Australia's environment, including its unique biodiversity and heritage sites, in a sustainable manner. The EPBC Act aims to ensure that environmental considerations are integrated into decision-making processes, particularly for actions that may have a significant impact on the environment. The Act empowers the relevant federal Minister to approve, control, or reject proposals that could affect areas of national environmental importance, thereby facilitating a balanced approach to development and conservation.
Scope and Application
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) applies to a wide range of actions, including industrial, commercial, and transport projects that may impact on matters of national environmental significance. These include World Heritage properties, National Heritage places, listed threatened species and ecological communities, and the Great Barrier Reef Marine Park. The Act applies to both individuals and entities, particularly those undertaking activities that may affect these protected areas. The geographic reach of the Act is national, applying across all states and territories within Australia. However, the application of the Act can be extended or restricted through subordinate instruments, such as regulations and codes of practice, which provide further detail on specific environmental issues and management practices. While the Act generally applies to all qualifying actions, there are certain exclusions and exemptions, particularly for actions that are minor in nature or have been assessed under other legislative frameworks. The Act also includes provisions for varying the conditions of approval to ensure ongoing compliance with environmental standards.
Key Provisions
The main operative sections of the EPBC Act (sections 75, 87, 133, and 143) are referenced in the Gazette as they relate to various projects and their approval statuses. Section 75 of the Act outlines actions determined to require approval, such as the CQ-H2 Surplus Industrial Water Pipeline (SIWP) Project and the CQ-H2 Hydrogen Production Facility (HPF) Project, both of which involve energy generation and supply in Queensland. Section 87 pertains to the assessment approach, which includes the preliminary documentation stage for these projects. Section 133 details the decision on approval, exemplified by the Calder Park Drive and Holden Road Level Crossing Removal Project in Victoria, which was approved with conditions. Section 143 addresses the variation of conditions of approval, seen in the decommissioning of the Northern Endeavour Phase 1 in the Timor Sea and the Mardie Project in Western Australia.
The Act imposes several obligations and requirements on the parties involved. Projects that may significantly impact matters of national environmental significance, such as World Heritage properties, National Heritage places, the Great Barrier Reef Marine Park, listed threatened species and communities, and listed migratory species, must undergo a rigorous assessment process. This includes submitting preliminary documentation and potentially facing conditions upon approval. Companies such as CQ-H2 Industrial Water Pty Ltd and CQ-H2 HPF Pty Ltd must ensure their projects comply with these stringent environmental standards and follow the prescribed assessment approaches.
Failure to comply with the requirements of the EPBC Act can result in various civil and criminal consequences. The Act does not explicitly detail specific penalties in the referenced sections, but non-compliance generally can lead to enforcement actions, fines, or legal proceedings. Companies found in breach of the Act's provisions could face substantial financial penalties, and individuals might be subject to criminal charges, depending on the severity and intent of the breach. The overarching goal is to ensure that environmental protections are upheld and that any impacts from projects are mitigated appropriately.