DEPARTMENT OF CLIMATE CHANGE, ENERGY, THE ENVIRONMENT AND WATER
Environment Protection and Biodiversity Conservation Act 1999
EPBC Act Part 7-9 decisions published, 08/08/2022 to 14/08/2022
For further information see the referrals list at https://epbcpublicportal.awe.gov.au/all-referrals/
and type the reference number in the Filter by Referral Number box
actions determined as requiring approval (EPBC Act s.75)
Reference | Title | Controlling Provisions | Date |
2022/09220 | Morisset Land Fund Pty Ltd / Commercial Development / 126 Dora Street Morisset, NSW / New South Wales / Caravan Park & Lifestyle Living | - Listed threatened species and communities (sections 18 & 18A)
| 3/08/2022 |
2022/09255 | Hancock Prospecting Pty Ltd / Mining / Mulga Downs Station / Western Australia / Mulga Downs Iron Ore Mine | - Listed threatened species and communities (sections 18 & 18A)
- Listed migratory species (sections 20 & 20A)
| 6/08/2022 |
2022/09268 | Burrendong Wind Farm Pty Ltd / Energy Generation and Supply (renewable) / 689 Burrendong Dam Road, Yarrabin / New South Wales / Burrendong Wind Farm | - Listed threatened species and communities (sections 18 & 18A)
- Listed migratory species (sections 20 & 20A)
| 8/08/2022 |
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2022/09220 | Morisset Land Fund Pty Ltd / Commercial Development / 126 Dora Street Morisset, NSW / New South Wales / Caravan Park & Lifestyle Living | Preliminary Documentation | 3/08/2022 |
2022/09255 | Hancock Prospecting Pty Ltd / Mining / Mulga Downs Station / Western Australia / Mulga Downs Iron Ore Mine | Public Environment Report | 6/08/2022 |
DECISION ON APPROVAL (EPBC Act s.133)
Reference | Title | Approval Decision | Date |
2020/8858 | Logan City Council / Transport - Land / 185-483 Edelsten Road, Jimboomba / Queensland / Edelsten Road Upgrade | Approved with conditions | 4/08/2022 |
2018/8330 | ROY HILL IRON ORE PTY LTD / Mining / M46/518, M46/519, L46/104, L46/110, L46/129, L46/141, L46/142, L47/346, L47/347, L47/642, L47/735 / Western Australia / Roy Hill Iron Ore Mine expansion, Pilbara Region, WA | Approved with conditions | 5/08/2022 |
variation of conditions of approval (EPBC Act s.143)
Reference | Title | Date |
2018/8289 | NEOEN AUSTRALIA PTY. LTD. / Energy Generation and Supply (renewable) / Refer to Kaban Green Power Hub Matters of Environmental Significance Report, Section 1.4. / Queensland / Kaban Green Power Hub, Kaban, Qld | 10/08/2022 |
NOTICE OF EXTENSION OF TIME (EPBC Act s.130(4))
Reference | Title | Extended to | Date |
2020/8869 | Communities Tasmania on behalf of the Director Housing / Residential Development / near Kingston / Tasmania / Huntingfield Master Plan – Stage 2 and 3 | 23/09/2022 | 12/08/2022 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.
Overview
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) was enacted by the Australian Parliament to address the need for a comprehensive framework that protects and manages the nation's environment, particularly in relation to matters of national environmental significance. The Act aims to integrate environmental considerations into decision-making processes, providing a mechanism to protect and manage the environment, heritage, and biodiversity. By setting out the legislative requirements for the assessment and approval of activities that may impact these areas, the EPBC Act plays a crucial role in ensuring sustainable development and environmental stewardship across the country. The Department of Climate Change, Energy, the Environment and Water is responsible for administering the Act, with a policy objective to effectively manage environmental impacts while supporting economic growth and development.
Scope and Application
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) applies to a wide range of activities and entities that may impact matters of national environmental significance, including listed threatened species, communities, and migratory species. The Act's jurisdiction extends throughout Australia, covering both Commonwealth and state lands, as well as territorial waters. It applies to both individuals and entities engaged in activities such as commercial development, mining, and energy generation, and any actions that may affect the environment. The EPBC Act provides mechanisms for the assessment and approval of certain actions that may impact the environment, with decisions on approvals and variations being published for public information. While the Act applies broadly, certain exclusions and exemptions may apply, and the scope of application can be extended or restricted through subordinate instruments. The Department of Climate Change, Energy, the Environment and Water is responsible for administering the Act and ensuring that all notifications and decisions are processed within the required timeframes, with quality assurance procedures in place to minimise any risk of missed notifications.
Key Provisions
The main sections of the EPBC Act that are relevant to the recent notifications include sections 75, 87, 133, 143, and 130(4). Section 75 pertains to the approval of actions that require assessment and approval under the Act. This includes developments that may impact listed threatened species and communities, or listed migratory species, as seen in the referrals for Morisset Land Fund Pty Ltd, Hancock Prospecting Pty Ltd, and Burrendong Wind Farm Pty Ltd. Section 87 is concerned with the approach taken in the assessment of these actions. For example, the assessment approach for the Morisset Land Fund Pty Ltd referral involved preliminary documentation, while for Hancock Prospecting Pty Ltd, it involved the preparation of a Public Environment Report. Section 133 addresses the approval of actions with conditions. The referrals for Logan City Council and ROY HILL IRON ORE PTY LTD were approved with conditions, demonstrating the application of this section. Section 143 covers the variation of conditions of approval, which was relevant to the NEOEN AUSTRALIA PTY. LTD referral, where the conditions of the Kaban Green Power Hub were varied. Lastly, section 130(4) deals with the extension of time for processing referrals, as seen in the extension granted to Communities Tasmania on behalf of the Director Housing for the Huntingfield Master Plan – Stage 2 and 3.
The EPBC Act imposes several obligations on the parties or entities it governs. These include the requirement to notify the Department of any proposed actions that may have a significant impact on matters of environmental significance, as specified in the Act. Developers or proponents must also submit detailed documentation and undergo assessment processes as outlined in the Act. This involves providing preliminary documentation or preparing comprehensive Public Environment Reports to facilitate the evaluation of potential environmental impacts. Additionally, once an action has been approved, the parties must adhere to the conditions set forth in the approval, which may include measures to mitigate environmental harm or monitor ongoing impacts. For instance, Logan City Council and ROY HILL IRON ORE PTY LTD were required to implement specific conditions as part of their approvals.
The EPBC Act also outlines potential offences, penalties, and consequences for breaches of its provisions. While specific penalties are not detailed in the notifications, the Act generally provides for both civil and criminal penalties for non-compliance. Civil penalties can include fines up to certain limits prescribed by the Act, which can vary depending on the nature and severity of the breach. Criminal penalties may apply for more serious or repeated offences and can result in substantial fines or imprisonment. The Act aims to enforce compliance through these deterrents, ensuring that parties take their environmental responsibilities seriously and mitigate potential harm to protected species and communities.
In summary, the Environment Protection and Biodiversity Conservation Act 1999 governs actions that may impact listed threatened species, communities, and migratory species through specific sections that require notification, assessment, and conditional approval. Parties must submit detailed documentation and adhere to the imposed conditions to ensure compliance and mitigate environmental harm. While the specific penalties for breaches are not detailed in the notifications, the Act provides for both civil and criminal penalties to enforce compliance and deter non-compliance. The Department of Climate Change, Energy, the Environment and Water has systems in place to minimise missed notifications, ensuring transparency and public access to referral histories.