Reference | Title | Controlling Provisions | Date |
2023/09646 | QUEENSLAND HYDRO PTY LTD / Energy Generation and Supply (renewable) / 131 Borgan Road, Lake Borumba / Queensland / Borumba Pumped Hydro Energy Storage (PHES) Project | - World Heritage (sections 12 & 15A)
- National Heritage (sections 15B & 15C)
- Wetlands of international importance (sections 16 & 17B)
- Listed threatened species and communities (sections 18 & 18A)
- Listed migratory species (sections 20 & 20A)
| 19/12/2023 |
2023/09691 | CASTILE RESOURCES LTD / Mining / NT Portion 3556, Warumungu / Northern Territory / Rover 1 Iron Oxide Copper Gold (IOCG) mine Project, NT | - Listed threatened species and communities (sections 18 & 18A)
| 22/12/2023 |
actions determined as NOT requiring approval (EPBC Act s.75)
Reference | Title | Date |
2023/09588 | Brisbane City Council / Transport - Land / Gardner Road, Rochedale (new road between Priestdale Road and School Road) / Queensland / Gardner Road Extension | 22/12/2023 |
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2023/09646 | QUEENSLAND HYDRO PTY LTD / Energy Generation and Supply (renewable) / 131 Borgan Road, Lake Borumba / Queensland / Borumba Pumped Hydro Energy Storage (PHES) Project | Accredited Assessment Process under the State Development and Public Works Organisation Act 1971 (Qld) | 19/12/2023 |
variation of conditions of approval (EPBC Act s.143)
Reference | Title | Date |
2007/3297 | MOOLARBEN COAL MINES PTY LTD / Mining / Ulan NE of Mudgee / New South Wales / Moolarben Coal Mine Project | 21/08/2019 |
2019/8520 | Pilbara Ports Authority / Transport - Water / Port Hedland / Western Australia / Port Hedland Spoilbank Marina, WA | 21/12/2023 |
2008/4398 | BG INTERNATIONAL LTD / Energy Generation and Supply (non-renewable) / Surat Basin / Queensland / Development of Existing Coal Seam Gas Fields | 22/12/2023 |
2019/8487 | DEPARTMENT OF TRANSPORT / Transport - Land / Multiple lots / Victoria / Healesville - Koo Wee Rup Road Upgrade, Vic | 22/12/2023 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.
Overview
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) was enacted to provide for the protection of the environment, particularly matters of national environmental significance, by regulating activities that may impact them. The EPBC Act was introduced to address the need for a comprehensive legislative framework to protect Australia’s unique biodiversity and heritage. The Act is administered by the Parliament of Australia and its policy objective is to ensure that developments and activities do not have a significant adverse impact on the environment, particularly on World Heritage properties, nationally and internationally significant wetlands, threatened species, and other matters of national environmental significance. Recent notifications and decisions published under the EPBC Act include projects such as the Borumba Pumped Hydro Energy Storage Project in Queensland, which requires approval under various sections of the Act including World Heritage and National Heritage provisions, and the Rover 1 Iron Oxide Copper Gold mine Project in the Northern Territory, which requires approval under the listed threatened species and communities provisions. These actions highlight the Act’s role in balancing development with environmental protection.
Scope and Application
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) applies to a broad range of activities across Australia that have the potential to impact on matters of national environmental significance. This includes actions by individuals, corporations, and public authorities that may affect World Heritage properties, national heritage places, listed threatened species and ecological communities, listed migratory species, Ramsar wetlands, the marine environment, the Great Barrier Reef, the atmosphere, or interstate and international waterways. The geographic reach of the Act is national, covering the entire territory of Australia, including states, territories, and external territories. The EPBC Act also extends to certain activities outside Australia's jurisdiction if they are likely to significantly affect a matter of national environmental significance. The Act provides for the approval, assessment, and monitoring of actions that may have environmental impacts, with specific sections outlining the types of controls and conditions that can be applied to approved actions. The Act may also be extended or restricted in its application through subordinate instruments such as regulations and guidelines. However, the Act excludes certain activities, such as those related to defence or nuclear actions, and provides exemptions for activities that have negligible impact on matters of national environmental significance.
Key Provisions
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) outlines several key provisions, including the determination of whether certain actions require approval under the Act (sections 75 and 87). For instance, the Act stipulates that certain actions, such as the Borumba Pumped Hydro Energy Storage (PHES) Project by Queensland Hydro Pty Ltd, require approval if they are likely to have a significant impact on matters of national environmental significance, as defined in the Act (section 12 for World Heritage, section 15B for National Heritage, etc.). Other actions, such as the Gardner Road Extension by Brisbane City Council, have been determined not to require approval because they are unlikely to significantly impact protected environmental matters (section 75). The assessment approach for actions that do require approval is also specified, with some projects assessed under accredited processes, such as the Rover 1 Iron Oxide Copper Gold (IOCG) mine Project by Castile Resources Ltd (section 87).
The EPBC Act imposes several obligations on parties or entities it governs. These include providing detailed environmental impact assessments for projects that require approval, ensuring compliance with any conditions set by the Minister under the Act, and adhering to the assessment approaches outlined. For example, Queensland Hydro Pty Ltd must provide comprehensive environmental impact assessments for their Borumba PHES Project, detailing how the project will affect protected World Heritage, National Heritage, wetlands, threatened species, and other environmental matters. Similarly, Castile Resources Ltd must ensure their Rover 1 IOCG mine Project complies with all relevant conditions and impact assessments.
Violations of the EPBC Act can lead to various civil and criminal consequences. The Act provides for offences and penalties for non-compliance, which can include substantial fines and imprisonment. For instance, if Queensland Hydro Pty Ltd fails to comply with the environmental impact assessment requirements for their Borumba PHES Project, they could face significant fines or even imprisonment. Similarly, Castile Resources Ltd could face similar penalties if they do not adhere to the conditions set for their Rover 1 IOCG mine Project. The specific penalties can vary depending on the nature and severity of the breach, but the Act ensures that there are severe consequences for failing to comply with its provisions.