Application for Grant of a Pipeline Licence - Woodside Energy Julimar Pty Ltd, KUFPEC Australia (Julimar) Pty Ltd

Administered by Department of Industry, Science and Resources

Legislation au C2020G00030 In force Gazette

Legislation content

 

COMMONWEALTH OF AUSTRALIA

 

Section 708

Offshore Petroleum and Greenhouse Gas Storage Act 2006

 

APPLICATION FOR GRANT OF A PIPELINE LICENCE

 

I, STEVEN ROBERT TAYLOR, delegate of the National Offshore Petroleum Titles Administrator, on behalf of the Commonwealth–Western Australia Offshore Petroleum Joint Authority hereby give notice pursuant to section 708 of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 that an application has been received from

 

Woodside Energy Julimar Pty Ltd

ACN 130 391 365

 

KUFPEC Australia (Julimar) Pty Ltd

ACN 139 500 502

 

for the grant of a pipeline licence for the conveyance of petroleum in the offshore area of Western Australia, as set out below.

 

This notice takes effect on the day in which it appears in the

Australian Government Gazette.

 

Made under the Offshore Petroleum and Greenhouse Gas Storage Act 2006

of the Commonwealth of Australia.

 

STEVEN ROBERT TAYLOR

DELEGATE OF THE TITLES ADMINISTRATOR

ON BEHALF OF THE COMMONWEALTH-WESTERN AUSTRALIA

OFFSHORE PETROLEUM JOINT AUTHORITY

 

 

 

 

 

 

ROUTE OF THE PIPELINE

 

The pipeline route is described in the table hereunder and displaced in the attached map (Attachment 1), commencing at the downstream connector hub face at the Julimar A Drill Centre Manifold to the upstream connector hub face of the existing Brunello A Cross-over Manifold within a corridor of 100m. Coordinates are based on Geodetic Datum of Australia (GDA94).

Feature ID

Feature Name

UTM Zone

Easting

(mE)

Northing

(mN)

1

Julimar-A Drill Centre Manifold

Zone 50

295 229.44

7 770 931.34

2

Julimar-A Flowline End Termination

Zone 50

295 401.46

7 770 949.15

3

Start of first bend (turning point)

Zone 50

295 558.01

7 771 392.93

4

Inflection point of bend 1

Zone 50

295 706.70

7 771 570.13

5

End of first bend (turning point)

Zone 50

295 885.38

7 771 717.04

6

In-Line Tee Assembly to allow for potential future expansion

Zone 50

298 097.04

7 773 535.45

7

Start of second bend (turning point)

Zone 50

310 114.54

7 783 416.19

8

Inflection point of bend 2

Zone 50

310 700.18

7 783 897.70

9

End of second bend (turning point)

Zone 50

311 454.63

7 783 972.80

10

Brunello-A Flowline End Termination

Zone 50

311 949.96

7 784 022.11

11

Brunello-A Cross-over Manifold

Zone 50

311 987

7 784 093

 

SPECIFICATIONS

 

Design and Construction

 

The offshore pipeline must be designed and constructed in accordance with Offshore Standard DNV-OS-F101 – Submarine Pipeline Systems (Offshore Pipeline), which is incorporated in its entirety in Australian Standard AS2885.4 – Pipelines, Gas and Liquid Petroleum (Part 4: Submarine Pipelines). Specifically, the design and construction phase of the pipeline must comply with DNVOS-F101.

 

Basis of Design

 

The pipeline design is based on the following parameters:

 

Item

Item Description

Details

1

Outside diameter of pipe and riser

457.2 mm (18 inches)

2

Wall thickness of pipe inclusive of riser (only for carbon steel)

3 mm

 

3

Length

21.352 km (approximate)

4

Design life

25 years (approximate)

5

Pipeline Material

Rigid Corrosion Resistant Alloy Clad Steel

6

Pipeline and Riser Steel Grade

DNV-OS-F101 Grade 450

7

Pipeline Specification

DNV-OS-F101 High Frequency Weld

8

Minimum yield strength of pipe steel

TBC

9

Maximum Allowable Operating Pressure

36.96 MPa(a)

10

Design Capacity

500 MMscf/d

11

Maximum Design Temperature

134⁰C

12

Minimum Design Temperature

Tie-in spools/FLET: -25⁰C

Flowline/ILT: -20⁰C

13

Characteristics of substance proposed to be conveyed

Gas

14

General plans and descriptions of pump stations, tank stations or valve stations and their equipment

Comprises of an 18-inch CRA clad flowline which will be routed approximately 22 km from a new

JULA drill centre to the existing BRUA XOM. The pipeline terminates at both ends with a FLET structure

and has an ILT approximately 5km from JULA for future tie-in.

15

General plans and description of pigging facilities

N/A

16

Cathodic Protection

29 sacrificial Aluminium-Zinc-Indium anodes installed on the flowline, spools and structures with a spacing of 61 joints.

 

The condition of the cathodic protection will be monitored via periodic ROV survey.

17

Hydrate Management

Insulation and MEG injection

 

Attachment 1

Overview

The Offshore Petroleum and Greenhouse Gas Storage Act 2006 was enacted by the Commonwealth Parliament to provide a regulatory framework for offshore petroleum and greenhouse gas storage activities in Australian waters. This legislation aimed to address the need for coordinated management and regulation of offshore petroleum operations, including the granting of pipeline licences for the conveyance of petroleum in offshore areas. The Act establishes the legislative foundation for the administration of offshore petroleum titles and ensures that activities are conducted in a manner that protects the environment and promotes the sustainable use of resources. The policy objective of the Act is to facilitate the exploration and production of offshore petroleum resources while ensuring that environmental and safety considerations are adequately addressed. This is achieved through a system of licensing, regulation, and oversight by the Commonwealth–Western Australia Offshore Petroleum Joint Authority, as delegated by the National Offshore Petroleum Titles Administrator. The notice published under section 708 of the Act pertains to an application for a pipeline licence by Woodside Energy Julimar Pty Ltd and KUFPEC Australia (Julimar) Pty Ltd for the conveyance of petroleum in the offshore area of Western Australia. The proposed pipeline route, as detailed in the notice, extends from the Julimar A Drill Centre Manifold to the Brunello A Cross-over Manifold within a specified corridor. The design and construction of the pipeline must adhere to stringent standards outlined in Offshore Standard DNV-OS-F101, which is incorporated into Australian Standard AS2885.4. The specifications provided include the pipeline’s outside diameter, wall thickness, length, design life, material, and other critical parameters to ensure the integrity and safety of the pipeline system. The application also outlines provisions for cathodic protection and hydrate management to mitigate potential corrosion and hydrate formation risks. The notice mandates public scrutiny and consultation to ensure that all relevant environmental, safety, and operational aspects are considered before a licence is granted.

Scope and Application

The Offshore Petroleum and Greenhouse Gas Storage Act 2006 applies to the grant of pipeline licences for the conveyance of petroleum in offshore areas, as demonstrated by the application received from Woodside Energy Julimar Pty Ltd and KUFPEC Australia (Julimar) Pty Ltd. The Act governs the process and criteria for granting such licences, ensuring that the construction, operation, and maintenance of offshore pipelines comply with specific standards and regulations. This legislative framework extends to the Commonwealth–Western Australia Offshore Petroleum Joint Authority, which is responsible for the administration and oversight of these activities within the offshore area of Western Australia. The geographic scope of the Act is confined to offshore areas, specifically the region where the proposed pipeline route is to be established. The Act does not specify exclusions or exemptions but relies on the application of standards such as DNV-OS-F101 to ensure compliance with technical and safety requirements. Additionally, the Act may be extended or restricted through subordinate instruments that provide further details on the implementation and enforcement of pipeline licences.

Key Provisions

The main sections of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 that are relevant to this application include section 708, which allows the Titles Administrator to delegate the authority to grant pipeline licences. Section 708(2) specifies that the pipeline must comply with the design and construction standards set out in Offshore Standard DNV-OS-F101, incorporated into Australian Standard AS2885.4. The application for a pipeline licence must include detailed information about the pipeline route, design specifications, and operational parameters, as outlined in the notice and attached documentation. The pipeline must adhere to strict technical standards, including the use of specific materials and construction methods, to ensure safety and durability. The obligations imposed on the parties applying for the pipeline licence are extensive. Woodside Energy Julimar Pty Ltd and KUFPEC Australia (Julimar) Pty Ltd must provide detailed plans and specifications for the pipeline, ensuring it meets all regulatory requirements and standards. This includes the offshore pipeline being designed and constructed in accordance with Offshore Standard DNV-OS-F101. The applicants must also ensure the pipeline is built to withstand the operational conditions specified, such as maximum allowable operating pressures and temperature ranges. Furthermore, the pipeline must be equipped with cathodic protection and hydrate management systems, and the condition of these systems must be regularly monitored. Breaches of the requirements set out in the Offshore Petroleum and Greenhouse Gas Storage Act 2006 can lead to serious consequences. Under section 711, any person who contravenes the Act, including failing to comply with the specified design and construction standards, can be subject to civil or criminal penalties. The maximum penalty for contravening the Act can include fines of up to $5.5 million for individuals and $27.5 million for corporations, reflecting the high stakes associated with offshore petroleum activities. Additionally, the Titles Administrator has the authority to suspend or revoke a pipeline licence if it is found that the pipeline operations are not being conducted in accordance with the licence conditions or the Act.

Legal classification tags

Area of Law
Environmental Law
Energy Law
Instrument
Gazette Notice
Concepts
Reporting & Disclosure Obligations
Licensing & Registration
Compliance Obligations

Interactions

Authorises

All Versions

Sourced from the Federal Register of Legislation at 26 August 2026. For the latest information on Australian Government law please go to https://www.legislation.gov.au.