Application for Grant of a Pipeline Licence (Wilcox Pipeline) – Offshore Area of Western Australia

Administered by Department of Industry, Science and Resources

Legislation au C2026G00285 In force Gazette

Legislation content

 

COMMONWEALTH OF AUSTRALIA

 

Section 708

Offshore Petroleum and Greenhouse Gas Storage Act 2006

 

APPLICATION FOR GRANT OF A PIPELINE LICENCE (WILCOX PIPELINE) – OFFSHORE AREA OF WESTERN AUSTRALIA

 

I, STEVEN ROBERT TAYLOR, Delegate of the National Offshore Petroleum Titles Administrator, on behalf of the Commonwealth–Western Australia Offshore Petroleum Joint Authority hereby give notice pursuant to section 708 of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 that an application has been received from

 

Woodside Energy Ltd.

(ACN 005 482 986)

 

Woodside Energy (North West Shelf) Pty Ltd

(ACN 004 514 489)

 

BP Developments Australia Pty. Ltd. 

(ACN 081 102 856)

 

Chevron Australia Pty Ltd

(ACN 086 197 757)

 

Japan Australia LNG (MIMI) Pty. Ltd.

(ACN 006 303 180)

 

Shell Australia Pty Ltd

(ACN 009 663 576)

 

for the grant of a pipeline licence for the conveyance of petroleum in the offshore area of Western Australia, as set out below.

 

A person may make a written submission to the Titles Administrator about this application within 30 days from the date of this notice.

 

This notice takes effect on the day in which it appears in the

Australian Government Gazette.

 

Made under the Offshore Petroleum and Greenhouse Gas Storage Act 2006

of the Commonwealth of Australia.

 

STEVEN ROBERT TAYLOR 

DELEGATE OF THE TITLES ADMINISTRATOR

ON BEHALF OF THE COMMONWEALTH-WESTERN AUSTRALIA

OFFSHORE PETROLEUM JOINT AUTHORITY

 

ROUTE OF THE PIPELINE

 

The pipeline route is described in the table hereunder and displayed in the attached map (Attachment 1), commencing at the Universal Connection System at the Wilcox A (WCA) Manifold to the Wilcox outlet Flowline End Termination (FLET) within a corridor of ±200 m (±100 m centred on the flowline). For the majority of the route the flexible flowline and the umbilical will be separated by a typical separation of 50 m. The flexible flowline and umbilical take a generally direct path in a north-easterly direction from the WCA manifold to the Wilcox outlet FLET.

All work associated with Wilcox development is as per the following coordinate system:

  • Geodetic Datum: Geodetic Datum of Australia (GDA94)
  • Projection: Universal Transverse Mercator (UTM)
  • Vertical Datum: LAT or MSL (m)

Wilcox Flowline – Route Coordinates

 Feature

KP

Easting [m]

Northing [m]

Radius [m]

Flowline Start (Universal Connection System at the Wilcox A Manifold)

0.0

343 105.08

788 055.39

-

IP 1

3.586

346 028.70

7 790 146.22

1000

IP 2

4.561

346 379.14

7 791 066.92

1000

Telstra Cable Crossing 1

4.689

346 678.68

7 791 430.47

-

Telstra Cable Crossing 2

9.466

349 662.44

7 795 051.78

-

IP 3

19.872

358 396.79

7 805 652.46

1000

Flowline End (Wilcox Outlet FLET Hub

Face)

24.89

359 245.14

7 806 806.74

-


SPECIFICATIONS

 

Design and Construction

 

Manufacturing of the flexible pipe structure is in accordance with API 17J and supplemented by

TechnipFMC standard manufacturing procedures and Woodside specifications.

 

The design, materials qualifications, fabrication, repair, control procedures and QA/QC system of

TechnipFMC flexible pipe structure has “Type Approval” by Bureau Veritas. It applies to static and

dynamic, sweet and sour service applications.

 

The issue of this certification for Type Approval was based upon validation of the design software with the results of full-scale tests performed on multiple TechnipFMC flexible pipe structures.

 

Two different pressure sheath materials are selected. TP37 (PVDF) has a higher maximum design temperature limit and will be used for the sections of the flowline closer to WCA. TP35 (PE) has a lower maximum design temperature limit and will be used for the remainder of the flowline. The flexible pipe layers are typical and may be subject to update.

 

Basis of Design

 

The pipeline design is based on the following parameters:

 

Item

Item Description

Details, Remarks and Units

1

Inside Diameter of Pipe

11-inch (279.4mm)

10-inch (254mm)

2

Wall Thickness of Pipe

47.32mm

42.12mm

3

Length

24.891km

0.220 km

4

Design Life

15 years

15 years

5

Pipeline Construction

Unbonded Flexible Pipe

Unbonded Flexible Pipe

6

Pipeline Material Grade

Smooth Carcass: Stainless Steel

Pressure Sheath: PVDF (TP37), PE (TP35)

Pressure Vault: Carbon Steel

Fabric Tape: Polyester

Tensile Armours: Carbon Steel

High Strength Tape: Aramid Fibre

External Sheath: Thermoplastic Elastomer

Smooth Carcass: Stainless Steel

Pressure Sheath: PVDF (TP37), PE (TP35)

Pressure Vault: Carbon Steel

Fabric Tape: Polyester

Tensile Armours: Carbon Steel

High Strength Tape: Aramid Fibre

External Sheath: Thermoplastic Elastomer

7

Pipeline Specification

Subsea Flexible: Unbonded Flexible Pipe to API 17J

Subsea Flexible: Unbonded Flexible Pipe to API 17J

8

Minimum Yield Strength of Pipe Steel

Various yield strengths are adopted within the flexible cross section.

Various yield strengths are adopted within the flexible cross section.

9

Pipeline System Pressure

Max operating (TP37): 247 bara

Max operating (TP35): 200 bara

Max design: 300 bara

Min design: Vacuum

Max operating: 140 bara

Max design: 300 bara

Min design: Vacuum

10

Design Capacity

300 MMscf/d

300 MMscf/d

11

Maximum Design Temperature

126 ºC (TP37), 90 ºC (TP35)

119 ºC

12

Minimum Design Temperature

-20 ºC

-17 ºC

13

Operating Temperature Range

-15 ºC / 121 ºC (TP37)

-15 ºC / 80 ºC (TP35)

-12 ºC / 114 ºC

14

Characteristics of Substance Proposed to

be Conveyed

Gas and condensate

Gas and condensate

15

General Plans and Descriptions of Pump

A two slot Wilcox Manifold is installed at the start of the Wilcox flowline at KP 0.0 which is nominated as a terminal station.

16

General Plans and Description of Pigging

Facilities

N/A

N/A

17

Cathodic Protection

Sacrificial bracelet anodes, Monitoring via ROV or AUV survey

Sacrificial bracelet anodes,

Monitoring via ROV or AUV survey

18

Hydrate Management

MEG Injection

MEG Injection

 

Preliminary Production Flowline Section Lengths

 Reel No.

Flowline Section

Proposed Length on Reel [m]

1-14

11-inch ID S-Carcass Flexible Flowline (TP37)

1133

15-16

11-inch ID S-Carcass Flexible Flowline (TP35)

1135

17-22

1136

Total

24948

Attachment 1

Interactions

Authorises

All Versions