COMMONWEALTH OF AUSTRALIA
Section 708
Offshore Petroleum and Greenhouse Gas Storage Act 2006
APPLICATION FOR GRANT OF A PIPELINE LICENCE - OFFSHORE AREA OF WESTERN AUSTRALIA
I, GRAEME ALBERT WATERS, the National Offshore Petroleum Titles Administrator, on behalf of the Commonwealth–Western Australia Offshore Petroleum Joint Authority hereby give notice pursuant to section 708 of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 that an application has been received from
Woodside Energy Ltd
(ACN 005 482 986)
BHP Petroleum (North West Shelf) Pty Ltd
(ACN 004 514 489)
BP Developments Australia Pty Ltd
(ACN 081 102 856)
Chevron Australia Pty Ltd
(ACN 086 197 757)
Japan Australia LNG (MIMI) Pty Ltd
(ACN 006 303 180)
Shell Australia Pty Ltd
(ACN 009 663 576)
for the grant of a pipeline licence for the conveyance of petroleum in the offshore area of Western Australia, as set out below.
A person may make a written submission to the Titles Administrator about this application within 30 days from the date of this notice.
This notice takes effect on the day in which it appears in the
Australian Government Gazette.
Made under the Offshore Petroleum and Greenhouse Gas Storage Act 2006
of the Commonwealth of Australia.
GRAEME ALBERT WATERS
TITLES ADMINISTRATOR
ON BEHALF OF THE COMMONWEALTH-WESTERN AUSTRALIA
OFFSHORE PETROLEUM JOINT AUTHORITY
ROUTE OF THE PIPELINE
The pipeline route is described in the table hereunder and displayed in the attached map (Attachment 1), commencing at the Universal Connection System (UCON) connector face on the flexible flowline downstream of the Lambert Deep manifold to the flange upstream of the riser emergency shutdown valve (RESDV) on the Angel Platform within an 80 m corridor (± 40 m centred on the pipeline). Coordinates are based on Geodetic Datum of Australia (GDA94).
Feature | UTM Zone | Easting (mE) | Northing (mN) | Radius m |
J-Tube Entry at Angel Platform | Zone 50 | 457 814 E | 7 843 974 N | |
TP1 | Zone 50 | 457 798 E | 7 843 994 N | |
IP1 | Zone 50 | 457 792 E | 7 844 001 N | 100 |
TP2 | Zone 50 | 457 784 E | 7 844 007 N | |
TP3 | Zone 50 | 457 705 E | 7 844 071 N | |
IP2 | Zone 50 | 457 686 E | 7 844 087 N | 70 |
TP4 | Zone 50 | 457 661 E | 7 844 087 N | |
TP5 | Zone 50 | 456 760 E | 7 844 087 N | |
IP3 | Zone 50 | 456 750 E | 7 844 087 N | 70 |
TP6 | Zone 50 | 456 740 E | 7 844 084 N | |
TP7 | Zone 50 | 455 878 E | 7 843 824 N | |
IP4 | Zone 50 | 455 421 E | 7 843 686 N | 1000 |
TP8 | Zone 50 | 455 026 E | 7 843 956 N | |
TP9 | Zone 50 | 452 366 E | 7 845 769 N | |
IP5 | Zone 50 | 452 238 E | 7 845 857 N | 1000 |
TP10 | Zone 50 | 452 142 E | 7 845 980 N | |
TP11 | Zone 50 | 451 667 E | 7 846 587 N | |
IP6 | Zone 50 | 451 621 E | 7 846 645 N | 500 |
TP12 | Zone 50 | 451 561 E | 7 846 688 N | |
TP13 | Zone 50 | 445 887 E | 7 850 675 N | |
IP7 | Zone 50 | 445 878 E | 7 850 682 N | 30 |
TP14 | Zone 50 | 445 866 E | 7 850 680 N | |
IP8 | Zone 50 | 445 855 E | 7 850 679 N | 30 |
TP15 | Zone 50 | 445 845 E | 7 850 686 N | |
Lambert Deep Manifold | Zone 50 | 445 760 E | 7 850 745 N | |
SPECIFICATIONS
Design and Construction
The offshore pipeline must be designed and constructed in accordance with Offshore Standard DNV-OS-F101 – Submarine Pipeline Systems (Offshore Pipeline), which is incorporated in its entirety in Australian Standard AS2885.4 – Pipelines, Gas and Liquid Petroleum (Part 4: Submarine Pipelines). Specifically, the design and construction phase of the pipeline must comply with DNVGL-ST-F101.
Basis of Design
The pipeline design is based on the following parameters:
Item | Item Description | Details |
1 | Outside diameter of pipe and riser | 254 mm (10 inches) |
2 | Wall thickness of flowline and riser section | TBC |
3 | Length | 14.7 km (approximate) |
4 | Design life | 20 years |
5 | Pipeline Material | Flexible Corrosion Resistant Alloy steel |
6 | Pipeline and Riser Steel Grade | DNVGL-ST-F101 API 17J unbonded flexible pipe |
7 | Pipeline Specification | DNVGL-ST-F101 |
8 | Minimum yield strength of pipe steel | 415 MPa |
9 | Maximum Allowable Operating Pressure | 19.5 MPa(a) |
10 | Design Capacity | 180 MMscf/d |
11 | Maximum Design Temperature | 115 ⁰C |
12 | Minimum Design Temperature | -30 ⁰C |
13 | Operating temperature range | Maximum: 97 – 115 ⁰C Minimum: 21.3 ⁰C |
14 | Characteristics of substance proposed to be conveyed | Gas |
15 | General plans and descriptions of pump stations, tank stations or valve stations and their equipment | Comprises of a 10-inch CRA clad flowline which will be routed from the Lambert Deep manifold drill centre to the Angel Platform. The applicants have requested that the proposed Lambert Deep manifold in Petroleum Production Licence WA‑16‑L be declared as a terminal station pursuant to section 16 of the Act. |
16 | General plans and description of pigging facilities | N/A |
17 | Cathodic Protection | Al-Zn-In sacrificial bracelet anodes Monitoring via ROV or AUV survey |
18 | Hydrate Management | Insulation and MEG injection |
Overview
The Offshore Petroleum and Greenhouse Gas Storage Act 2006 was enacted to establish a framework for the regulation of offshore petroleum and greenhouse gas storage activities. This Act addresses the need for a comprehensive legislative regime to manage the environmental, safety, and economic aspects of offshore petroleum exploration, production, and storage. Enacted by the Parliament of Australia, the policy objective of this Act is to ensure that offshore petroleum activities are conducted in a manner that is safe, environmentally responsible, and economically efficient. The Act provides the legal basis for the regulation of offshore petroleum operations, including the issuance of licenses and permits, the setting of environmental standards, and the imposition of penalties for non-compliance.
The legislation establishes a joint authority between the Commonwealth and the relevant state or territory to administer the Act. This collaborative approach ensures that both federal and state interests are considered in the regulation of offshore activities. The Act also includes provisions for public consultation and the consideration of community impacts, reflecting a commitment to transparency and stakeholder engagement in the decision-making process. Through this legislative framework, the Act aims to balance the development of offshore resources with the protection of the marine environment and the interests of local communities.
Scope and Application
The Offshore Petroleum and Greenhouse Gas Storage Act 2006 applies to the granting of a pipeline licence for the conveyance of petroleum in the offshore area of Western Australia. Specifically, this notice pertains to an application received from Woodside Energy Ltd, BHP Petroleum (North West Shelf) Pty Ltd, BP Developments Australia Pty Ltd, Chevron Australia Pty Ltd, Japan Australia LNG (MIMI) Pty Ltd, and Shell Australia Pty Ltd for such a licence. The application details the design, construction, and operational specifications of the proposed pipeline, including its route, materials, and capacity. This notice is effective upon its publication in the Australian Government Gazette and is issued by the National Offshore Petroleum Titles Administrator on behalf of the Commonwealth-Western Australia Offshore Petroleum Joint Authority. The Act provides for public submissions regarding the application within 30 days of the notice’s publication, allowing stakeholders to voice their concerns or support. The application is subject to compliance with the Offshore Standard DNV-OS-F101 and Australian Standard AS2885.4, ensuring the pipeline's design and construction meet stringent safety and technical standards.
Key Provisions
The notice given under section 708 of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 (the Act) pertains to an application for the grant of a pipeline licence by several companies, including Woodside Energy Ltd, BHP Petroleum (North West Shelf) Pty Ltd, BP Developments Australia Pty Ltd, Chevron Australia Pty Ltd, Japan Australia LNG (MIMI) Pty Ltd, and Shell Australia Pty Ltd, for the conveyance of petroleum in the offshore area of Western Australia. The pipeline's route is described in detail and is depicted in the attached map (Attachment 1), specifying the coordinates based on the Geodetic Datum of Australia (GDA94). The design and construction of the pipeline must adhere to the Offshore Standard DNV-OS-F101 – Submarine Pipeline Systems, as incorporated in Australian Standard AS2885.4 – Pipelines, Gas and Liquid Petroleum (Part 4: Submarine Pipelines), specifically complying with DNVGL-ST-F101. The pipeline design parameters include an outside diameter of 254 mm (10 inches), a length of approximately 14.7 km, a design life of 20 years, and a flexible Corrosion Resistant Alloy steel material.
The Act imposes several obligations and requirements on the parties involved. The offshore pipeline must be designed and constructed according to the specified standards and parameters. This includes the use of flexible Corrosion Resistant Alloy steel for the pipeline material, ensuring compliance with DNVGL-ST-F101 API 17J unbonded flexible pipe. The pipeline's design capacity is set at 180 MMscf/d, with a maximum allowable operating pressure of 19.5 MPa. Additionally, the pipeline must be capable of operating within a temperature range of 97–115 °C and -30 °C. The applicants have requested that the proposed Lambert Deep manifold in Petroleum Production Licence WA-16-L be declared as a terminal station. The design must also incorporate cathodic protection using Al-Zn-In sacrificial bracelet anodes, monitored via ROV or AUV survey, and hydrate management through insulation and MEG injection.
Failure to comply with the provisions of the Act may result in various civil and criminal consequences. The Act provides for offences and penalties for breaches, although specific maximum penalties are not detailed in the notice. Breaches of the Act can lead to enforcement actions, including fines, imprisonment, or both, depending on the nature and severity of the violation. Additionally, the applicants may face legal action if their pipeline does not meet the required standards or if they fail to adhere to the specified operational and safety requirements. The penalties can vary based on the specific provisions of the Act and the circumstances of the breach.