actions determined as requiring approval (EPBC Act s.75)
Reference | Title | Controlling Provisions | Date |
2018/8191 | ADANI INFRASTRUCTURE PTY LTD / Transport - Water / Various lots / Queensland / North Galilee Water Scheme, 160km northwest of Clermont, Qld |
| 17/09/2018 |
actions determined as NOT requiring approval (EPBC Act s.75)
Reference | Title | Date |
2018/8256 | ICON WATER LIMITED / Waste Management (sewerage) / North of Ginninderra Drive, Belconnen, ACT / Australian Capital Territory / Belconnen Trunk Sewer Project, ACT | 10/09/2018 |
2018/8267 | LOGOS DEVELOPMENT MANAGEMENT PTY LTD / Commercial Development / 39 / 43 Marshall Court, Altona, VIC, 3018 / Victoria / Industrial Development 39-43 Marshall Court, Altona, VIC | 13/09/2018 |
2018/8241 | CARPENTARIA RESOURCES LTD / Mining / Multiple lots / New South Wales / Hawsons Iron Project, 60 km south-west of Broken Hill, NSW | 14/09/2018 |
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2018/8191 | ADANI INFRASTRUCTURE PTY LTD / Transport - Water / Various lots / Queensland / North Galilee Water Scheme, 160km northwest of Clermont, Qld | Preliminary Documentation | 17/09/2018 |
2018/8226 | HANSON CONSTRUCTION MATERIALS PTY LTD / Mining / Lot 8, LP219459 / Victoria / Sand quarry, Lot 8 Seereys Road, Coimadai, Vic | Preliminary Documentation | 17/09/2018 |
OUTCOME OF REQUEST FOR RECONSIDERATION OF S75(1) DECISION (EPBC Act s.78C)
Reference | Title | Reconsideration Decision | Date |
2017/8063 | Goldwind Australia Pty Ltd / Energy Generation and Supply (renewable) / Ballark to Elaine / Victoria / Overhead Transmission Line, Ballark to Elaine, Victoria | Not a Controlled Action | 17/09/2018 |
variation of conditions of approval (EPBC Act s.143)
Reference | Title | Date |
2011/6020 | PINJAR PROPERTIES / Residential Development / Lots 4 and 5 Mornington Drive, Mariginiup / Western Australia / National Lifestyle Villages Development | 12/07/2018 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of the Environment and Energy or may not meet timeframes for notification. The Department of the Environment and Energy has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of the Environment and Energy regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.