DEPARTMENT OF THE ENVIRONMENT AND ENERGY
Environment Protection and Biodiversity Conservation Act 1999
For further information see the referrals list at http://epbcnotices.environment.gov.au/referralslist/
and type the reference number in the Filter by Referral Number box
actions determined as requiring approval (EPBC Act s.75)
Reference | Title | Controlling Provisions | Date |
2017/8021 | SIBELCO AUSTRALIA LIMITED/Mining/Parcel Allotment 601, Filled Plan 195213 Wye, and Parcel Section 330 and 331/South Australia/Glenelg Dolomite Quarry | - Wetlands of international importance (sections 16 & 17B)
- Listed threatened species and communities (sections 18 & 18A)
- Listed migratory species (sections 20 & 20A)
| 25/01/2018 |
2017/8032 | Joyful View Garden Real Estate Development Resort Co. Pty Ltd/Mining/Lot 1000 on SP268215/Queensland/Cherrabah Mine and Access Road, south of Warwick, Qld | - Listed threatened species and communities (sections 18 & 18A)
| 29/01/2018 |
2017/8106 | WELLINGTON SHIRE COUNCIL/Transport - Air and Space/Lot 4 on PS704998/Victoria/West Sale Airport Runway Extension, Vic | - Listed threatened species and communities (sections 18 & 18A)
| 29/01/2018 |
2017/8088 | KALIUM LAKES POTASH PTY LTD/Mining/Eastern Pilbara/Western Australia/Beyondie Sulphate of Potash Project, Eastern Pilbara, WA | - Listed threatened species and communities (sections 18 & 18A)
| 30/01/2018 |
2017/8091 | ROADS CORPORATION/Transport - Land/5km east of Mordialloc/Victoria/Mordialloc Bypass Project, Vic | - Wetlands of international importance (sections 16 & 17B)
- Listed threatened species and communities (sections 18 & 18A)
- Listed migratory species (sections 20 & 20A)
| 30/01/2018 |
actions determined as NOT requiring approval (EPBC Act s.75)
Reference | Title | Date |
2017/8105 | HV COKING COAL PTY LIMITED/Mining/Upper Hunter Valley/New South Wales/Integra Underground Mine Longwall Extension Modification, NSW | 15/01/2018 |
2017/8097* | DEPARTMENT OF ECONOMIC DEVELOPMENT JOBS TRANSPORT AND RESOURCES/Exploration (mineral, oil and gas - marine)/Adjacent to Golden Beach township, south Gippsland/Victoria/Pelican 3D Marine Seismic Survey, Gippsland Basin, Vic | 1/02/2018 |
* Actions which are not controlled actions provided they are undertaken in a particular manner. Further information on provision and manner specified is available from http://epbcnotices.environment.gov.au/referralslist/
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2017/8032 | Joyful View Garden Real Estate Development Resort Co. Pty Ltd/Mining/Lot 1000 on SP268215/Queensland/Cherrabah Mine and Access Road, south of Warwick, Qld | Preliminary Documentation | 29/01/2018 |
2017/8088 | KALIUM LAKES POTASH PTY LTD/Mining/Eastern Pilbara/Western Australia/Beyondie Sulphate of Potash Project, Eastern Pilbara, WA | Preliminary Documentation | 30/01/2018 |
DECISION ON APPROVAL (EPBC Act s.133)
Reference | Title | Approval Decision | Date |
2017/7994 | CAPITAL PARTNERS AUSTRALIA PTY LIMITED/Energy Generation and Supply (non-renewable)/191CSH2361/Queensland/Lockyer Energy Project, 2.5 km north of Gatton, QLD | Approved with conditions | 29/01/2018 |
variation of conditions of approval (EPBC Act s.143)
Reference | Title | Date |
2009/4839 | ONEWIND AUSTRALIA PTY LTD/Energy Generation and Supply (renewable)/Between Waddamana township & the eastern shore of Lake Echo/Tasmania/Cattle Hill Wind Farm | 25/01/2018 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of the Environment and Energy or may not meet timeframes for notification. The Department of the Environment and Energy has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of the Environment and Energy regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.
Overview
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) was enacted by the Australian Parliament to address the need for a comprehensive framework for the protection and management of the nation's environment, particularly in relation to biodiversity conservation and the impacts of proposed actions. This legislation provides a mechanism for the Commonwealth to assess and approve certain actions that may have significant environmental impacts, particularly those that involve matters of national environmental significance such as listed threatened species and communities, listed migratory species, and wetlands of international importance. The EPBC Act aims to ensure that the environment is protected and managed in a sustainable manner, contributing to the overall goal of biodiversity conservation. The Department of the Environment and Energy is responsible for the administration of the Act, which includes overseeing the assessment and approval process for proposed actions that may impact the environment. The Department has implemented quality assurance procedures to ensure that notifications are timely and accurate, and late notifications are communicated to the public where identified.
Scope and Application
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) applies to activities that may have a significant impact on matters of national environmental significance, as identified in the Act. These include the World Heritage properties, listed threatened species and ecological communities, listed migratory species, Ramsar-listed wetlands, the nuclear actions, the Commonwealth marine areas, the waters of the Great Barrier Reef Marine Park, and the Commonwealth radioactive materials. The Act applies to both individuals and entities, including corporations and government bodies, engaging in activities that may affect these environmental matters. The geographic scope of the Act is national, with jurisdiction over actions across Australia, including both onshore and offshore areas, and it extends to Australian activities with extraterritorial impacts. The Act can be applied through subordinate instruments, which provide further detail on specific matters such as listed species and communities, or the processes for approval and assessment. Certain activities may be exempt from the Act's requirements, typically where they are already subject to stringent regulation under state or territory laws, or where they are minor and unlikely to have a significant environmental impact. However, exclusions and exemptions are subject to detailed provisions within the Act and related regulations.
Key Provisions
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) governs various activities that may impact the environment, including listed threatened species, communities, and migratory species, as well as wetlands of international importance (sections 16, 17B, 18, 18A, 20, and 20A). Actions determined to require approval under the Act include mining, transport infrastructure, and other projects that could affect the environment (section 75). For instance, the Glenelg Dolomite Quarry by SIBELCO AUSTRALIA LIMITED (2017/8021) and the Cherrabah Mine and Access Road by Joyful View Garden Real Estate Development Resort Co. Pty Ltd (2017/8032) are subject to approval due to their potential environmental impacts. On the other hand, actions determined not to require approval, provided they are undertaken in a specified manner, include modifications to the Integra Underground Mine Longwall Extension by HV COKING COAL PTY LIMITED (2017/8105) and the Pelican 3D Marine Seismic Survey by the Department of Economic Development Jobs Transport and Resources (2017/8097) (section 75).
The Act imposes obligations on entities to ensure that their proposed actions are assessed and approved, if necessary, by the Department of the Environment and Energy. This includes providing detailed documentation about the potential environmental impacts of their projects. For example, Joyful View Garden Real Estate Development Resort Co. Pty Ltd and KALIUM LAKES POTASH PTY LTD have submitted preliminary documentation for their proposed projects (2017/8032, 2017/8088). Entities must also comply with any conditions attached to their approval to mitigate potential environmental harm.
Entities found to be in breach of the Act may face both civil and criminal penalties. Civil penalties for non-compliance can include fines of up to AUD 666,000 for individuals and AUD 3.3 million for corporations (section 528). Criminal offences under the Act can lead to imprisonment for up to five years for individuals and fines of up to AUD 212,000 for corporations (section 528A). Additionally, the Act allows for the imposition of injunctions and other remedies to prevent or remedy environmental harm. These penalties underscore the importance of adhering to the Act's requirements to protect Australia's environment and biodiversity.