Reference | Title | Controlling Provisions | Date |
2018/8359 | LENDLEASE COMMUNITIES (PINE VALLEY) PTY LIMITED / Residential Development / Multiple Lots. Refer to Attachment 2. / Queensland / Pine Valley Residential Development, Morayfield, Qld | - Listed threatened species and communities (sections 18 & 18A)
| 19/03/2019 |
actions determined as NOT requiring approval (EPBC Act s.75)
Reference | Title | Date |
2018/8320 | Queensland Bulk Water Supply authority / Water Management and Use / Bushland Rd, Dennis Rd, Cedar Grove Rd, Cedar Pocket Rd, Undullah Rd, Brookland Rd, Allan Creek Rd.. / Queensland / South West Pipeline and Wyaralong Tanks Project, Qld | 25/03/2019 |
2018/8344 | LOGAN CITY COUNCIL / Waste Management (sewerage) / Approximate central Lot: Lot 4 on RP43903 / Queensland / Greenbank to Flagstone Central Conveyance Pipeline Project, Qld | 27/03/2019 |
2018/8351 | Berrybank Development Pty Ltd / Energy Generation and Supply (renewable) / Berrybank, Victoria / Victoria / Berrybank Windfarm, Berrybank, Vic | 28/03/2019 |
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2018/8359 | LENDLEASE COMMUNITIES (PINE VALLEY) PTY LIMITED / Residential Development / Multiple Lots. Refer to Attachment 2. / Queensland / Pine Valley Residential Development, Morayfield, Qld | Preliminary Documentation | 19/03/2019 |
2019/8414 | Essendon Airport Pty Ltd / Transport - Air and Space / Essendon Fields / Victoria / ARC Commercial Office Development MDP, Essendon Fields Airport, Vic | Accredited Assessment Process under the Airports Act 1996 (Cth) | 22/03/2019 |
DECISION ON APPROVAL (EPBC Act s.133)
Reference | Title | Approval Decision | Date |
2016/7784 | NSW Electricity Networks Operations Pty Ltd / Energy Generation and Supply (renewable) / South of Parkwood Drive, extending up to 900m to the south of Stockdill Drive. / Australian Capital Territory / Construction of new substation and associated transmission line works, ACT | Approved with conditions | 7/03/2019 |
2017/8123 | INFIGEN ENERGY LIMITED / Energy Generation and Supply (renewable) / Lot 800 on SP201454 / Queensland / Bowen Solar Farm, Bruce Highway, Bowen QLD | Approved without conditions | 22/03/2019 |
OUTCOME OF REQUEST FOR RECONSIDERATION OF S75(1) DECISION (EPBC Act s.78C)
Reference | Title | Reconsideration Decision | Date |
2014/7133 | KEPCO BYLONG AUSTRALIA PTY LTD / Mining / Bylong / New South Wales / Bylong Coal Project north east of Mudgee, NSW | Controlled action | 21/03/2019 |
lapsed proposals (EPBC Act s.155)
Reference | Title | Date |
2009/5058 | GEORGE BALIS / Commercial Development / 3040 Remembrance Drive, 4km N of Bargo / New South Wales / Clearing of vegetation for several facilities, Bargo, NSW | 8/03/2019 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of the Environment and Energy or may not meet timeframes for notification. The Department of the Environment and Energy has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of the Environment and Energy regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.
Overview
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) was enacted to provide for the protection of the environment, particularly with respect to matters of national environmental significance. This legislation was introduced by the Commonwealth Parliament to address the gap in environmental protection and to provide a comprehensive framework for the conservation of biodiversity and the management of environmental impacts. The EPBC Act aims to ensure that the Commonwealth’s environmental responsibilities are met effectively by providing for the assessment and approval of actions that may have a significant environmental impact. The Act establishes processes for the identification, assessment, and management of actions that affect listed threatened species, communities, and ecological communities, as well as other matters of national environmental significance.
Scope and Application
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) applies to a broad range of actions that may have a significant impact on matters of national environmental significance, including listed threatened species and ecological communities. The Act applies to both individuals and entities, covering a wide array of industries such as residential development, water management, waste management, and energy generation and supply. The geographic reach of the Act is national, applying across Australia, including the Commonwealth, states, and territories. Certain actions are determined to require approval under the EPBC Act, while others do not, as decided by the Department of the Environment and Energy. The Act's application can also extend or be restricted through subordinate instruments, which provide further detail on how the Act is implemented and enforced. While the Act generally applies to a wide range of activities, there may be exclusions, exemptions, or thresholds specified within the Act or its regulations that determine the applicability of the approval process to specific actions.
Key Provisions
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) (sections 75 and 87) includes provisions for the approval and assessment of certain actions that may impact on matters of national environmental significance. Section 75 sets out the actions that are determined to require approval, while section 87 outlines the assessment approach for these actions. Section 133 details the process for approving such actions, and section 78C pertains to the reconsideration of decisions made under section 75(1). Section 155 addresses lapsed proposals. In the context of the listed projects, Lendlease Communities (Pine Valley) Pty Limited's residential development in Morayfield, Queensland, is an action that requires approval (EPBC Act s.75). The other actions, such as the South West Pipeline and Wyaralong Tanks Project in Queensland, the Greenbank to Flagstone Central Conveyance Pipeline Project in Queensland, and the Berrybank Windfarm in Victoria, are determined not to require approval (EPBC Act s.75).
The Act imposes several obligations on the parties or entities governed by it. These include the duty to provide the necessary information and documentation for the assessment of actions that may impact on matters of national environmental significance. For example, under section 87, the responsible party for the Pine Valley Residential Development in Morayfield, Queensland, must submit preliminary documentation as part of the assessment process. Additionally, the Act requires the Department of the Environment and Energy to implement systems and quality assurance procedures to ensure that public notifications relating to the processing of referrals for approval are not missed or delayed (EPBC Act s.155).
The Act also outlines various offences, penalties, and consequences for breaches of its provisions. For instance, knowingly or recklessly making a false or misleading statement in a document required by the Act is an offence (EPBC Act s.536). The maximum penalty for this offence is 12 months imprisonment or a fine of up to $10,500, or both. Similarly, contravening an approval condition is an offence, with the maximum penalty being 12 months imprisonment or a fine of up to $10,500, or both (EPBC Act s.537). In the case of the Bylong Coal Project in New South Wales, the reconsideration decision under section 78C of the Act indicates that the action is controlled and requires approval. Failure to comply with the conditions of approval could result in civil or criminal consequences, including potential fines or imprisonment.