WA Trolleys Pty Ltd v Johnson

Case [2002] WASC 26 (S)


WA TROLLEYS PTY LTD -v- JOHNSON [2002] WASC 26 (S)



SUPREME COURT OF WESTERN AUSTRALIACitation No:[2002] WASC 26 (S)
Case No:CIV:1983/200029 NOVEMBER 2001
Coram:MASTER SANDERSON21/02/02
22/03/02
3Judgment Part:1 of 1
Result: Judgment for plaintiff for $260,000 plus costs to be taxed
B
PDF Version
Parties:WA TROLLEYS PTY LTD
LESLIE JOHNSON

Catchwords:

Supplementary reasons
Turns on own facts

Legislation:

Nil

Case References:

Nil
Nil

JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
    IN CHAMBERS
CITATION : WA TROLLEYS PTY LTD -v- JOHNSON [2002] WASC 26 (S) CORAM : MASTER SANDERSON HEARD : 29 NOVEMBER 2001 DELIVERED : 21 FEBRUARY 2002 SUPPLEMENTARY
DECISION : 22 MARCH 2002 FILE NO/S : CIV 1983 of 2000 BETWEEN : WA TROLLEYS PTY LTD
    Plaintiff

    AND

    LESLIE JOHNSON
    Defendant



Catchwords:

Supplementary reasons - Turns on own facts




Legislation:

Nil




Result:

Judgment for plaintiff for $260,000 plus costs to be taxed



(Page 2)

Category: B

Representation:


Counsel:


    Plaintiff : Ms A J Crichton-Browne
    Defendant : MrJ P Thomson


Solicitors:

    Plaintiff : Ilberys
    Defendant : Mullins Handcock



Case(s) referred to in judgment(s):

Nil

Case(s) also cited:



Nil

(Page 3)

1 MASTER SANDERSON: On 21 February 2002, I published reasons in relation to this matter. Having published the reasons, I offered the plaintiff and the defendant the opportunity to comment upon any of the calculations I had made regarding damages. I made it plain that any submissions should address simply the mathematical quantification of the damages, not the basis upon which the calculations had been made.

2 The plaintiff raised no issues. The defendant made submissions that the calculation I had made with respect to the Woolworths contract overstated the position. Essentially, the defendant said that the Woolworths contract would have expired in March 2001 and it was therefore not appropriate to adopt a global figure for all contractual revenue over a period of three years.

3 Clearly, this is not an issue which relates solely to mathematical calculation. However, lest there be some misunderstanding on the point, I will clarify the approach that I have adopted. The evidence of John Keith Graham ("Graham") was to the effect that he did not believe that it was possible for a trolley operator to successfully maintain a business in Kalgoorlie unless he had the Coles and the Kmart contracts as well as the Woolworths contract: see par 11 of my reasons. As I was satisfied that the plaintiff's contract with Coles and Kmart would have been renewed for a two-year period, together with a one-year extension, it follows that I accept the plaintiff would have had the Woolworths contract during that time. That is the basis upon which I have calculated the damages. That being so, I am not satisfied that there is any mathematical error in the calculations.

4 Accordingly, there will be judgment for the plaintiff in an amount of $260,000, together with costs of the action, including reserved costs to be taxed. The judgment will be entered from the date upon which these reasons are published.

Details
AGLC
WA Trolleys Pty Ltd v Johnson [2002] WASC 26 (S)
Case
[2002] WASC 26 (S)
Decision Date

CaseChat Overview and Summary

The Supreme Court of Western Australia delivered a judgment in the matter of WA Trolleys Pty Ltd v Johnson, with the case number CIV 1983 of 2000. The plaintiff, WA Trolleys Pty Ltd, sued the defendant, Leslie Johnson, for damages following a breach of contract. The court, presided over by Master Sanderson, had to determine the extent of the damages owed by the defendant to the plaintiff.

The primary legal issue before the court was the calculation of damages owed by the defendant to the plaintiff. The plaintiff claimed that the defendant's actions had led to the loss of a significant contract with Woolworths, which would have provided ongoing revenue for three years. The defendant contested the calculation of damages, arguing that the contract would have expired within a shorter period than considered by the court.

Master Sanderson reviewed the submissions made by both parties and concluded that the initial calculation of damages was correct. The court found that the evidence presented by the plaintiff supported the conclusion that the Woolworths contract would have been in effect for the entire period considered. The court held that there was no mathematical error in the initial calculation of damages and therefore upheld the original judgment.

The court ordered that the defendant pay the plaintiff $260,000 in damages, along with the costs of the action, including reserved costs to be taxed. The judgment was to take effect from the date the reasons were published.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.