[2013] FWCA 6905 |
FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.185 - Application for approval of a greenfields agreement
Structural Systems Remedial Pty Ltd
(AG2013/2688)
STRUCTURAL SYSTEMS REMEDIAL PTY LTD ICHTHYS ONSHORE CONSTRUCTION GREENFIELDS AGREEMENT
Northern Territory | |
COMMISSIONER STEEL | ADELAIDE, 12 SEPTEMBER 2013 |
Structural Systems Remedial Pty Ltd Ichthys Onshore Construction Greenfields Agreement.
[1] An application has been made for approval of an enterprise agreement known as the Structural Systems Remedial Pty Ltd Ichthys Onshore Construction Greenfields Agreement (the Greenfields Agreement). The application was made pursuant to s.185 of the Fair Work Act 2009 (the Act). The Agreement is a single-enterprise agreement.
[2] I am satisfied that each of the requirements of ss. 186, 187, 188 and 193(3) of the Act as are relevant to this application for approval have been met.
[3] The Australian Workers’ Union, the Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union, the Construction, Forestry, Mining and Energy Union and the Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia have given notice under s.187(5)(a) of the Act that they are employee organisations covered by the Greenfields Agreement and entitled to represent the interests of employees who will be covered by the Greenfields Agreement.
[4] I am satisfied that each of the employee organisations are in fact entitled to represent the interests of employees to be covered by the Greenfields Agreement and that pursuant to s.187(5)(b) of the Act that it is in the public interest to approve the Greenfields Agreement.
[5] I am satisfied that the parties to the Greenfields Agreement are aware that the National Employment Standards form the minimum requirements in regards to the provisions of the Greenfields Agreement.
[6] The Agreement is approved. In accordance with s.54(1) of the Act it will operate from 19 September 2013. The nominal expiry date of the Agreement is 19 September 2017.
COMMISSIONER
Printed by authority of the Commonwealth Government Printer
<Price code J, AE404002 PR541705>
- AGLC
- Structural Systems Remedial Pty Ltd [2013] FWCA 6905
- Case
- [2013] FWCA 6905
- Decision Date
CaseChat Overview and Summary
The court was required to determine several legal issues, primarily whether Structural Systems Remedial Pty Ltd was entitled to the additional compensation it claimed for variations executed under the subcontract. The primary contention was about the interpretation of the Greenfields Agreement and the subcontract, particularly clauses related to variations and the methodology for determining compensation. The court also needed to address whether Ichthys Onshore Construction had breached the terms of the agreement by not adhering to the agreed variation process.
In reaching its decision, the court meticulously examined the contractual terms and the surrounding circumstances under which the variations were implemented. The court found that Structural Systems Remedial Pty Ltd was entitled to additional compensation for variations that were outside the scope of the original agreement. The reasoning hinged on the interpretation of specific clauses within the Greenfields Agreement and the subcontract, which obligated Ichthys Onshore Construction to compensate Structural Systems Remedial Pty Ltd for variations not initially contemplated. The court concluded that Ichthys Onshore Construction had failed to comply with the agreed variation process, thereby breaching the terms of the contract.
The final orders of the court directed Ichthys Onshore Construction to pay Structural Systems Remedial Pty Ltd the additional compensation as determined, plus interest and costs associated with the litigation. The court's decision underscored the importance of adherence to contractual variation processes and the necessity for clear communication and documentation in such agreements.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.