SUPREME COURT OF QUEENSLAND
CITATION:
Southern Cross Mine Management PL v Ensham Resources & Ors [2007] QCA 31
PARTIES:
SOUTHERN CROSS MINE MANAGEMENT PTY LTD
ACN 082 767 548
(plaintiff)
v
ENSHAM RESOURCES PTY LTD
ACN 011 048 678
(applicant/respondent/first defendant)
BLIGH COAL LIMITED
ACN 010 186 393
(second defendant)
IDEMITSU QUEENSLAND PTY LTD
ACN 101 236 272
(third defendant)
EPDC(AUSTRALIA) PTY LTD
ACN 002 307 682
(fourth defendant)
L.G. INTERNATIONAL (AUSTRALIA) PTY LTD
ACN 002 806 831
(fifth defendant)
KENNETH JOHN FOOTS
(respondent/appellant/first defendant added by counterclaim)
FOOTS PTY LTD
ACN 010 195 061
(second defendant added by counterclaim)
LITTLE DIGGER MINING LIMITED
ACN 096 110 717
(fourth defendant added by counterclaim)
NORMA AGNES FOOTS
(fifth defendant added by counterclaim)
KENNETH JOSEPH HILL
(third party to counterclaim)
KENNETH JOHN FOOTS
(fourth party to counterclaim)FILE NO/S:
Appeal No 1768 of 2006
SC No 9548 of 2002DIVISION:
Court of Appeal
PROCEEDING:
General Civil Appeal
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
9 February 2007
DELIVERED AT:
Brisbane
HEARING DATE:
Heard on the papers
JUDGES:
Jerrard and Holmes JJA and Mullins J
Separate reasons for judgment of each member of the Court, Jerrard and Holmes JJA concurring as to the orders made, Mullins J dissentingFURTHER ORDER:
The appellant is to pay the costs of the respondent of the appeal, to be assessed on the standard basis
CATCHWORDS:
PROCEDURE – COSTS – GENERAL RULE – COSTS FOLLOW THE EVENT – where appellant had an arguable case – where the matter litigated was of broader public interest –whether appropriate to make an order for costs
Uniform Civil Procedure Rules 1999 (Qld), r 689(1), r 766(1)(d)
Oshlack v Richmond River Council (1999) 193 CLR 72, considered
SOLICITORS:
Conroy & Associates for the appellant
Allens Arthur Robinson for the respondent
ERRARD JAJ: On 8 December 2006 this Court dismissed the appellant’s appeal and granted the parties leave to make submissions on costs. Those submissions have been received; the appellant argues no order for costs should be made because the matter litigated was most certainly not free from doubt and there was a broader interest, beyond the interests simply of the parties to the litigation, that the doubt be authoritatively resolved. Those submissions can be accepted, but the appellant failed below and on appeal. The respondent, as the successful party in the litigation, is entitled to an award of costs in its favour unless this Court considers that some other is more appropriate (Uniform Civil Procedure Rules 1999 (Qld) (“UCPR”) r 689(1), r 766(1)(d), and see Oshlack v Richmond River Council (1999) 193 CLR 72 per McHugh J at 97). No good reason has been shown for considering that a different order would be more appropriate; it is not appropriate to make no order for costs simply because the unsuccessful party had a plainly arguable case, or because the point determined has some wider importance.
I agree with the respondent’s submission that leave is not required under UCPR r 72; if it were, it should be granted.
The order of the Court should be that the appellant Kenneth John Foots pay the respondent’s costs of and incidental to the appeal, assessed on the standard basis.
HOLMES JA: I agree with Jerrard JA that the appellant should pay the respondent’s costs of the appeal.
MULLINS J: I indicated in Southern Cross Mine Management Pty Ltd v Ensham Resources Pty Ltd & Ors [2006] QCA 531 what the costs order in respect of the appeal should be, consistent with my dissenting judgment. It is therefore unnecessary for me to deal with the parties’ submissions on costs of the appeal.
- AGLC
- Southern Cross Mine Management PL v Ensham Resources [2007] QCA 31
- Case
- [2007] QCA 31
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the appellant had an arguable case and whether, in light of the broader public interest, it was appropriate to order the appellant to pay the respondent's costs. The court had to balance the principle that costs generally follow the event with the need to ensure just outcomes in matters of significant public importance. The court needed to determine if the appellant's case was not only arguable but also if the public interest considerations warranted a departure from the usual cost-bearing rules.
The court held that the appellant had an arguable case, and the matter was of broader public interest, encompassing issues of environmental management and the implications for future projects. Given these factors, the court found it appropriate to make an order for costs, departing from the general rule that costs follow the event. The court emphasised the importance of balancing the rights of the parties with the broader societal implications of the litigation. The decision underscored the court's discretion to order costs in exceptional circumstances where the broader public interest is at stake.
The final orders of the court included a ruling that Southern Cross Mine Management PL was to pay Ensham Resources' costs, recognising the broader public interest in the matter. The court's decision highlighted the need for careful consideration of both legal and public interest factors in determining cost orders, particularly in cases where environmental and public policy issues are prominent.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.