SMEC Australia Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd [No 3]
Case
•
[2012] VSC 557
•28 NOVEMBER 2012
Details
AGLC
Case
Decision Date
SMEC Australia Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd [No 3] [2012] VSC 557
[2012] VSC 557
28 NOVEMBER 2012
CaseChat Overview and Summary
SMEC Australia Pty Ltd sought to strike out parts of the amended statement of claim brought by McConnell Dowell Constructors (Aust) Pty Ltd, which sought damages for misleading or deceptive conduct. The Supreme Court was asked to rule on the application to strike out, the appropriateness of the claim for damages, and the connection between the conduct and the alleged losses. The court had to determine whether certain parts of the amended statement of claim could be struck out and how the proceedings should be managed, including whether the issues should be settled by the court through a list of issues.
The court first considered whether certain parts of the amended statement of claim could be struck out under Rule 23.02 of the Supreme Court (General Civil Procedure) Rules 2005. The court found that some parts of the statement of claim were not amenable to being struck out at any time, such as issues related to the causation of loss and the discrete loss sustained. The court held that the contractor needed to prove a causal link between the misleading or deceptive conduct and the discrete loss claimed. The court applied Practice Note No. 2 of 2009 (TEC List) paragraph 40(g) and s 7(1) of the Civil Procedure Act 2010 to manage the proceedings.
The court granted the application to strike out certain parts of the amended statement of claim but found that some issues should remain for determination by the court. The court ordered that the proceeding be closely managed and that a list of issues be settled by the court once pleadings were closed. The court took into account the cost/benefit in proceeding with an issue and the need for the contractor to prove a causal link between the conduct and the discrete loss claimed. The court emphasised that the proceeding should be conducted in a manner that is fair and efficient.
The court made orders that certain parts of the amended statement of claim be struck out, and that the proceeding be closely managed. The court also ordered that a list of issues be settled by the court once pleadings were closed, and that the proceeding be conducted in a manner that is fair and efficient. The court emphasised the need for the contractor to prove a causal link between the misleading or deceptive conduct and the discrete loss claimed. The court's decision provides guidance on the management of complex proceedings and the pleading of claims for damages under the Trade Practices Act 1974 (Cth).
The court first considered whether certain parts of the amended statement of claim could be struck out under Rule 23.02 of the Supreme Court (General Civil Procedure) Rules 2005. The court found that some parts of the statement of claim were not amenable to being struck out at any time, such as issues related to the causation of loss and the discrete loss sustained. The court held that the contractor needed to prove a causal link between the misleading or deceptive conduct and the discrete loss claimed. The court applied Practice Note No. 2 of 2009 (TEC List) paragraph 40(g) and s 7(1) of the Civil Procedure Act 2010 to manage the proceedings.
The court granted the application to strike out certain parts of the amended statement of claim but found that some issues should remain for determination by the court. The court ordered that the proceeding be closely managed and that a list of issues be settled by the court once pleadings were closed. The court took into account the cost/benefit in proceeding with an issue and the need for the contractor to prove a causal link between the conduct and the discrete loss claimed. The court emphasised that the proceeding should be conducted in a manner that is fair and efficient.
The court made orders that certain parts of the amended statement of claim be struck out, and that the proceeding be closely managed. The court also ordered that a list of issues be settled by the court once pleadings were closed, and that the proceeding be conducted in a manner that is fair and efficient. The court emphasised the need for the contractor to prove a causal link between the misleading or deceptive conduct and the discrete loss claimed. The court's decision provides guidance on the management of complex proceedings and the pleading of claims for damages under the Trade Practices Act 1974 (Cth).
Details
Key Legal Topics
Areas of Law
-
Civil Litigation & Procedure
-
Competition Law
Legal Concepts
-
Appeal
-
Jurisdiction
-
Costs
-
Discovery & Disclosure
-
Misleading or Deceptive Conduct
-
Trade Practices Act 1974 (Cth) s 82
Actions
Download as PDF
Download as Word Document
Citations
SMEC Australia Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd [No 3] [2012] VSC 557
Most Recent Citation
ZX Group Pty Ltd v LPD Corporation Pty Ltd [2013] VSC 542
Cases Citing This Decision
4
Oswal v Carson & Ors
[2013] VSC 615
ZX Group Pty Ltd v LPD Corporation Pty Ltd
[2013] VSC 542
Oswal v Carson & Ors
[2013] VSC 615
Cases Cited
11
Statutory Material Cited
0
Keet v Ward
[2011] WASCA 139
Henville v Walker
[2001] HCA 52