Pirelli and Pirelli and Anor (No. 2)

Case

[2018] FamCA 758

25 September 2018


Details
AGLC Case Decision Date
Pirelli and Pirelli and Anor (No. 2) [2018] FamCA 758 [2018] FamCA 758 25 September 2018

CaseChat Overview and Summary

In *Pirelli and Pirelli and Anor (No. 2)*, Hogan J of the Federal Circuit and Family Court of Australia was required to determine an application concerning costs. The application was brought by the Applicant against the First Respondent.

The central legal issue before the court was the appropriate order for costs in relation to an application filed on 23 March 2018, within the context of ongoing property settlement proceedings between the parties.

Hogan J ordered that the First Respondent pay the Applicant's costs of and incidental to the application. These costs were to be assessed on a party/party basis, either by agreement or in accordance with Schedule 3 of the *Family Law Rules 2004* (Cth). The payment of these costs was deferred, to be made within 30 days of either the final order in the property settlement proceedings or the final resolution of those proceedings by other means.
Details

Areas of Law

  • Civil Procedure

  • Family Law

Legal Concepts

  • Costs

  • Remedies

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

3

Statutory Material Cited

3

Yunghanns v Yunghanns [2000] FamCA 681