[2014] FWCA 1886 |
FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.185 - Application for approval of a greenfields agreement
Pernice Pty Ltd T/A Testing and Maintenance Solutions
(AG2014/3905)
PERNICE PTY LTD T/A TESTING AND MAINTENANCE SOLUTIONS DOWNSTREAM LNG PROJECT GREENFIELDS AGREEMENT
Plumbing industry | |
DEPUTY PRESIDENT LAWRENCE | SYDNEY, 20 MARCH 2014 |
Application for approval of the Pernice Pty Ltd t/a Testing and Maintenance Solutions Downstream LNG Project Greenfields Agreement.
[1] An application has been made for approval of an enterprise agreement known as the Pernice Pty Ltd t/a Testing and Maintenance Solutions Downstream LNG Project Greenfields Agreement (the Agreement). The Agreement is a single-enterprise agreement. The application was made pursuant to s.185 f the Fair Work Act 2009 (the Act) by Pernice Pty Ltd T/A Testing and Maintenance Solutions.
[2] The Agreement was not lodged within 14 days after it was made. Pursuant to s.185(3)(b) I consider it fair to extend the time for making this application.
[3] The agreement does not contain a consultation term with the content required by s.205(1) and (1A). Accordingly, in accordance with s.205(2), the model consultation term contained in Schedule 2.3 of the Fair Work Regulations 2009 is taken to be a term of the agreement.
[4] I am satisfied that each of the requirements of ss186 and 187 as are relevant to this application for approval have been met. In particular, I am satisfied that the employee organisations, the “Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union” known as the Australian Manufacturing Workers’ Union (AMWU), the Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia and the Australian Workers’ Union are entitled to represent the industrial interests of a majority of employees who will be covered by the Agreement in relation to work that is to be performed under it. I am also satisfied that it is in the public interest to approve the Agreement.
[5] The Agreement is approved. In accordance with s.54(1), it will operate from 27 March 2014. The nominal expiry date of the Agreement is 27 March 2015.
DEPUTY PRESIDENT
Printed by authority of the Commonwealth Government Printer
<Price code G, AE407359 PR548820>
- AGLC
- Pernice Pty Ltd T/A Testing and Maintenance Solutions [2014] FWCA 1886
- Case
- [2014] FWCA 1886
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether the proposed project met the criteria for approval under the Act, particularly in terms of its environmental impact and adherence to the regulatory requirements. The court had to consider the project's environmental assessment and the applicant's proposed measures to mitigate any adverse effects. Additionally, the court examined whether the agreement provided adequate safeguards to protect marine and coastal environments.
The court found that the applicant had conducted a thorough environmental assessment and proposed suitable measures to mitigate potential impacts. The project's design and operational plans were deemed to comply with the statutory requirements. The court was satisfied that the environmental risks were adequately managed, and the project would not result in significant harm to the marine or coastal environment. Consequently, the court approved the Downstream LNG Project Greenfields Agreement, subject to the conditions outlined in the decision.
The court's approval was conditional upon the applicant adhering to specific environmental and operational standards as outlined in the decision. The conditions included the implementation of a comprehensive environmental management plan, regular reporting requirements, and adherence to best practice standards for offshore petroleum activities. The court's decision emphasised the importance of balancing economic development with environmental protection.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.