Land and Environment Court
of New South Wales
CITATION: Owners Strata Plan 10897 v Woollahra Municipal Council [2004] NSWLEC 5 PARTIES: APPLICANT
RESPONDENT
Owners Strata Plan 10897
Woollahra Municipal CouncilFILE NUMBER(S): 11202 of 2003 CORAM: Hussey C KEY ISSUES: Waste Disposal :- Issue of Direction for preventative action - reasonableness LEGISLATION CITED: Environmental Planning and Assessment Act 1979
Protection of Environmental Operations Act 1997CASES CITED: DATES OF HEARING: 19 January 2004 EX TEMPORE
JUDGMENT DATE :01/19/2004 LEGAL REPRESENTATIVES: RESPONDENT
APPLICANT
Mr J Davies (Representative Strata Body)
Mr M Connell , solicitor
SOLICITORS
Michell Sillar
JUDGMENT:
IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES11202 of 2003
Hussey C
19 January 2004
Owners Strata Plan 10897
Applicant
vJudgmentWoollahra Municipal Council
Respondent
1 . This appeal is against council’s issue of a s 96(1) Direction to take preventative action to rectify unauthorised effluet discharge from a private sewer line discharging into Cooper Street, Paddington.
2 . I understand from the various statements that the discharge problem was evident for some time, with a number of complaints regarding odour being made by various residents.
3 . Mr Lee from council checked the origin of the discharge by placing dye in the sewerage system that confirmed the source of the pollution was the flats at No. 190 Glenmore Road. This resulted in the issue of the s 96 Direction to take preventative action. As the pollution source was traced to the subject property, I consider it was reasonable on the basis of the known information to issue the Direction to rectify the pollution, in order to protect the public interest.
4 . The appeal process allows for an appeal top be lodged within 21 days. However, in this case the work has been completed in the interim period by the Body Corporate at some considerable cost. On an appeal the Court has the discretion to decide whether it is reasonable that the Direction be issued, or further matters such as the basis and time on which the work is to be completed. That option has not been followed in this case, because the work has been completed.
5 . In undertaking the rectification works then, it has been found by the applicant’s licensed plumber that there is a failure of the underlying stormwater pipe which is likely to have contributed to the damage to the sewer because of a reduction in bearing capacity. That being the case, it appears there could be a case for separate action, regarding appropriation of costs.
6 . Furthermore, there is an issue to ensure that the stormwater line is adequately cleaned and repaired so that it will not cause future damage to the private sewer line. However in the ultimate, I consider that there was at the time, reasonable evidence to justify the issue of the Direction to rectify the sewer discharge/pollution.
7 . Accordingly the Court order is that the appeal is dismissed.
___________
R Hussey
Commissioner of the Court
rjs
- AGLC
- Owners Strata Plan 10897 v Woollahra Municipal Council [2004] NSWLEC 5
- Case
- [2004] NSWLEC 5
- Decision Date
CaseChat Overview and Summary
The central legal issue was whether the Council's issuance of the s 96 Direction was reasonable. The court examined the evidence of the pollution source traced to the applicant's property, the completion of rectification works by the Body Corporate, and the discovery of a failure in the underlying stormwater pipe, which might have contributed to the sewer damage. The court also considered the discretion available to decide whether the Direction should be upheld or if further matters, such as the basis and timing of the work, should be addressed. However, the court noted that the work had been completed, limiting the scope of its decision.
In its reasoning, the court acknowledged the reasonable basis for the Council's action in issuing the Direction to protect the public interest, given the known information at the time. The court determined that the appeal should be dismissed, as the Direction was justified based on the available evidence. Additionally, the court noted that separate action could be pursued regarding the appropriation of costs due to the discovered failure in the stormwater pipe. The court also highlighted the importance of ensuring that the stormwater line is adequately cleaned and repaired to prevent future damage to the private sewer line.
The court's final order was to dismiss the appeal, finding that the Council's issuance of the s 96 Direction was reasonable. The court did not entertain further matters such as the basis and timing of the work, as the rectification works had already been completed by the Body Corporate.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.