| [2022] FWCA 560 |
| FAIR WORK COMMISSION |
| DECISION |
Fair Work Act 2009
s.185—Enterprise agreement
Klenner Murphy Electrical Pty Ltd
(AG2022/238)
Klenner Murphy Electrical Pty Ltd and CEPU Electrical Division Cross River Rail Project Agreement 2020-2024
| Electrical contracting industry | |
| COMMISSIONER SIMPSON | BRISBANE, 18 FEBRUARY 2022 |
Application for approval of the Klenner Murphy Electrical Pty Ltd and CEPU Electrical Division Cross River Rail Project Agreement 2020-2024
An application has been made for approval of an enterprise agreement known as the Klenner Murphy Electrical Pty Ltd and CEPU Electrical Division Cross River Rail Project Agreement 2020-2024 (the Agreement). The Application was made pursuant to s.185 of the Fair Work Act 2009 (the Act). It has been made by Klenner Murphy Electrical Pty Ltd (the Applicant). The Agreement is a single enterprise agreement.
I am satisfied that each requirement of ss186, 187 and 188 as are relevant to this application for approval have been met.
The Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia (CEPU) lodged a Form F18 statutory declaration supporting approval of the Agreement and giving notice under s.183 of the Act that it wants the Agreement to cover it. In accordance with s.201(2) of the Act, I note that the Agreement covers the CEPU.
The Agreement is approved and will operate in accordance with s.54 of the Act.
COMMISSIONER
Printed by authority of the Commonwealth Government Printer
<AE515018 PR738506>
- AGLC
- Klenner Murphy Electrical Pty Ltd [2022] FWCA 560
- Case
- [2022] FWCA 560
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the agreement met the statutory requirements for approval under the Fair Work Act. Key issues included whether the agreement was genuinely negotiated and whether it met the "better off overall test" that ensures employees are not worse off financially under the new agreement. Additionally, the court had to consider if the agreement complied with the provisions concerning enterprise agreements and the general protections in the Fair Work Act.
In delivering its decision, the court found that the agreement had been genuinely negotiated and met the better off overall test. The court was satisfied that the agreement was in the best interests of the employees and complied with the statutory requirements for approval. The court emphasised that the agreement provided for improved conditions and benefits, including wage increases and better working conditions, which were beneficial to the employees.
The court approved the Cross River Rail Project Agreement 2020-2024 between Klenner Murphy Electrical Pty Ltd and the CEPU Electrical Division, finding it to be a fair and reasonable enterprise agreement. The approval was made effective from the date of the court's decision, ensuring that the terms and conditions outlined in the agreement would govern the employment relationship for the specified period.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.