CITATION:Jemena Northern Gas Pipeline Pty Ltd v Civmec Constructions & Engineering Pty Ltd & Smith [2019] NTSC 54
PARTIES:JEMENA NORTHERN GAS PIPELINE PTY LTD (ABN 12 607 928 790)
AND:
CIVMEC CONSTRUCTIONS AND ENGINEERING PTY LTD (ABN 98 137 816 025)
AND:
SMITH, Gordon
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT exercising Territory jurisdiction
FILE NO: No. 59 of 2019 (21924329)
DELIVERED ON: 10 July 2019
HEARING DATE: 27 June 2019
JUDGMENT OF: Graham AJ
CATCHWORDS:
CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT 2004 (NT)
– PAYMENT CLAIMS – COSTS
Contracts (Security of Payments) Act 2004 (NT)
REPRESENTATION:
Counsel:
Plaintiff:J Pizer SC & G Crafti
First Defendant: A Wyvill SC & D Alderman
Solicitors:
Plaintiff:Ward Keller as town agent for Hall & Willcox
First Defendant: Hunt & Hunt as town agent for Mills Oakley
Judgment category classification: B
Judgment ID Number: Grah1906
Number of pages: 3
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINJemena Northern Gas Pipeline Pty Ltd v Civmec Constructions & Engineering Pty Ltd & Smith [2019] NTSC 54
No.59 of 2019 (21924329)
BETWEEN:
JEMENA NORTHERN GAS PIPELINE PTY LTD
Plaintiff
AND:
CIVMEC CONSTRUCTIONS AND ENGINEERING PTY LTD
First Defendant
AND:
GORDON SMITH
Second Defendant
CORAM: GRAHAM AJ
RULING
(Delivered 10 July 2019)
Introduction
I delivered a judgement in this matter on Monday 1 July 2019, but reserved the issue of costs and requested the parties to file written submissions on costs by Wednesday 3 July 2019. These submissions are now filed.
It is not in dispute that the plaintiff should be ordered to pay the taxed costs of the first defendant. The issue before me is whether the plaintiff should be ordered to pay costs on an indemnity basis and it is this issue that I will deal with in the ruling.
I make no order in regard to the costs of the second named defendant who filed no appearance and took no part in the hearing.
The first defendant argues that it was not reasonable for the plaintiff to make the application to the court. It was submitted that applications of the kind in question should not be brought unless there are exceptional circumstances. The purpose of the legislation[1] is to enable the rapid and informal determination of payment disputes. It was submitted that an indemnity costs payment would deter others from making similar applications.
The exercise of discretion to order costs on an indemnity basis is restricted to cases where a party has been engaged in unmeritorious, high-handed or improper conduct. A court by ordering indemnity costs is showing its disapproval of the conduct of the unsuccessful party whilst ensuring the successful party is not out of pocket.
I do not find that this is a case where I should exercise my discretion to order indemnity costs. The plaintiff conducted the litigation in a prompt and targeted manner and at the final hearing was seeking to support an interim injunction that had been awarded in its favour. I do not conclude that the litigation falls within the ambit of cases where indemnity costs are ordered.
I will order that the plaintiff pay the costs of the first named defendant, such costs to be taxed in default of agreement. I further certify that this was a matter fit for the attendance of two counsel.
---------------------
[1] Contracts (Security of Payments) Act 2004 (NT).
- AGLC
- Jemena Northern Gas Pipeline Pty Ltd v Civmec Constructions and Engineering Pty Ltd and Smith [2019] NTSC 54
- Case
- [2019] NTSC 54
- Decision Date
CaseChat Overview and Summary
The court considered whether Jemena was liable to pay the claim and whether Civmec was entitled to an adjudication of the claim. It also considered whether, if the claim was not paid, Civmec was entitled to costs under section 20 of the Construction Contracts (Security of Payment) Act 2004 (NT).
The court held that Jemena was liable to pay the claim, and Civmec was entitled to an adjudication. The court noted that Civmec had provided sufficient information to substantiate the claim, and that Jemena had not provided any evidence to counter the claim. The court further held that Civmec was entitled to costs under section 20 of the Act, as Jemena had not paid the claim within the required time. The court noted that Jemena had not demonstrated any exceptional circumstances that would prevent the award of costs.
Jemena was ordered to pay the interim payment claim to Civmec, and to pay Civmec's costs of the proceedings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.