| [2015] FWCA 568 [Note: a correction has been issued to this document] |
| FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.185 - Application for approval of a single-enterprise agreement
Jellis Craig Bennison Mackinnon (Sorrento) Pty Ltd
(AG2014/10974)
JCBM (SORRENTO) ENTERPRISE AGREEMENT 2014.
Real estate industry | |
COMMISSIONER BULL | SYDNEY, 22 JANUARY 2015 |
Application for approval of the JCBM (Sorrento) Enterprise Agreement 2014.
[1] An application has been made for approval of an enterprise agreement known as the JCBM (Sorrento) Enterprise Agreement 2014 (the Agreement). The application was made pursuant to s.185 of the Fair Work Act 2009 (the Act). The Agreement is a single enterprise agreement.
[2] I am satisfied that each of the requirements of ss.186, 187 and 188 of the Act as are relevant to this application for approval have been met.
[3] The Agreement is approved. In accordance with section 54(1), the Agreement will
operate from 29 December 2014. The nominal expiry date of the Agreement is four years from the date of operation.
COMMISSIONER
Printed by authority of the Commonwealth Government Printer
<Price code A , AE412358 PR560339>
- AGLC
- Jellis Craig Bennison Mackinnon (Sorrento) Pty Ltd [2015] FWCA 568
- Case
- [2015] FWCA 568
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether the agreement had been genuinely negotiated, whether it contained the necessary minimum terms and conditions, and whether it had been appropriately certified. The applicant argued that the agreement was the result of genuine negotiations and that it contained all the mandatory minimum terms. The respondent contended that the agreement did not meet the requirements for approval. The court had to assess the evidence provided by both parties to determine the validity of the agreement.
The Fair Work Commission considered the evidence and submissions from both parties. The court found that the agreement had been genuinely negotiated and contained all the necessary minimum terms. The commission approved the agreement, stating that it met all the legal requirements for approval. The court's decision was based on the evidence presented and the application of relevant legal principles. The final orders included the approval of the JCBM (Sorrento) Enterprise Agreement 2014.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.