Land and Environment Court
of New South Wales
CITATION: Hoyts Cinemas Limited (ACN 066 234 900) v Penrith City Council & Anor [2000] NSWLEC 31 PARTIES: Hoyts Cinemas Ltd (Applicant)
Penrith City Council (First Respondent
Penrith Panther's Rugby League Club Limited (Second Respondent)FILE NUMBER(S): 40246 of 1998 CORAM: Lloyd J KEY ISSUES: Costs :- Applicant unsuccessful - whether both respondents entitled to orders for costs. LEGISLATION CITED: Land & Environment Court Act 1979, s 69 CASES CITED: DATES OF HEARING: 22/10/99 EX TEMPORE
JUDGMENT DATE :10/22/1999 LEGAL REPRESENTATIVES:
Applicant: D T Miller (Barrister)
SOLICITORS:
Cutler Hughes & Harris
Second Respondent: B A J Coles QC
SOLICITORS:
Mallesons Stephen Jaques
JUDGMENT:
1. This is a notice of motion by the second respondent for an order that the applicant pay its costs. The principal proceedings were heard on 21 and 22 June 1999 and in a reserved judgment delivered on 13 August 1999 I dismissed the application but reserved the question of costs. The applicant has consented to meeting the first respondent’s costs.
2. The applicant submits that no costs order should be made in favour of the second respondent because it was not a necessary party and its participation in the proceedings added nothing to the case. I do not agree.
3. The second respondent was the beneficiary of the development consent, the validity of which was sought to be impugned by the applicant in the proceedings. It thus had a proprietary interest in seeking to uphold the validity of that consent.
4. Mr Duncan Miller, who appears for the applicant, submits that the primary argument was directed to the council's, that is the first respondent's, conduct in its determination of the development application. There were other questions, namely questions of law which also had to be resolved, in particular the question of the validity of the means of access to the site which formed part of the proposed development for which consent had been granted.
5. Mr Miller also submits that since the primary argument in the case was directed to the council's manner of dealing with the development application and its consideration thereof and the Council sought in the proceedings to uphold the validity of what it had done there was nothing that the second respondent could add.
6. I should say that in relation to the question of access and the validity of consent as regards the access, the Court derived considerable assistance from the participation of Mr Bernard Coles QC who appeared for the second respondent in the proceedings. In particular the Court accepted the submissions of Mr Coles on that issue and those submissions were largely adopted by me in the judgment; and I must say I personally derived considerable assistance on the submissions of Mr Coles QC in this case.
7. It was in my opinion necessary for Mr Coles QC to be here throughout the case, both to hear the applicant's opening, to be present when the evidence (which was largely documentary) was tendered and to be here when the submissions of the other parties were made so that his submissions could be modified accordingly if necessary. It was also proper I think for Mr Coles QC to prepare submissions on all the issues that were raised in the proceedings lest any should be overlooked by the first respondent.
8. In my opinion, although the Court has a wide ranging discretion as to costs under s 69 of the Land & Environment Court Act 1979 that discretion must be exercised judicially. It is a cardinal principle in the exercise of that judicial discretion, that a successful party should except in special circumstances have its costs.
9. I n my opinion there is nothing in the present case which should displace that principle.
10. Accordingly I make the order sought in para 1 of the second respondent's notice of motion dated 2 September 1999, as follows:
Order that the applicant pay the second respondent’s costs (pursuant to s 69(2) Land & Environment Court Act 1979)
- AGLC
- Hoyts Cinemas Limited (ACN 066 234 900) v Penrith City Council [2000] NSWLEC 31
- Case
- [2000] NSWLEC 31
- Decision Date
CaseChat Overview and Summary
The court held that the second respondent's involvement was justified because it held a proprietary interest in the development consent, which was directly challenged by the applicant. The court found that the submissions made by counsel for the second respondent, Bernard Coles QC, provided significant assistance in resolving issues related to the validity of the access to the site, which were crucial to the case. Lloyd J concluded that the second respondent's participation was necessary for a comprehensive consideration of all issues, and thus, the principle that a successful party should generally be awarded its costs should be upheld. The court exercised its discretion under section 69 of the Land and Environment Court Act 1979 to order that the applicant pay the second respondent's costs.
In light of the above, the court granted the second respondent's motion for an order that the applicant pay its costs. The decision affirmed that the second respondent's participation was not only necessary but also beneficial, justifying the award of costs against the unsuccessful applicant. This ruling underscores the importance of necessary parties in legal proceedings and the court's discretion in awarding costs under the relevant legislation.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.