| [2017] FWCA 2676 |
| FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.185—Enterprise agreement
Grant’s Coachlines Pty Ltd
(AG2017/937)
GRANT’S COACHLINES ENTERPRISE AGREEMENT 2016
Passenger vehicle transport (non rail) industry | |
COMMISSIONER ROE | MELBOURNE, 17 MAY 2017 |
Application for approval of the Grant’s Coachlines Enterprise Agreement 2016.
[1] An application has been made for approval of an enterprise agreement known as the Grant’s Coachlines Enterprise Agreement 2016 (the Agreement). The application was made pursuant to s.185 of the Fair Work Act 2009 (the Act). It has been made by Grant’s Coachlines Pty Ltd. The Agreement is a single enterprise agreement.
[2] The Applicant has provided written undertakings. A copy of the undertakings is attached in Annexure A. I am satisfied that the undertakings will not cause financial detriment to any employee covered by the Agreement and that the undertakings will not result in substantial changes to the Agreement.
[3] Subject to the undertakings referred to above, I am satisfied that each of the requirements of ss.186, 187, 188 and 190 as are relevant to this application for approval have been met.
[4] The Agreement was approved on 17 May 2017 and, in accordance with s.54, will operate from 24 May 2017. The nominal expiry date of the Agreement is 1 July 2019.
COMMISSIONER
Printed by authority of the Commonwealth Government Printer
<Price code G, AE424354 PR592950>
Annexure A
- AGLC
- Grant’s Coachlines Pty Ltd [2017] FWCA 2676
- Case
- [2017] FWCA 2676
- Decision Date
CaseChat Overview and Summary
The primary issue was whether the agreement met the requirements of the Fair Work Act 2009 and the Fair Work Regulations 2009. Specifically, the court needed to assess whether the agreement provided for a fair and reasonable set of terms and conditions for the employees, and whether it had been genuinely agreed upon by the parties.
The Commissioner found that the agreement was fair and reasonable, meeting all the statutory requirements. The application was approved, and the agreement was approved for registration. The Commissioner considered the process by which the agreement was negotiated and the evidence presented by both parties. The Commissioner concluded that the agreement was the result of genuine bargaining and provided for fair and reasonable terms and conditions for the employees.
The Fair Work Commission approved the Grant’s Coachlines Enterprise Agreement 2016 and ordered its registration. The agreement was to take effect from the first day of July 2016.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.