Gosford City Council v Beville [Costs]

Case [2003] NSWLEC 80


>

Land and Environment Court


of New South Wales


CITATION: Gosford City Council v Beville [Costs] [2003] NSWLEC 80
PARTIES:

APPLICANT
Gosford City Council

RESPONDENT
John Alexander Beville
FILE NUMBER(S): (4)0477 of 2002
CORAM: Pain J
KEY ISSUES: Costs :- Class 4 - breach of Environmental Planning and Assessment Act 1979 - whether costs should be awarded
LEGISLATION CITED: Land and Environment Court Act 1979 s 69
CASES CITED: Richmond River Council v Oshlack (1996) 39 NSWLR 622
DATES OF HEARING: 19/02/2003
EX TEMPORE
JUDGMENT DATE :

02/19/2003
LEGAL REPRESENTATIVES:


APPLICANT
Mr P Donnellan (solicitor)
SOLICITORS
PJ Donnellan & Co

RESPONDENT
Mr B Spinks (solicitor)
SOLICITORS
Robinson Legal


JUDGMENT:

IN THE LAND AND


ENVIRONMENT COURT


OF NEW SOUTH WALES

                          (4) 0477 of 2002

                          Pain J

                          19 February 2003
GOSFORD CITY COUNCIL
                                  Applicant
      v
JOHN ALEXANDER BEVILLE
                                  Respondent
Judgment on Costs

1. It does seem to me that the Council was essentially successful in this matter. There was a slight modification of the order sought, but that was to ameliorate the impact of the declarations and demolition order because the complying development certificate is void.

2. I have broad discretion under s 69 of the Land and Environment Court Act 1979 to deal with costs. The usual practice of the Court is that the successful party receives its costs. Applying the Court of Appeal decision of Clarke J in Richmond River Council v Oshlack (1996) 39 NSWLR 622 there was no disentitling behaviour on the Council’s part. I adopt Mr Donnellan’s submissions in relation to this case, which I understand to represent the law on this aspect. In all the circumstances I do think it is appropriate that the Council get its costs.

3. I will make the declarations and orders as set out in the minutes of order handed up this morning by the parties, with the addition of the letter "A" at the end of order 4 and the plan being marked accordingly. I will also add order 6, that the Respondent pay the Applicant's costs as agreed or assessed and order 7, the exhibits may be returned.

Orders and declarations

The Court declares that:


1. The development, being the timber decking and ramp erected at the rear of the land being Lot 1 in Deposited Plan 201059 at 54 Coral crescent, Pearl Beach in the State of New South Wales, is not complying development.


2. The complying development certificate determined on 29 November 2001 by Jennifer Dallas, Accredited Certifier/Principal Certifying Authority No 6010, with respect to complying Development No 1011/01 relating to the Development is void and of no effect.


3. The Development is unlawful.

The Court orders that:


4. The Respondent be required to demolish so much of the timber deck and ramp as is seaward of the outer edge of the existing concrete patio attached to the rim of the dwelling as indicated on the attached plan "A".


5. The said demolition be carried out within three months of the date of these Orders.


6. The Respondent pay the Applicant's costs as agreed or assessed.


7. The exhibits may be returned.

Details
AGLC
Gosford City Council v Beville [Costs] [2003] NSWLEC 80
Case
[2003] NSWLEC 80
Decision Date

CaseChat Overview and Summary

The Land and Environment Court of New South Wales dealt with an application for costs in the case of Gosford City Council v Beville. The council sought to enforce compliance with planning regulations against John Alexander Beville, who had constructed an unauthorised timber deck and ramp at his property. The council sought a declaration that the development was not complying, that the certificate issued for the development was void, and an order for the deck and ramp to be demolished. The court agreed with the council and issued the declarations and orders sought, with a modification to the demolition order to limit its impact.

The legal issue before the court was whether the council, as the successful party, was entitled to its costs under section 69 of the Land and Environment Court Act 1979. The court found that there was no disentitling behaviour on the part of the council, adopting the submissions of the council’s solicitor and the decision in Richmond River Council v Oshlack. The court concluded that the council was entitled to its costs as the successful party.

In the resulting orders, the court declared that the deck and ramp were not complying development and that the certificate issued for the development was void. The court ordered the respondent to demolish the portion of the deck and ramp that was seaward of the existing concrete patio. The court also ordered the respondent to pay the council’s costs as agreed or assessed, and that the exhibits could be returned.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.