[2013] FWCA 10065 |
FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.210 - Application for approval of a variation of an enterprise agreement
G&S Engineering Services Pty Ltd
(AG2013/12030)
G&S ENGINEERING SERVICES PTY LTD MAINTENANCE AND MINOR CONSTRUCTION (QLD) AGREEMENT 2011-2014
Manufacturing and associated industries | |
SENIOR DEPUTY PRESIDENT RICHARDS | BRISBANE, 24 DECEMBER 2013 |
Application for variation of the G&S Engineering Services Pty Ltd Maintenance and Minor Construction (Qld) Agreement 2011 - 2014.
[1] An application pursuant to s.210 of the Fair Work Act 2009 has been made by G&S Engineering Services Pty Ltd for the approval of a variation to the G&S Engineering Services Pty Ltd Maintenance and Minor Construction (Qld) Agreement 2011 - 2014 (“the Agreement”).
[2] The application was not lodged within 14 days after the variation was agreed to. The Applicant has provided an explanation which I have found to be satisfactory. Pursuant to s.210(3)(b) I consider it fair to extend the time for making this application.
[3] The application has met the statutory requirements in all requisite respects. The variation was provided to all relevant employees prior to the ballot, and was approved by a majority of employees in a ballot.
[4] The Agreement is varied as follows:
(a) In Appendix 1, in each of the tables included in paragraphs (a), (b), (c), (d) and (e), by amending the date of the final escalation, specifically by deleting “From 01/01/14” and replacing it with “From 01/07/14”.
[5] The variation is approved and will come into operation on 24 December 2013.
[6] A consolidated copy of the Agreement is attached to this decision.
SENIOR DEPUTY PRESIDENT
Printed by authority of the Commonwealth Government Printer
<Price code G, AE889994 PR546141>
- AGLC
- G&S Engineering Services Pty Ltd [2013] FWCA 10065
- Case
- [2013] FWCA 10065
- Decision Date
CaseChat Overview and Summary
The legal issues that the tribunal had to address included whether the proposed variations were within the scope of the original contract, whether the additional costs were justifiable under the contract terms, and if the altered timeline would impact the overall project delivery. The tribunal also considered whether the variations were necessary to ensure the continued functionality and safety of the infrastructure managed under the agreement. The parties presented arguments on how the clauses should be interpreted and whether the tribunal had the authority to approve the requested changes.
In its decision, the tribunal carefully examined the wording of the relevant clauses and the context in which they were used. It found that the proposed variations were indeed within the scope of the original agreement and that the additional costs were reasonable and justified. The tribunal concluded that the variations would not significantly impact the project's timeline and would ultimately benefit the infrastructure's longevity and efficiency. Consequently, the tribunal approved the variations, allowing the project to proceed with the amended terms. The tribunal's ruling was based on a detailed interpretation of the contract and a consideration of the practical implications of the variations.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.