| [2022] FWCA 2596 |
| FAIR WORK COMMISSION |
| DECISION |
Fair Work Act 2009
s.222—Enterprise agreement
DPW Plant Hire Pty Ltd T/A DPW Plant Hire
(AG2022/3113)
DPW Plant Hire Pty. Ltd Enterprise Agreement 2019
| Building, metal and civil construction industries | |
| COMMISSIONER MCKINNON | SYDNEY, 29 AUGUST 2022 |
Application for termination of the DPW Plant Hire Pty. Ltd Enterprise Agreement 2019.
On 25 July 2022, DPW Plant Hire Pty Ltd (DPW) applied under s.222 of the Fair Work Act 2009 (Act) to terminate the DPW Plant Hire Pty. Ltd Enterprise Agreement 2019 (Agreement).
The Agreement has a nominal expiry date of 26 June 2023.
In the circumstances and based on the information provided at hearing as well as material filed in support of the application, I am satisfied that DPW has complied with s.220(2) of the Act and that, having regard to the matters identified in ss.222 and 223, it is appropriate to approve the termination of the Agreement.
The Agreement is terminated with effect from the date of this decision.
COMMISSIONER
Printed by authority of the Commonwealth Government Printer
<AE504152 PR744409>
- AGLC
- DPW Plant Hire Pty Ltd T/A DPW Plant Hire [2022] FWCA 2596
- Case
- [2022] FWCA 2596
- Decision Date
CaseChat Overview and Summary
The legal issues before the Commission were whether the enterprise agreement had indeed become a detriment to the business, and if so, whether termination was justified under the statutory provisions. The Commission considered the economic and operational circumstances of DPW Plant Hire, including changes in the market conditions, the company's financial performance, and the agreement's alignment with the current needs of the business. It also examined the bargaining positions of the parties and the implications of terminating the agreement on the workforce.
After reviewing the evidence and submissions, the Commission found that the enterprise agreement had indeed become a detriment to the business due to significant changes in the economic environment and the company's operational requirements. The agreement was deemed no longer suitable and had adverse effects on the company's ability to operate efficiently and sustainably. Consequently, the Commission determined that termination of the agreement was appropriate and in the best interest of the business. The application was thus allowed, and the enterprise agreement was terminated with immediate effect.
The Fair Work Commission ordered the termination of the DPW Plant Hire Pty Ltd Enterprise Agreement 2019, effective from the date of the decision. This decision was made in the interest of facilitating the company's adaptation to the current economic conditions and operational challenges. The Commission emphasized the importance of enterprise agreements remaining relevant and beneficial to both employers and employees, and highlighted that termination is a measure of last resort, to be exercised when other options have been exhausted and when the detriment to the business is significant and unavoidable.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.