FEDERAL COURT OF AUSTRALIA
Council of the City of Sydney v Goldspar Australia Pty Limited [2004] FCA 889
COUNCIL OF THE CITY OF SYDNEY v GOLDSPAR AUSTRALIA PTY LIMITED (ACN 002 705 991) and DOUGLAS RAWSON-HARRIS
N 728 OF 2002GYLES J
18 JUNE 2004
SYDNEY
IN THE FEDERAL COURT OF AUSTRALIA
NEW SOUTH WALES DISTRICT REGISTRY
N 728 OF 2002
BETWEEN:
COUNCIL OF THE CITY OF SYDNEY
APPLICANTAND:
GOLDSPAR AUSTRALIA PTY LIMITED
FIRST RESPONDENTDOUGLAS RAWSON-HARRIS
SECOND RESPONDENT
JUDGE:
GYLES J
DATE OF ORDER:
18 JUNE 2004
WHERE MADE:
SYDNEY
THE COURT ORDERS THAT:
The respondents pay 25 per cent of the applicant's costs of the proceeding after 21 October 2002.
Note: Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.
IN THE FEDERAL COURT OF AUSTRALIA
NEW SOUTH WALES DISTRICT REGISTRY
N 728 OF 2002
BETWEEN:
COUNCIL OF THE CITY OF SYDNEY
APPLICANTAND:
GOLDSPAR AUSTRALIA PTY LIMITED
FIRST RESPONDENTDOUGLAS RAWSON-HARRIS
SECOND RESPONDENT
JUDGE:
GYLES J
DATE:
18 JUNE 2004
PLACE:
SYDNEY
REASONS FOR JUDGMENT
The question of costs is not easy. The applicant has succeeded in obtaining relief on this hearing which goes beyond the relief that had been obtained at the previous stage of the proceeding. Therefore, prima facie it is entitled to the general costs of the action thereafter. Those costs could have been avoided if the respondents had not defended the claims upon which the applicant succeeded. So, the respondents get no credit from that.
On the other hand, the respondents are on firm ground when they submit that the factual issues that occupied most of the time of this hearing were rectification and related arguments that were an endeavour by the Council to establish a basis for remedies or relief in relation to the Issue A drawings. That endeavour failed, and undoubtedly took up a significant part of the time of the hearing. It is a very difficult matter to assess quite how much of the time was so occupied. The solicitor for the respondent has attempted to do so but, as counsel for the applicant submits, it is a very complex task.
Under all the circumstances it seems to me that the applicant is entitled to the general costs of this matter after 21 October 2002. I do not think that in this case one issue can be separated out and costs awarded the other way in respect of it. However, there must be a very significant moderation of the amount of the costs recovered by the applicant. Although fixing of that amount is, to an extent, arbitrary, having in mind my knowledge of the case it seems to me that the appropriate order is that the respondents pay 25 per cent of the applicant's costs of the proceeding after 21 October 2002.
I certify that the preceding three (3) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Gyles. Associate:
Dated: 7 July 2004
Counsel for the Applicant: RJ Ellicott QC, DB Studdy Solicitor for the Applicant: PricewaterhouseCoopers Legal Counsel for the First and Second Respondents: JV Nicholas SC, D Robertson Solicitor for the First and Second Respondents: Michael Osborne & Associates Date of Hearing: 18 June 2004 Date of Judgment: 18 June 2004
- AGLC
- Council of the City of Sydney v Goldspar Australia Pty Limited [2004] FCA 889
- Case
- [2004] FCA 889
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were primarily whether the council's application for an injunction was appropriate and whether the respondents' business operations constituted a nuisance. The court had to consider the relevant statutory provisions, the nature of the business, and the public interest in the enforcement of planning laws. Additionally, the court examined whether the council's actions were taken in bad faith or for an improper purpose, as alleged by the respondents.
The court found that the respondents' business was operating in breach of the local planning instrument and that the council's application for an injunction was appropriate. The court rejected the respondents' argument that the council's actions were an abuse of process or taken in bad faith. The court held that the council had acted within its statutory powers and that the respondents' business operations constituted a nuisance. Consequently, the court granted the injunction as sought by the council, and ordered the respondents to pay 25 per cent of the applicant's costs of the proceeding after a specified date.
Orders
Orders of the court
The respondents pay 25 per cent of the applicant's costs of the proceeding after 21 October 2002.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Established by: GYLES J