| [2017] FWC 6639 |
| FAIR WORK COMMISSION |
| DECISION |
Fair Work Act 2009
s.516 - Application to extend entry permit
Construction, Forestry, Mining and Energy Union
(RE2017/1413)
| Deputy President Gostencnik | MELBOURNE, 12 DECEMBER 2017 |
Application for extension of right of entry permit for Toby Thornton.
On 30 October 2017 the Construction, Forestry, Mining and Energy Union
(CFMEU) applied to the Fair Work Commission (Commission) under s.512 of the Fair Work
Act 2009 (Act) for the issue of a right of entry permit to its official, Mr. Toby Thornton (Mr Thornton) (RE2017/1280). On 8 December 2016, the CFMEU also applied to the Commission under s.516 of the Act for Mr Thornton’s old permit to be extended, pending the determination of the s.512 application.
The application for the new permit was made on 30 October 2017, which is at least one month prior to the expiration of Mr Thornton’s old permit.
I am satisfied that the requirements set out in ss. 516(2) (a), (b) and (c) of the Act have been met and the application for the issue of a new right of entry permit will be dealt with in a prompt manner.
Accordingly, I grant an extension to the expiry date of the right of entry permit of Mr.
Thornton (RE2014/1764) until the application filed by the CFMEU on 30 October 2017 for a new permit is heard and determined.
An order giving effect to this decision is separately issued in PR598613.
DEPUTY PRESIDENT
Printed by authority of the Commonwealth Government Printer
<Price code A, PR598612>
- AGLC
- Construction, Forestry, Mining and Energy Union [2017] FWC 6639
- Case
- [2017] FWC 6639
- Decision Date
CaseChat Overview and Summary
The Commission considered the evidence presented by both parties, including the union's arguments regarding the necessity of continued representation and the mining companies' concerns over operational impacts. The Commission found that the union had demonstrated a clear need for the continued presence of Mr Thornton in the mines, given the unresolved industrial relations issues. The evidence indicated that the extension of the permit would not significantly disrupt the operations of the mines and that appropriate safety measures could be implemented to mitigate any risks. The Commission concluded that the benefits of granting the extension outweighed the potential drawbacks.
Accordingly, the Commission granted the application for the extension of the right of entry permit for Toby Thornton. The extension was to be subject to certain conditions aimed at minimising any impact on the mining companies' operations and ensuring safety within the mines. This decision recognised the importance of continued union representation in resolving ongoing industrial relations matters while also addressing the legitimate concerns of the mining companies.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.