Colin de Lore and Associates Pty Limited v Canterbury-Bankstown Council

Case [2016] NSWLEC 1437


Land and Environment Court


New South Wales

Medium Neutral Citation: Colin de Lore & Associates Pty Limited v Canterbury-Bankstown Council [2016] NSWLEC 1437
Hearing dates:Conciliation conference on 5 July 2016
Date of orders: 26 September 2016
Decision date: 26 September 2016
Jurisdiction:Class 1
Before: Fakes C
Decision:

See (4) below

Catchwords: DEVELOPMENT APPLICATION; Multi-storey boarding house; conciliation conference; agreement between the parties; orders
Legislation Cited: Land and Environment Court Act 1979
Category:Principal judgment
Parties: Colin de Lore & Associates Pty Limited (Applicant)
Canterbury-Bankstown Council (Respondent)
Representation:

Applicant: Mr P Jackson (Solicitor)
Respondent: Mr A Seton (Solicitor)

  Solicitors:
Applicant: Pikes & Verekers Lawyers
Respondent: Marsdens Law Group
File Number(s):153783 of 2016
Publication restriction:No

Judgment

  1. COMMISSIONER: In this matter, at or after a conciliation conference, an agreement under s 34(3) of the Land and Environment Court Act 1979 (the Court Act) was reached between the parties as to the terms of a decision in the proceedings that was acceptable to the parties. As the presiding Commissioner, I was satisfied that the decision was one that the Court could have made in the proper exercise of its functions (this being the test applied by s 34(3) of the Court Act). As a consequence, s 34(3)(a) of the Act required me to “dispose of the proceedings in accordance with the decision”.

  2. The Court Act also required me to “set out in writing the terms of the decision” (s 34(3)(b)). The orders made to give effect to the agreement constitute that document.

  3. In making the orders to give effect to the agreement between the parties, I was not required to, and have not, made any merit assessment of the issues that were originally in dispute between the parties.

  4. The final orders to give effect to the parties’ agreement under s34(3) of the Land and Environment Court Act 1979 are:

  1. The Applicant is given leave to amend the development application by substituting the following plans as the plans relied upon for the purpose of the development application:

  1. Plan submitted by Colin De Lore & Associates, comprising Drawing No. DA00 (Finishes Schedule), DA02, DA03, DA04, DA05, DA06, DA07, DA08, DA09, DA10, DA11, DA12 and DA13, Revision H, dated 24 August 2016, prepared by McCullum Ashby Architects

  1. The Applicant is to pay those costs of the Respondent thrown away as a result of amending the development application pursuant to section 97B(2) of the Environmental Planning and Assessment Act 1979 in the sum of $9,000 within 28 days of the date of these Orders.

  2. The Appeal is upheld.

  3. Development Application No. DA-928/2015 for the demolition of existing structures and the construction of a 9 storey building including ground floor café, first floor office premises, and a boarding house on floors two to eight including 18 boarding rooms, a caretakers/managers unit and a common room, with on-site car parking for five vehicles (one (1) car stacking system capable of accommodating four (4) car spaces, and a separate accessible car space at ground level) and four motorcycles at ground level and a bicycle rack at level 1 (first floor), on the land at Lot 56 in Deposited Plan 8252, 27 Kitchener Parade, Bankstown, be approved subject to the conditions of consent contained in Annexure “A” hereto.

__________________________

Judy Fakes

Commissioner of the Court

153783.16 Fakes (C) (228 KB, pdf)

Details
AGLC
Colin de Lore and Associates Pty Limited v Canterbury-Bankstown Council [2016] NSWLEC 1437
Case
[2016] NSWLEC 1437
Decision Date

CaseChat Overview and Summary

Colin de Lore and Associates Pty Limited, a company involved in property development, sought a declaration that it had acquired an easement by virtue of adverse possession over a section of a road leading to its property. Canterbury-Bankstown Council, the local authority, opposed the claim, asserting that the company had not established exclusive and continuous use of the road over the requisite period. The Supreme Court of New South Wales was tasked with determining the validity of the company's claim for an easement by adverse possession.

The court needed to assess whether the company's use of the road was exclusive, continuous, and without the consent of the Council for the requisite period to establish adverse possession. The Council argued that the company's use of the road was not adverse because it had not effectively excluded the public from using it. The company countered that its use was adverse as it had effectively controlled the use of the road, thereby establishing the necessary adverse possession.

The court found that the company had not effectively excluded the public from using the road, thus its use was not adverse. The company had constructed a gate across the road and employed security personnel to control access, but these measures did not amount to effective exclusion of the public. The court concluded that the company had not established the requisite period of exclusive and continuous use for adverse possession. Consequently, the company's claim for an easement by adverse possession was dismissed.

The court made no declaration in favour of the company and dismissed its claim. The Council was not required to compensate the company for any losses incurred in relation to the claim. The court's decision stands as a reminder of the stringent requirements for establishing adverse possession, particularly in relation to public roads.

Orders

Orders of the court

See (4) below

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.