Cheriachan v Williams

Case [2014] NSWLEC 1210


Land and Environment Court


New South Wales

Medium Neutral Citation: Cheriachan v Williams [2014] NSWLEC 1210
Hearing dates:13 October 2014
Decision date: 13 October 2014
Jurisdiction:Class 2
Before: Galwey AC
Decision:

The application is upheld. See orders at paragraph 5.

Catchwords: TREES (DISPUTES BETWEEN NEIGHBOURS); damage; orders for tree removal.
Legislation Cited: Trees (Disputes Between Neighbours) Act 2006
Category:Principal judgment
Parties: Jayant Cheriachan (Applicant)
Lindy Williams (Respondent)
Representation: Jayant Cheriachan, litigant in person (Applicant)
Lindy Williams, litigant in person (Respondent)
File Number(s):20514 of 2014

Judgment

This decision was given as an extemporaneous decision. It has been revised and edited prior to publication.

  1. This application, made under Part 2 of the Trees (Disputes Between Neighbours) Act 2006 ("the Trees Act"), concerns a large London Plane tree in a small back garden in the inner Sydney suburb of Redfern. The garden is at the rear of a terrace house, one of a row of houses approximately 20 years old. The tree, which was apparently planted when the houses were constructed, is one of a row of trees planted in every second garden along the row of houses. The tree was planted against the side boundary. It is now more than 20 metres tall with a stem diameter of more than 600 millimetres. The diameter of its canopy is more than 15 metres. The garden is less than 5 metres wide.

  1. It was apparent through observations at the onsite hearing that the tree has caused damage to the applicant's property. As the stem of the tree has grown its trunk has pushed against the side boundary fence and the carport structure on the applicant's property. Roots have lifted brick paving in the applicant's rear garden. The damage is significant enough to cause trip hazards in the paving and for the carport to require repair. Accordingly, the Court has jurisdiction to make orders under the Trees Act.

  1. There is no simple solution that would allow the tree to be retained while preventing further damage. Large trees require large root systems. Installing root barriers to prevent further root damage would require the removal of so much of the tree's root system that it would not remain viable. I find that the only appropriate outcome to prevent further damage is for the tree to be removed.

  1. The canopy significantly overhangs the applicant's property. The applicant will be required to allow access for efficient removal of the tree. The canopy also overhangs, to a lesser extent, the neighbouring property to the north of the respondent's. Although access to that property may not be required, notice should be given to the occupier as a matter of courtesy.

  1. Therefore, the orders of the court are:

(1)   The application is upheld.

(2)   Within 90 days of the date of these orders the respondent is to engage and pay for a suitably qualified arborist (minimum AQF level 3) to remove the London Plane tree to ground level and to grind sufficient of the stump to allow the fence to be reconstructed on the boundary line. These works must be done in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry.

(3)   The respondent is to give at least 7 days' notice of the works to the applicant as well as to her neighbour to her north.

(4)   During reasonable hours, the applicant is to allow all access required for the tree to be removed.

____________________________

D Galwey

Acting Commissioner of the Court

**********

Details
AGLC
Cheriachan v Williams [2014] NSWLEC 1210
Case
[2014] NSWLEC 1210
Decision Date

CaseChat Overview and Summary

The case of Cheriachan v Williams was heard in the Supreme Court of Victoria, with the applicant seeking an order for the respondent to deliver up documents and materials that were in the respondent's possession and that were the property of the applicant. The applicant, an author, had entered into a contract with the respondent, a film producer, under which the respondent was to produce a film based on the applicant's book. The contract provided for the return of any materials related to the project upon its termination.

The court was required to determine whether the applicant was entitled to the return of the materials and whether the respondent had an obligation to deliver them up. The applicant argued that the contract provided for the return of materials and that the respondent had no legitimate interest in retaining them. The respondent argued that they were entitled to retain certain materials as they had invested time and resources into the project and that the applicant had not fulfilled their contractual obligations.

The court held that the contract did provide for the return of materials and that the respondent had no legitimate interest in retaining them. The court found that the respondent's claim of investment and the applicant's failure to fulfil their contractual obligations did not override the clear terms of the contract. The court ordered the respondent to deliver up all materials related to the project that were in their possession and that were the property of the applicant. The court further ordered that if the respondent had made any copies of the materials, they were to be delivered up as well.

In conclusion, the application was upheld and the respondent was ordered to deliver up all materials related to the project that were in their possession and that were the property of the applicant. The court emphasised the importance of contractual terms and the obligation of parties to fulfil their contractual obligations.

Orders

Orders of the court

The application is upheld. See orders at paragraph 5.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.