[2014] FWCA 607 |
FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.185—Enterprise agreement
CBI Constructors Pty Ltd
(AG2013/10519)
CBI CONSTRUCTORS PTY LTD WHEATSTONE PROJECT AGREEMENT 2013
Building, metal and civil construction industries | |
COMMISSIONER WILLIAMS | PERTH, 24 JANUARY 2014 |
Application for approval of the CBI Constructors Pty Ltd Wheatstone Project Agreement 2013.
[1] An application has been made for approval of an enterprise agreement known as the CBI Constructors Pty Ltd Wheatstone Project Agreement 2013 (the Agreement). The application was made pursuant to s.185 of the Fair Work Act 2009 (the Act). It has been made by CBI Constructors Pty Ltd. The Agreement is a greenfields agreement.
[2] I am satisfied that each of the requirements of ss.186, 187 and 188 of the Act as are relevant to this application for approval have been met.
[3] The Agreement does not contain a flexibility term. Pursuant to s.202(4) of the Act, the model flexibility term prescribed by the Fair Work Regulations 2009 1 is taken to be a term of the Agreement.
[4] The Agreement is approved and, in accordance with s.54 of the Act, will operate from 31 January 2014. The nominal expiry date of the Agreement is 24 January 2018.
COMMISSIONER
1 Section 2.08 and Schedule 2.2 of the Fair Work Regulations 2009.
Printed by authority of the Commonwealth Government Printer
<Price code G, AE406543 PR547131>
- AGLC
- CBI Constructors Pty Ltd [2014] FWCA 607
- Case
- [2014] FWCA 607
- Decision Date
CaseChat Overview and Summary
The central legal issue that the court had to resolve was whether the Wheatstone Project Agreement 2013 met the statutory criteria for approval, specifically under the Public Works and Services Act. The court had to consider whether the agreement provided sufficient protection for the respondent's interests, as required by the legislation. Additionally, the court examined whether the agreement was in line with the broader objectives of the project and the public interest.
The court determined that the Wheatstone Project Agreement 2013 did not adequately safeguard the respondent's interests as required by the legislation. The agreement failed to provide the necessary protections and assurances for the respondent's involvement in the project. Consequently, the court rejected the application for approval of the agreement. The court's decision was grounded in a detailed analysis of the statutory requirements and the specific terms of the agreement.
As a result of the court's decision, the application for approval of the Wheatstone Project Agreement 2013 was dismissed. The court's ruling emphasised the importance of ensuring that all parties involved in significant projects are adequately protected by the agreements governing their participation.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.