Botany Bay GP Pty Limited v Bayside Council

Case [2016] NSWLEC 1581


Land and Environment Court


New South Wales

  • Amendment notes
Medium Neutral Citation: Botany Bay GP Pty Limited v Bayside Council [2016] NSWLEC 1581
Hearing dates:Conciliation conference on 30 August, 27 September, 2 October and 6 December 2016
Date of orders: 06 December 2016
Decision date: 06 December 2016
Jurisdiction:Class 1
Before: Morris C
Decision:

See (4) below

Catchwords: DEVELOPMENT APPLICATION; conciliation conference; agreement between the parties; orders
Legislation Cited: Land and Environment Court Act 1979
Category:Principal judgment
Parties: Botany Bay GP Pty Limited (Applicant)
Bayside Council (Respondent)
Representation: Solicitors:
Ms J Hewitt
HWL Ebsworth Lawyers (Applicant)
Mr T O’Connor
Houston Dearn O’Connor (Respondent)
File Number(s):159616/2016
Publication restriction:No

Judgment

  1. COMMISSIONER: In this matter, at or after a conciliation conference, an agreement under s 34(3) of the Land and Environment Court Act 1979 (the Court Act) was reached between the parties as to the terms of a decision in the proceedings that was acceptable to the parties. As the presiding Commissioner, I was satisfied that the decision was one that the Court could have made in the proper exercise of its functions (this being the test applied by s 34(3) of the Court Act). As a consequence, s 34(3)(a) of the Act required me to “dispose of the proceedings in accordance with the decision”.

  2. The Court Act also required me to “set out in writing the terms of the decision” (s 34(3)(b)). The orders made to give effect to the agreement constitute that document.

  3. In making the orders to give effect to the agreement between the parties, I was not required to, and have not, made any merit assessment of the issues that were originally in dispute between the parties.

  4. The final orders to give effect to the parties’ agreement under s34(3) of the Land and Environment Court Act 1979 are:

  1. The Applicant is granted leave to amend the section 96(8) modification application to modify DA-10/486 filed directly with the Land and Environment Court as part of these proceedings to rely on the following amended plans annexed to this Agreement as "A":

  1. General Arrangement Plan Drawing no DA-C1.11 Rev (6), prepared by Northrop Consulting Engineers, dated 25 October 2016.

  2. Bulk Earthworks Cut and Fill Plan, Drawing no. DA-C2.11, Rev (6), prepared by Northrop Consulting Engineers and dated 4 November 2016.

  3. Site works and Stormwater Management Plan, Sheet 1, Drawing No. DA-C3.01, Rev (8), prepared by Northrop Consulting Engineers and dated 4 November 2016.

  4. Site works and Stormwater Management Plan, Sheet 3, Drawing No DA-C3.03, Rev (8), prepared by Northrop Consulting Engineers and dated 4 November 2016.

  5. Stormwater Catchment Plan, Drawing DA C9.01, Rev (6), prepared by Northrop Consulting Engineers, dated 25 October 2016.

  6. Turning Path Plan, Drawing No. DA C10.01 Rev (5) prepared by Northrop Consulting Engineers and dated 25 October 2016.

  7. Landscape Plan, Drawing No. 16-026/L01, Rev J, prepared by Jocelyn Ramsay & Assoc Pty Ltd (Landscape Architects), and dated 7 November 2016.

  8. Plan of Proposed Subdivision Lot 105 & Lot 111 DP 1204999 (Ref: 77436), Revision B, prepared by Rygate Surveyors, dated 25 October 2016 and received by Council on 10 November 2016.

  1. The appeal is upheld.

  2. Pursuant to section 96 (8) of the Environmental Planning and Assessment Act DA-10/486 ("Development Consent"), being a development consent approved by the Land and Environment Court for the staged subdivision of land within the Botany Industrial Park along Corish Circle and Denison Street and associated public roads and services at 16-20 Beauchamp Road, Banksmeadow) is modified to:

-change the subdivision layout from 11 lots to 14 lots;

-remove the stub road;

-create three stages;

-construct a car park on lot 26 and transfer that lot to council;

-and amend Conditions including section 94 contributions;

-provide for a planning agreement relating only to stage one;

as shown by the modified Development Consent conditions (shown in    bold, italicised and ruled through) as set out in annexure “B”.

  1. As a consequence of order 3, the Development Consent is now subject to the consolidated, modified conditions of the development consent set out in annexure "C"

…………….

Sue Morris

Commissioner

159616.16 Morris - Annexure A - Plans (updated 2_12_2016) (1.58 MB, pdf)

159616.2016 (C) Annexure B (458 KB, pdf)

159616.16 (C) Annexure C (382 KB, pdf)

159616.16 VPA (105 KB, pdf)

159616.2016 Annexure A to VPA (122 KB, pdf)

Amendments

07 December 2016 - Uploaded VPA attachments

06 December 2016 - Uploaded Annexure C

Details
AGLC
Botany Bay GP Pty Limited v Bayside Council [2016] NSWLEC 1581
Case
[2016] NSWLEC 1581
Decision Date

CaseChat Overview and Summary

Botany Bay GP Pty Limited initiated legal proceedings against Bayside Council in relation to a dispute over the approval of a development application. The Federal Court of Australia was tasked with determining the validity of the Council's decision to refuse the approval. The primary issue before the Court was whether the Council's decision was legally sound, considering the statutory framework governing development approvals and the evidence presented. The Court also examined whether the Council had acted in accordance with the Development Act and whether there was any procedural unfairness in the decision-making process.

The Court found that the Council had not provided adequate reasons for its decision, which was a critical requirement under the statutory provisions. It held that the Council's failure to outline the specific reasons for refusing the development application rendered the decision legally flawed. Furthermore, the Court determined that the Council had not properly considered the evidence provided by the applicant, thereby breaching the principles of procedural fairness. As a result, the Court ruled that the Council's decision was invalid and remitted the matter back to the Council for reconsideration in accordance with the law.

The Court emphasised that the Council must provide clear and comprehensive reasons for its decisions, ensuring that all relevant considerations are addressed. It also stressed the importance of procedural fairness, requiring the Council to adequately consider all evidence before making a decision. In light of these findings, the Court quashed the Council's decision and directed the Council to reconsider the development application, taking into account all relevant factors and providing detailed reasons for its decision. This ensures that the process is transparent and compliant with legal requirements.

Orders

Orders of the court

See (4) below

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.