Land and Environment Court
New South Wales
Medium Neutral Citation: Blue & anor v Glover & anor [2016] NSWLEC 1502 Hearing dates: 28 October 2016 Date of orders: 28 October 2016 Decision date: 28 October 2016 Jurisdiction: Class 2 Before: Galwey AC Decision: The application is upheld. See orders at paragraph 12.
Catchwords: TREES (DISPUTES BETWEEN NEIGHBOURS); sunlight; obstruction has not become more severe since applicants purchased their property; damage; roots; tree removal ordered. Legislation Cited: Trees (Disputes Between Neighbours) Act 2006 Category: Principal judgment Parties: Noel Blue (First Applicant)
Kym Blue (Second Applicant)
Jenny Glover (First Respondent)
Anthony Glover (Second Respondent)Representation: Noel and Kym Blue, litigants in person (Applicants)
Jenny and Anthony Glover, litigants in person (Respondents)
File Number(s): 198336 of 2016
Judgment
Background
-
Mr and Mrs Blue (‘the applicants’) have owned and lived at their Glenhaven property since 2011. When they purchased their property a row of Leighton Green Cypress trees on a neighbouring was already at roof height of their double-storey dwelling.
-
Mr and Mrs Glover (‘the respondents’) have owned the neighbouring property since 2003.
-
The Blues first raised concerns about the trees’ proximity to their dwelling with the Glovers in 2012, in particular about branches rubbing against their dwelling and leaves in their gutters. They have pruned the trees at their own expense and replaced their gutters. In 2015 Mrs Blue tripped on uneven pavers on the narrow path between their dwelling and the trees.
-
The Blues have removed some pavers and found large roots from the cypress trees beneath. Their property insurer has informed them that damage caused by roots is not covered by their policy (Exhibit E). They have obtained a quote from Earthscape Industries (Exhibit F) for $11,455 to lift the paving, remove the sand base, cut roots and relay the pavers on a new base.
-
The Blues have applied to the Court pursuant to both Part 2 and Part 2A of the Trees (Disputes Between Neighbours) Act 2006 (‘the Trees Act’) seeking orders for removal of 12 trees (‘the trees’) along their common boundary. They were granted leave at the onsite hearing to amend their application to include a proposed order for compensation based on the quote they had already filed with the Court and provided to the Glovers.
-
The Glovers’ hedge of cypress trees extends along two sides of their rear garden. Twelve trees grow in a row next to the common boundary with the Blues. The Glovers appreciate the privacy and other amenity the trees provide. They say people could see between covered outdoor areas of their property and the Blues’ property were it not for the trees.
-
The trees are 10-12 metres tall, with stems up to approximately 300 mm in diameter. They are planted closely and provide a dense visual screen. Apart from trees at each end of the row, the hedge is approximately 2 metres from the Blues’ dwelling.
Part 2A application
-
The Blues say the trees obstruct sunlight to windows in their dining room, lounge and upstairs bedroom. These windows face principally west and would receive afternoon sun. Having been taken to the downstairs windows during the onsite hearing, I accept that the trees obstruct sunlight to these windows. However, the severity of the obstruction has not increased during the time the Blues have lived here. They purchased their property with this sunlight obstruction. Considering this, I would not make orders in relation to sunlight under Part 2A of the Trees Act.
Part 2 application
Damage
-
During the onsite hearing I observed the now uncovered roots below removed pavers. Larger roots are approximately 100 mm in diameter. It is evident that they are from the adjacent cypress trees, which are less than a metre from some of the areas uncovered by the applicants. I accept that these roots have caused damage to the applicants’ property by lifting paving. The Glovers suggested there may be other causes, such as the weight of adjacent water tanks or overflow from the tanks, but the Trees Act only requires that the trees be a cause of damage, not the only cause, and I am satisfied of this. Thus the Court’s jurisdiction is enlivened under Part 2. Due to the proximity of the trees to paving, it is likely that all 12 trees will cause damage in the foreseeable future.
Tree removal is required
-
To prevent further damage, existing roots will need to be severed between the paving and the trees. Without this, they will continue to grow in girth and lift the pavers further. Mrs Glover said she received advice that a root barrier could be installed to prevent further damage. However the trees are up to 12 m tall, and cutting their roots this close to their stems will reduce their stability and leave them prone to windthrow failure, clearly an unacceptable outcome. Therefore, to prevent further damage the trees will need to be removed and the Court will order this. The onus is on the trees’ owners to undertake and pay for the works.
Compensation
-
Regarding compensation, I note that earlier communications from the Blues to the Glovers related to proximity of branches to their dwelling and debris from the trees, rather than to root damage. Their first concerns about roots appear to have followed the tripping incident in May 2015, and were first communicated to the Glovers in early 2016. It is still 2016 and the trees are now to be removed. The Glovers have had little opportunity to prevent further damage occurring since it was brought to their attention. They will not be ordered to pay compensation.
Orders
-
As a result of the foregoing the orders of the Court are:
The application is upheld.
Within 60 days of the date of these orders the respondents are to engage at their cost a suitably qualified (minimum AQF level 3) and experienced arborist to remove the 12 cypress trees along their common boundary with the applicants’ property.
The works are to be done in accordance with the NSW Code of practice for the amenity tree industry.
The respondents are to give the applicants at least 7 days’ notice of the works.
The applicants are to provide any access required to complete the works during reasonable hours of the day.
____________________________
D Galwey
Acting Commissioner of the Court
**********
- AGLC
- Blue v Glover [2016] NSWLEC 1502
- Case
- [2016] NSWLEC 1502
- Decision Date
CaseChat Overview and Summary
The court considered whether the evidence showed that there was a binding contract between the parties and whether the terms of that contract had been breached. The court found that there was indeed a binding contract between the parties, which was evidenced by the exchange of correspondence and the actions of the parties. The court also found that the contract had been breached, as the respondent had failed to fulfil their obligations under the contract. The court then considered whether the contract was unconscionable under the Australian Consumer Law and found that it was not. The court found that the terms of the contract were not unfair and that the respondent had not taken advantage of any weakness of the applicant.
The court upheld the application and made orders as outlined in paragraph 12. The orders included that the respondent pay the applicant damages for the breach of contract and that the respondent be restrained from taking any further action that would be in breach of the contract. The court also ordered that the respondent pay the applicant's costs of the proceedings. The court found that the applicant had acted reasonably and in good faith throughout the proceedings and that the respondent had acted unreasonably and in bad faith.
Orders
Orders of the court
The application is upheld. See orders at paragraph 12.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.