Bijok v S J Weir P/L
Case
•
[2011] SADC 20
•23 February 2011
Details
AGLC
Case
Decision Date
Bijok v S J Weir P/L [2011] SADC 20
[2011] SADC 20
23 February 2011
CaseChat Overview and Summary
The case of Bijok v S J Weir P/L involved the plaintiffs, Bijok, who claimed damages for subsidence caused to their land by the defendant's excavation activities. The defendant, S J Weir P/L, was a builder who excavated next to the plaintiffs' boundary without an adequate retaining structure, resulting in damage to the plaintiffs' buildings. The legal issues that the court had to address included whether the builder had constructed the retaining wall in accordance with the engineer's designs and whether the weight of the building on the plaintiffs' land caused the subsidence.
The court found that the builder had proceeded with an unpropped retaining structure in contravention of the engineer's design. The court accepted the evidence of Mr Vreugdenburg, an engineer, who stated that the carport section of the boundary was not propped before 2 August, which was in contravention of the engineer's design. The court found that the propping design was adequate after the subsidence props were installed and the excavation proceeded without further subsidence. The court also found that the builder was solely responsible for the subsidence under the Bijok’s land.
The court found that the plaintiffs were entitled to damages for the subsidence caused to their land. The court declined to award exemplary damages as it was unable to find that the builder acted in a manner that would give rise to such an award. The plaintiffs were awarded damages in the sum of $141,952, with interest on the judgment sum in the amount of $3,750.00. The defendant was ordered to pay the plaintiffs' costs of the action to be taxed or agreed.
The court found that the builder had proceeded with an unpropped retaining structure in contravention of the engineer's design. The court accepted the evidence of Mr Vreugdenburg, an engineer, who stated that the carport section of the boundary was not propped before 2 August, which was in contravention of the engineer's design. The court found that the propping design was adequate after the subsidence props were installed and the excavation proceeded without further subsidence. The court also found that the builder was solely responsible for the subsidence under the Bijok’s land.
The court found that the plaintiffs were entitled to damages for the subsidence caused to their land. The court declined to award exemplary damages as it was unable to find that the builder acted in a manner that would give rise to such an award. The plaintiffs were awarded damages in the sum of $141,952, with interest on the judgment sum in the amount of $3,750.00. The defendant was ordered to pay the plaintiffs' costs of the action to be taxed or agreed.
Details
Key Legal Topics
Areas of Law
-
Tort Law
Legal Concepts
-
Nuisance
-
Negligence
-
Contract Formation
Actions
Download as PDF
Download as Word Document
Citations
Bijok v S J Weir P/L [2011] SADC 20
Most Recent Citation
Walford Anglican School for Girls Incorporated v Romaldi Constructions Pty Ltd [2020] SADC 146
Cases Citing This Decision
16
Raedel v Shahin
[2019] SASCFC 141
Raedel v Shahin
[2019] SASCFC 141
SJ Weir Ltd v Bijok
[2011] SASCFC 165
Cases Cited
1
Statutory Material Cited
0
168 Wharf St Pty Ltd v Amstar Learning Pty Ltd
[2005] QCA 44
168 Wharf St Pty Ltd v Amstar Learning Pty Ltd
[2005] QCA 44